RERA projects in Sasvad (M Cl)

56 projects under 57 MahaRERA registrations, registered 2017–2026. 14% have a completion date extended beyond the one promised.

Locality
56RERA projects
57Registrationssome projects hold several
22Completion still due35 past their completion date
12 monthsMedian extension beyond promised date14% of registrations extended
0Regulatory casesnone on MahaRERA's lists
5Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201713
20184
20193
20206
20214
20223
202310
20246
20255
20263

Projects in Sasvad (M Cl)

56 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Vrundavan ViharNamdev Damodar KhenatPM126000260171431 Aug 202630 Apr 2030—Not yet due0
Moraya ViharJay Sadguru BuildersPR126000260007815 Apr 202631 Mar 2029—Not yet due0
Bhairavi TranquilityBhairavi BuildersPM126000250221730 Jan 202625 Dec 2028—Not yet due0
Balaji ParadiseShri Balaji DevelopersPR126000250135230 Oct 202531 Dec 2030—Not yet due0
Shree Sai SahwasAnuradha Landline And Housing DevelopersPR126000250075611 Sep 202531 Dec 2030—Not yet due0
Prestige PlatinumThe Prestige GroupPM12600025004471 Aug 202531 Jan 2030—Not yet due0
Narayan BaugHbcl InfraP5210007923918 Feb 202531 Oct 2028—Not yet due0
Sangameshwar GoldSable Sanjivani Saswad Infrastructure LLPP521000786641 Jan 202515 May 2025—Promised date passed0
Jp TowerJp BuildconP5210007859427 Dec 202431 May 2027—Not yet due0
Central Park Wing-AAditya BuildconP5210007848817 Dec 202431 Dec 2029—Not yet due0
Moraya VastuVedant BuildersP5210005505526 Feb 202431 Dec 202431 Dec 2025Extended 12 mo0
KP HeritageK P AssociatesP5210005483915 Feb 202431 Dec 2026—Not yet due0
Morya ParkGajdant Constructions LLPP5210005483715 Feb 202431 Dec 2027—Not yet due0
Shree Ganesh PalaceShree Ganesh DevelopersP521000546482 Feb 202430 Dec 2028—Not yet due0
Krishna ResidencyDream Sakruti DevelopersP5210005410327 Dec 202331 Jul 2025—Promised date passed0
N B OnyxGanesh AssociatesP5210005361210 Nov 202331 Dec 2026—Not yet due0
Anand Baug C WingSankalp DevelopersP521000528485 Oct 202331 Dec 2026—Not yet due0
Bhairavnath ComplexJ P BuildconsP5210005160327 Jun 202321 Apr 2025—Promised date passed0
Venkatesh Little HeartSanjay Dnyanoba JagtapP5210005141914 Jun 202331 Dec 2028—Not yet due0
Karha VastuS J DevelopersP521000507773 May 202321 Nov 2026—Not yet due0
Laxmidatta HeightsDeepak Dattatraya TakaleP5210005075228 Apr 20231 Jan 2026—Promised date passed0
Kanishka Grand PlazaPlatinum Lifespace DevelopersP5210004977424 Feb 202331 Dec 2026—Not yet due0
Mayureshwar HeightsAkshay Balaso KamtheP5210004961922 Feb 202331 May 2025—Promised date passed0
Prathamesh HeightsKrishna DevelopersP5210004870112 Jan 202331 Dec 2027—Not yet due0
Sangameshwar Villa PlottingSable Sanjivani Saswad Infrastructure LLPP5210004615020 Jun 202231 Mar 2023—Promised date passed0
Shree Sai DattaAbhijit Madhukar JagtapP5210003394014 Mar 202230 Dec 2027—Not yet due0
Venkatesh Nandanvan A WingSanjay Dnyanoba JagtapP5210003274924 Jan 202231 Dec 2026—Not yet due0
Zurange ComplexDattatraya Maruti ZurangeP5210003100929 Sep 202131 Aug 202331 Mar 2024Extended 7 mo0
Vishwa Laxmi ResidencySantosh Ramchandra JagtapP5210003013431 Jul 202130 Dec 2024—Promised date passed0
Smartnest RoyaleSmart Nest PropertiesP521000295374 Jun 202131 Dec 2022—Promised date passed0
Purandhar GoldSupriya Sanjay WadekarP521000281476 Feb 202131 Dec 202831 Dec 2028Not yet due0
Vrundavan HeritageKanha PropertiesP5210002768431 Dec 202030 Mar 2027—Not yet due0
Om Ganesh CornerJai Ganesh DevelopersP5210002723725 Nov 202030 Jun 2024—Promised date passed0
Gokul HeightAudumbar DevelopersP521000269023 Nov 202030 Jun 2022—Promised date passed0
NB CoralGanesh AssociatesP5210002653630 Sep 202030 Sep 2023—Promised date passed0
Udyam Biz CasaKadu Properties LLPP5210002623130 Aug 202030 Jun 202430 Sep 2024Extended 3 mo0
Kanha ViharSamarthrealitiesP5210002467328 Feb 202030 Dec 2022—Promised date passed0
NandanvanNitin Govind SableP5210002273316 Oct 20195 Oct 2019—Promised date passed0
Sangameshwar Phase ASable Sanjivani Saswad Infrastructure LLPP5210002244824 Sep 201931 Dec 202215 Sep 2023Extended 9 mo0
Karha GoldKhara ConstructionP5210002050118 Apr 20191 Apr 2023—Promised date passed0
Pandhare HeightsSantosh Vijay PandhareP5210001699428 Jun 201830 Mar 2022—Promised date passed0
Savali Towersavali developersP521000159279 Apr 201820 Dec 2019—Promised date passed0
N B ParadiseGanesh AssociatesP5210001504122 Jan 201830 Dec 2021—Promised date passed0
ShivyogShiv DeveopersP521000147942 Jan 201830 May 2023—Promised date passed0
Vrundaavan HeightsKrushnai DevelopersP5210001327921 Sep 201730 Mar 20237 May 2025Extended 26 mo0
Grand OrchidShree Siddhivinayak Construction GroupP5210001170731 Aug 20171 Sep 201928 Feb 2021Extended 17 mo0
Venkatesh Nandanvan C WingSanjay Dnyanoba JagtapP5210001176831 Aug 201730 Mar 2021—Promised date passed0
Vishwa LaxmiSantosh Ramchandra JagtapP5210001051831 Aug 20177 Jul 2019—Promised date passed0
Anand Baug Building DSankalp DevelopersP5210001029624 Aug 201731 Dec 2018—Promised date passed0
Morya HeightsEkdant Construction And DevelopersP5210000945622 Aug 201731 Dec 2018—Promised date passed0
Venkatesh Nandanvan D WingSanjay Dnyanoba JagtapP5210000971222 Aug 201730 Mar 2021—Promised date passed0
VedantShree Siddhivinayak Construction GroupP521000051199 Aug 201731 Dec 201931 Jul 2022Extended 31 mo0
Samrudhee MalharSamrudhee HomesP521000028664 Aug 201731 Dec 201831 Dec 2019Extended 12 mo0
Sahara PearlSahara BuildconP521000025511 Aug 201725 Dec 2019—Promised date passed0
Jay ResidencyJay ConstructionsP5210000142428 Jul 201731 Jul 2018—Promised date passed0
SwapnanagariSanjay Dnyanoba JagtapP52100001447, P5210000279128 Jul 201730 Dec 2022—Promised date passed0

Other localities in Purandhar

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Sanjay Dnyanoba Jagtap5 projects
  2. Ganesh Associates3 projects
  3. Sable Sanjivani Saswad Infrastructure LLP3 projects
  4. Sankalp Developers2 projects
  5. Santosh Ramchandra Jagtap2 projects
  6. Shree Siddhivinayak Construction Group2 projects
  7. Abhijit Madhukar Jagtap1 project
  8. Aditya Buildcon1 project
  9. Akshay Balaso Kamthe1 project
  10. Anuradha Landline And Housing Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology