Diamond 1
Deedo IDDP-PUN-VJRWCompletion was pushed back 1 year to Dec 2025, and that date has passed too; no MahaRERA orders on record; 21% of its units are booked.
Mamurdi, Pune 412101 · by Usman Hasan Shaikh
Buying a flat here?
See every deed registered on it.
Completion was pushed back 1 year to Dec 2025, and that date has passed too
- This projectRegistered 10 May 2022, completion promised 31 Dec 2024, revised to 30 Dec 2025, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100045259
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100045259 | 10 May 2022 | 31 Dec 2024 | 30 Dec 2025 | Usman Hasan Shaikh | Project page |
Documents153
3 documents held by Deedo, 150 filings listed on MahaRERA's project page
Other
- OtherDate not statedView
Finance
- PAN Cardpan usman.pdf · uploaded 13 Jan 2022Source
Legal
Migrated
- 1 PAN Cardpan usman.pdf · uploaded 13 Jan 2022Source
Show all 153 documentsShow fewer documents
Migrated
- 1 Details of encumbrancesencumbrance letter.pdf · uploaded 13 Jan 2022Source
- 1 Declaration about Commencement Certificatecircular 32.pdf · uploaded 13 Jan 2022Source
- 1 Declaration in FORM Busman form B.pdf · uploaded 13 Jan 2022Source
- 1 Proforma of Allotment letterallotment letter.pdf · uploaded 13 Jan 2022Source
- 2 Proforma of Allotment letterdraft ats.pdf · uploaded 17 Jan 2022Source
- 1 Copy of Layout Approval (in case of layout)layout plan.pdf · uploaded 1 Feb 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentsheet 2.pdf · uploaded 1 Feb 2022Source
- 2 Building Plan Approval / NA Order for plotted developmentsheet 3.pdf · uploaded 1 Feb 2022Source
- 1 CERSAI detailsCERSAI_Search_Report_200229298653_For_Asset_Based_Search_01_02_2022_18_35_41_326.pdf · uploaded 1 Feb 2022Source
- 1 Copy of the legal title reportUsman Shaikh Search Report 07-Apr-2022 14-38-21_compressed.pdf · uploaded 8 Apr 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentcommencement certificate final.pdf · uploaded 25 Apr 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 25 Apr 2022Source
- 1 Declaration in FORM BForm B Final.pdf · uploaded 21 Oct 2024Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)_Disclosure RERA Bank.pdf · uploaded 11 Nov 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of interest.pdf · uploaded 11 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1.pdf · uploaded 21 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1NEW.pdf · uploaded 21 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1NEW.pdf · uploaded 21 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1NEW.pdf · uploaded 21 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1NEW.pdf · uploaded 21 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1NEW.pdf · uploaded 21 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1NEW.pdf · uploaded 21 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1NEW.pdf · uploaded 21 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1NEW.pdf · uploaded 21 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 21 Nov 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 21 Nov 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Final Form 2.pdf · uploaded 21 Nov 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 (1).pdf · uploaded 21 Nov 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 (2).pdf · uploaded 21 Nov 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 (1).pdf · uploaded 21 Nov 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 (2).pdf · uploaded 21 Nov 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 (1).pdf · uploaded 21 Nov 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 (2).pdf · uploaded 21 Nov 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FinalForm 2.pdf · uploaded 21 Nov 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Final Form 2 (1).pdf · uploaded 21 Nov 2024Source
- 1 Disclosure of sold/ booked inventorysoldcircular.pdf · uploaded 21 Nov 2024View
- 1 Disclosure of sold/ booked inventorysoldcircular.pdf · uploaded 21 Nov 2024View
- 1 Disclosure of sold/ booked inventorysoldcircular.pdf · uploaded 21 Nov 2024View
- 1 Disclosure of sold/ booked inventorysoldcircular.pdf · uploaded 21 Nov 2024View
- 1 Disclosure of sold/ booked inventorysoldcircular.pdf · uploaded 21 Nov 2024View
- 1 Disclosure of sold/ booked inventorysoldcircular.pdf · uploaded 21 Nov 2024View
- 1 Disclosure of sold/ booked inventorysoldcircular.pdf · uploaded 21 Nov 2024View
- 1 Disclosure of sold/ booked inventorysoldcircular.pdf · uploaded 21 Nov 2024View
- 1 Disclosure of sold/ booked inventorysoldcircular.pdf · uploaded 21 Nov 2024View
- 1 Disclosure of sold/ booked inventorysoldcircular.pdf · uploaded 21 Nov 2024View
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 21 Nov 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 21 Nov 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 21 Nov 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 21 Nov 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 21 Nov 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 21 Nov 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 21 Nov 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 21 Nov 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3 (1).pdf · uploaded 21 Nov 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 21 Nov 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 21 Nov 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 21 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1.pdf · uploaded 21 Nov 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1NEW.pdf · uploaded 21 Nov 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1NEW.pdf · uploaded 21 Nov 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1NEW.pdf · uploaded 21 Nov 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1NEW.pdf · uploaded 21 Nov 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1NEW.pdf · uploaded 21 Nov 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1NEW.pdf · uploaded 21 Nov 2024Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1NEW.pdf · uploaded 21 Nov 2024Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1NEW.pdf · uploaded 21 Nov 2024Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 21 Nov 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 21 Nov 2024Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 21 Nov 2024Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3 (1).pdf · uploaded 21 Nov 2024Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 21 Nov 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 21 Nov 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 21 Nov 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 21 Nov 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 21 Nov 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 21 Nov 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 21 Nov 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 (2).pdf · uploaded 21 Nov 2024Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Final Form 2 (1).pdf · uploaded 21 Nov 2024Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)FinalForm 2.pdf · uploaded 21 Nov 2024Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 (2).pdf · uploaded 21 Nov 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 (1).pdf · uploaded 21 Nov 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 (1).pdf · uploaded 21 Nov 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 (1).pdf · uploaded 21 Nov 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Final Form 2.pdf · uploaded 21 Nov 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 21 Nov 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 (2).pdf · uploaded 21 Nov 2024Source
- 7 Disclosure of sold/ booked inventorysoldcircular.pdf · uploaded 21 Nov 2024View
- 10 Disclosure of sold/ booked inventorysoldcircular.pdf · uploaded 21 Nov 2024View
- 9 Disclosure of sold/ booked inventorysoldcircular.pdf · uploaded 21 Nov 2024View
- 8 Disclosure of sold/ booked inventorysoldcircular.pdf · uploaded 21 Nov 2024View
- 6 Disclosure of sold/ booked inventorysoldcircular.pdf · uploaded 21 Nov 2024View
- 5 Disclosure of sold/ booked inventorysoldcircular.pdf · uploaded 21 Nov 2024View
- 4 Disclosure of sold/ booked inventorysoldcircular.pdf · uploaded 21 Nov 2024View
- 3 Disclosure of sold/ booked inventorysoldcircular.pdf · uploaded 21 Nov 2024View
- 2 Disclosure of sold/ booked inventorysoldcircular.pdf · uploaded 21 Nov 2024View
- 1 Disclosure of sold/ booked inventorysoldcircular.pdf · uploaded 21 Nov 2024View
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 21 Nov 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 21 Nov 2024Source
- 1 CERSAI detailsFinal Doc CERSAI.pdf · uploaded 6 Dec 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 FY 22-23.pdf · uploaded 6 Dec 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 FY 23-24.pdf · uploaded 6 Dec 2024Source
Technical
Technical (Architect)
- DocumentFORM1.pdf · uploaded 21 Nov 2024Source
- DocumentFORM1NEW.pdf · uploaded 21 Nov 2024Source
- DocumentFORM1NEW.pdf · uploaded 21 Nov 2024Source
- DocumentFORM1NEW.pdf · uploaded 21 Nov 2024Source
- DocumentFORM1NEW.pdf · uploaded 21 Nov 2024Source
- DocumentFORM1NEW.pdf · uploaded 21 Nov 2024Source
- DocumentFORM1NEW.pdf · uploaded 21 Nov 2024Source
- DocumentFORM1NEW.pdf · uploaded 21 Nov 2024Source
- DocumentFORM1NEW.pdf · uploaded 21 Nov 2024Source
- DocumentForm 1.pdf · uploaded 21 Nov 2024Source
- DocumentFORM1.pdf · uploaded 21 Nov 2024Source
- DocumentFORM1NEW.pdf · uploaded 21 Nov 2024Source
- DocumentFORM1NEW.pdf · uploaded 21 Nov 2024Source
- DocumentFORM1NEW.pdf · uploaded 21 Nov 2024Source
- DocumentFORM1NEW.pdf · uploaded 21 Nov 2024Source
- DocumentFORM1NEW.pdf · uploaded 21 Nov 2024Source
- DocumentFORM1NEW.pdf · uploaded 21 Nov 2024Source
- DocumentFORM1NEW.pdf · uploaded 21 Nov 2024Source
- DocumentFORM1NEW.pdf · uploaded 21 Nov 2024Source
- DocumentForm 1.pdf · uploaded 21 Nov 2024Source
Technical (Engineer)
- DocumentForm 2.pdf · uploaded 21 Nov 2024Source
- DocumentFinal Form 2.pdf · uploaded 21 Nov 2024Source
- DocumentForm 2 (1).pdf · uploaded 21 Nov 2024Source
- DocumentForm 2 (2).pdf · uploaded 21 Nov 2024Source
- DocumentForm 2 (1).pdf · uploaded 21 Nov 2024Source
- DocumentForm 2 (2).pdf · uploaded 21 Nov 2024Source
- DocumentForm 2 (1).pdf · uploaded 21 Nov 2024Source
- DocumentForm 2 (2).pdf · uploaded 21 Nov 2024Source
- DocumentFinalForm 2.pdf · uploaded 21 Nov 2024Source
- DocumentFinal Form 2 (1).pdf · uploaded 21 Nov 2024Source
- DocumentForm 2.pdf · uploaded 21 Nov 2024Source
- DocumentFinal Form 2.pdf · uploaded 21 Nov 2024Source
- DocumentForm 2 (1).pdf · uploaded 21 Nov 2024Source
- DocumentForm 2 (2).pdf · uploaded 21 Nov 2024Source
- DocumentForm 2 (1).pdf · uploaded 21 Nov 2024Source
- DocumentForm 2 (2).pdf · uploaded 21 Nov 2024Source
- DocumentForm 2 (1).pdf · uploaded 21 Nov 2024Source
- DocumentForm 2 (2).pdf · uploaded 21 Nov 2024Source
- DocumentFinalForm 2.pdf · uploaded 21 Nov 2024Source
- DocumentFinal Form 2 (1).pdf · uploaded 21 Nov 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 15/1/1/2 p 17/1 b
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK28 units in all
- Address
- 15/1/1/2 p 17/1 b, MAMURDI, MAMURDIPIN 412101
- Village
- Mamurdi, Haveli taluka
- Location
- 18.67369, 73.71812
- Land area for this project
- 848 sq m (9,128 sq ft)
- Permissible built-up area
- 1,866 sq m (20,082 sq ft)
- Sanctioned built-up area
- 1,493 sq m (16,065 sq ft)
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
15/1/1/2 p 17/1 b
Boundaries
- North
- Property Of Forest Hill Society
- South
- Road
- East
- Property Of Sunil Gavai
- West
- Property Of Mr Anarse
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking28 units
6 of 28 units booked (21%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 23.44 sq m · 252 sq ft | 1 | 0 |
| 1BHK | 32.5 sq m · 350 sq ft | 4 | 1 |
| 1BHK | 33.88 sq m · 365 sq ft | 1 | 0 |
| 1BHK | 35.79 sq m · 385 sq ft | 1 | 0 |
| 1BHK | 35.8 sq m · 385 sq ft | 4 | 2 |
| 1BHK | 37.37 sq m · 402 sq ft | 8 | 1 |
| 1BHK | 37.92 sq m · 408 sq ft | 4 | 1 |
| 1BHK | 39.37 sq m · 424 sq ft | 1 | 0 |
| 2BHK | 50.56 sq m · 544 sq ft | 4 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Nk Associates | — |
| Chartered accountant | Ymk And Associates | — |
| Engineer | Asif Mursal | — |
| Other | Ymk And Associates | — |
Source: MahaRERA project page. Contact details are not shown.