Bhivari, Pune
Deedo IDDL-PUN-BHIVARI10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects2
Registrations2
Completion still due11 past their date
Median extension8 months100% of registrations extended
Regulatory cases0none on MahaRERA's lists
10 in 10 registrations run late here
2 MahaRERA registrations in Bhivari
1 extended, not yet due1 past even the latest date
Extended registrations moved their completion date by a median of 8 months.
Projects in Bhivari
2 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Shubharambh HeightsShubharambh Towers | Due Jan 2029, extended 4 mo | — | 5% |
| Shubharambha TowersShubharambha Towers | Completed, extended 11 mo | — | 44% |
Nearby: other villages in Purandhar
Most active promoters
- Shubharambha Towers1 project
- Shubharambh Towers1 project
Bhivari, in questions
How many projects in Bhivari run late?
10 in 10 MahaRERA registrations (2 of 2): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Bhivari by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology