RERA projects in Mamurdi
28 projects under 30 MahaRERA registrations, registered 2021–2026. 57% have a completion date extended beyond the one promised.
Locality
28RERA projects
30Registrationssome projects hold several
20Completion still due10 past their completion date
4 monthsMedian extension beyond promised date57% of registrations extended
0Regulatory casesnone on MahaRERA's lists
73Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2021 | 4 |
| 2022 | 6 |
| 2023 | 7 |
| 2024 | 3 |
| 2025 | 3 |
| 2026 | 7 |
Projects in Mamurdi
28 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Austin IraYashada Shravani Group | PM1260002601545 | 13 Aug 2026 | 31 Dec 2031 | 31 Dec 2031 | Not yet due | 0 |
| Arohi SkylineShivkrupa Associates | PR1260002601521 | 11 Aug 2026 | 31 Dec 2029 | 31 Dec 2029 | Not yet due | 0 |
| Raajwada LegacySN Iconic Infratech | PM1260002601324 | 27 Jul 2026 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Rk AmorRk Infra & Real Estate-Mamurdi | PM1260002600597 | 1 Jun 2026 | 31 Mar 2030 | 31 Jul 2030 | Extended 4 mo | 0 |
| Jefro KingsfortJefro Realty LLP | PM1260002600286 | 28 Apr 2026 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| My Home SanctuaryMamurdi Developers LLP | PR1261012502725, PR1261012601727 | 12 Mar 2026 | 30 Jun 2032 | 30 Jun 2032 | Not yet due | 0 |
| Sai StellaM/s.Shree Sai Capstone | PM1260002500576 | 14 Aug 2025 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Lotus FlorinaLotus Florina | P52100080893 | 1 Aug 2025 | 30 Jun 2026 | 30 Jun 2026 | Promised date passed | 0 |
| Mahalaxmi HeightsMahalaxmi Associates | P52100078120 | 25 Nov 2024 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| Yashada DreamsongYashada Vivanta Realty Pvt. Ltd. | P52100078168 | 25 Nov 2024 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Emerald HeightsSwayambhu Properties | P52100076861 | 3 Jul 2024 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Life Canvas Phase 2Vighnaharta Reality | P52100053517 | 8 Nov 2023 | 30 Jun 2027 | 30 Oct 2027 | Extended 4 mo | 0 |
| Meriton HeightsRBS Builder & Developers | P52100053019 | 10 Oct 2023 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Millennium AmaraMillennium Developers | P52100052838, PR1261012500899 | 5 Oct 2023 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Shilp ShantivanEcho Stone Buildcon | P52100052197 | 31 Jul 2023 | 30 Jun 2028 | 30 Oct 2028 | Extended 4 mo | 0 |
| Shree ApartmentS R Developers | P52100051723 | 27 Jun 2023 | 31 Dec 2025 | 31 Dec 2025 | Promised date passed | 0 |
| Shree Ganesha HeightsSiddhivinayak Enterprises | P52100049450 | 14 Feb 2023 | 31 Mar 2026 | 31 Mar 2026 | Promised date passed | 0 |
| Sparkle At Godrej SereneGodrej Skyline Developers Limited | P52100048467 | 3 Jan 2023 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Shree HeightsV R Buildcon | P52100048290 | 22 Dec 2022 | 31 Dec 2025 | 31 Dec 2025 | Promised date passed | 0 |
| EkaantShree Balaji Associates | P52100047560 | 9 Nov 2022 | 31 Jan 2027 | 31 Dec 2025 | Not yet due | 0 |
| Godrej SereneGodrej Skyline Developers Limited | P52100047405 | 27 Oct 2022 | 30 Jun 2027 | 30 Oct 2027 | Extended 4 mo | 0 |
| Swami Samarth HeightsSwami Samarth Developers | P52100046268 | 20 Jun 2022 | 5 May 2024 | 5 May 2024 | Promised date passed | 0 |
| Diamond 1Usman Hasan Shaikh | P52100045259 | 10 May 2022 | 31 Dec 2024 | 30 Dec 2025 | Extended 12 mo | 0 |
| Sai PlanetJsk Associates | P52100032486 | 10 Jan 2022 | 31 Dec 2025 | 31 Dec 2025 | Promised date passed | 0 |
| Kedar ResidencySubhagya Promoters & Builders Pvt Ltd | P52100032109 | 14 Dec 2021 | 31 Dec 2026 | 31 Dec 2026 | Not yet due | 0 |
Other localities in Haveli
Most active promoters
By projects registered here, as named on MahaRERA.
- Godrej Skyline Developers Limited2 projects
- Vighnaharta Reality2 projects
- Echo Stone Buildcon1 project
- Jefro Realty LLP1 project
- Jsk Associates1 project
- Lotus Florina1 project
- Mahalaxmi Associates1 project
- Mamurdi Developers LLP1 project
- Millennium Developers1 project
- M/s.Shree Sai Capstone1 project
Data through15 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology