Residential / Group Housing · 2 buildings · 150 unitsRERA P52100005785

Mist Aqua

Deedo IDDP-PUN-TK3G

Completion was pushed back 2 years and 2 months to Oct 2020, and that date has passed too; no MahaRERA orders on record; 59% of its units are booked.

Gorhe Bk., Pune 411042 · Property rates in Gorhe Bk. · by Gm Promoters Llp

Delivery8 yrs 3 mo latePromised Aug 2018 · revised Oct 2020 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales59% booked89 of 150 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 2 years and 2 months to Oct 2020, and that date has passed too

  • This projectRegistered 14 Aug 2017, completion promised 31 Aug 2018, revised to 30 Oct 2020, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100005785
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210000578514 Aug 201731 Aug 201830 Oct 2020GM Promoters LLPProject page
Documents52

2 documents held by Deedo, 50 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardG_M_Promoters_Pan.pdf · uploaded 30 Jul 2017Source

Legal

  • Declaration Form BDeclaration - RERA-Aqua.pdf · uploaded 30 Jul 2017Source
  • Legal Title reportaqua title report.pdf · uploaded 31 Jul 2017Source
  • OtherCompletion Aqua BC.pdf · uploaded 11 Apr 2019Source

Migrated

  • 1 PAN CardG_M_Promoters_Pan.pdf · uploaded 30 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)Drawing 1 PRH NASR 1065 07 03 2015.pdf · uploaded 30 Jul 2017Source
Show all 52 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval (IOD)Drawing 1 PRH NASR 1065 07 03 2015.pdf · uploaded 30 Jul 2017Source
  • 2 Building Plan Approval (IOD)Drawing 2 PRH NASR 1065 07 03 2015.pdf · uploaded 30 Jul 2017Source
  • 3 Building Plan Approval (IOD)Drawing 3 PRH NASR 1065 07 03 2015.pdf · uploaded 30 Jul 2017Source
  • 4 Building Plan Approval (IOD)Drawing 4 PRH NASR 1065 07 03 2015.pdf · uploaded 30 Jul 2017Source
  • 5 Building Plan Approval (IOD)Drawing 5 PRH NASR 1065 07 03 2015.pdf · uploaded 30 Jul 2017Source
  • 6 Building Plan Approval (IOD)Drawing 6 PRH NASR 1065 07 03 2015.pdf · uploaded 30 Jul 2017Source
  • 7 Building Plan Approval (IOD)Drawing 7 PRH NASR 1065 07 03 2015.pdf · uploaded 30 Jul 2017Source
  • 8 Building Plan Approval (IOD)Drawing 8 PRH NASR 1065 07 03 2015.pdf · uploaded 30 Jul 2017Source
  • 9 Building Plan Approval (IOD)Drawing 9 PRH NASR 1065 07 03 2015.pdf · uploaded 30 Jul 2017Source
  • 10 Building Plan Approval (IOD)Drawing 10 PRH NASR 1065 07 03 2015.pdf · uploaded 30 Jul 2017Source
  • 11 Building Plan Approval (IOD)Drawing 11 PRH NASR 1065 07 03 2015.pdf · uploaded 30 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentN_A_120areAqua_.pdf · uploaded 30 Jul 2017Source
  • 1 Declaration in FORM BDeclaration - RERA-Aqua.pdf · uploaded 30 Jul 2017Source
  • 1 Proforma of Allotment letterAllotment letter - RERA-Aqua.pdf · uploaded 30 Jul 2017Source
  • 2 Proforma of Allotment letterAqua-agr-RERA.pdf · uploaded 30 Jul 2017Source
  • 1 Copy of the legal title reportaqua title report.pdf · uploaded 31 Jul 2017Source
  • 1 Details of encumbrancesaqua encumbrance.pdf · uploaded 31 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate Aqua BC.pdf · uploaded 31 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Cert Aqua B C.pdf · uploaded 31 Jul 2017Source
  • 1 Certificates of CA (Form 3)CA Cert MIST AQUA B C.pdf · uploaded 31 Jul 2017Source
  • 1 Certificates of CA (Form 5)Form 5 - Aqua BC.pdf · uploaded 30 Sep 2018Source
  • 1 OtherCompletion Aqua BC.pdf · uploaded 11 Apr 2019Source
  • 2 Certificates of CA (Form 5)MIST Aqua B C.PDF · uploaded 30 Sep 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)zMIST Aqua B C.PDF · uploaded 22 Nov 2019Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)zMIST Aqua B C.PDF · uploaded 26 Dec 2019Source
  • 3 Certificates of CA (Form 5)09Aqua BC.pdf · uploaded 29 Sep 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Mist Aqua A SIGNED.pdf · uploaded 30 Sep 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Mist Aqua.pdf · uploaded 30 Sep 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)2A Aqua 17-18 - Signed.pdf · uploaded 17 May 2024Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)2A Aqua 18-19 - Signed.pdf · uploaded 17 May 2024Source

Technical

  • DocumentDrawing 11 PRH NASR 1065 07 03 2015.pdf · uploaded 30 Jul 2017Source
  • DocumentDrawing 10 PRH NASR 1065 07 03 2015.pdf · uploaded 30 Jul 2017Source
  • DocumentDrawing 7 PRH NASR 1065 07 03 2015.pdf · uploaded 30 Jul 2017Source
  • DocumentDrawing 8 PRH NASR 1065 07 03 2015.pdf · uploaded 30 Jul 2017Source
  • DocumentDrawing 9 PRH NASR 1065 07 03 2015.pdf · uploaded 30 Jul 2017Source
  • DocumentDrawing 1 PRH NASR 1065 07 03 2015.pdf · uploaded 30 Jul 2017Source
  • DocumentDrawing 1 PRH NASR 1065 07 03 2015.pdf · uploaded 30 Jul 2017Source
  • DocumentDrawing 2 PRH NASR 1065 07 03 2015.pdf · uploaded 30 Jul 2017Source
  • DocumentDrawing 3 PRH NASR 1065 07 03 2015.pdf · uploaded 30 Jul 2017Source
  • DocumentDrawing 4 PRH NASR 1065 07 03 2015.pdf · uploaded 30 Jul 2017Source
  • DocumentDrawing 5 PRH NASR 1065 07 03 2015.pdf · uploaded 30 Jul 2017Source
  • DocumentDrawing 6 PRH NASR 1065 07 03 2015.pdf · uploaded 30 Jul 2017Source

Technical (Architect)

  • DocumentArchitect Certificate Aqua BC.pdf · uploaded 31 Jul 2017Source

Technical (Engineer)

  • DocumentEngineer Cert Aqua B C.pdf · uploaded 31 Jul 2017Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel S No 121

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK150 units in all
Address
S No 121PIN 411042
Village
Gorhe Bk., Haveli taluka
Land area for this project
7,157 sq m (77,036 sq ft)
Permissible built-up area
7,283 sq m (78,390 sq ft)
Sanctioned built-up area
6,458 sq m (69,509 sq ft)
Recreational open space
1,165 sq m (12,543 sq ft)
Designated bank account
28
Developed in phases
Yes

Survey, CTS, gat or plot numbers

S No 121

Land as published on MahaRERA's project page

S No 121

Boundaries

North
Road
South
Road and Boundry of Village Donje
East
Gat No 120
West
Gat No 121 Part

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking150 units

89 of 150 units booked (59%), as the promoter reported to MahaRERA

1BHK · 84 units2BHK · 66 units
BuildingTypeCarpet areaUnitsBooked
Aqua B1BHK29.53 sq m · 318 sq ft2118
Aqua B1BHK31.78 sq m · 342 sq ft119
Aqua B1BHK31.89 sq m · 343 sq ft109
Aqua B2BHK45.03 sq m · 485 sq ft106
Aqua B2BHK45.25 sq m · 487 sq ft10
Aqua B2BHK46.11 sq m · 496 sq ft119
Aqua B2BHK49.83 sq m · 536 sq ft116
Aqua C1BHK29.53 sq m · 318 sq ft2112
Show all 14 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Aqua C1BHK31.78 sq m · 342 sq ft117
Aqua C1BHK31.89 sq m · 343 sq ft106
Aqua C2BHK45.03 sq m · 485 sq ft102
Aqua C2BHK45.25 sq m · 487 sq ft10
Aqua C2BHK46.11 sq m · 496 sq ft113
Aqua C2BHK49.83 sq m · 536 sq ft112

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMr Vikas Achalkar—
Chartered accountantSiddharth Smart—
EngineerMahesh Mate—
EngineerMr Umesh Joshi—
Registered real estate agentSham Ramakant Yawatkar—

Source: MahaRERA project page. Contact details are not shown.