Delayed projects in Maharashtra
8,417 MahaRERA projects in 36 districts are past their promised completion date, and MahaRERA shows no completion for them.
Most overdue first
Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 79 of 169.
| Project | Locality | Promised | Revised | Delivery |
|---|---|---|---|---|
| Shivaalik ParkSun Realtors | Bhiwandi (M Corp.)Thane | Dec 2023 | Dec 2025 | 2 yrs 11 mo late |
| Shivaraj ResidencyRanjit Dinkar Shinde | VanvaswadiSatara | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| ShivohamShiv Sai Constructions | WahalRaigarh | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Shivom EnclaveMegaj Realtors Private Limited | AndheriMumbai Suburban | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Shree Ganesh KrupaKeshav Hasha Madhavi | PanvelRaigarh | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Shree Ram ParkShree Ram Infra | VichumbeRaigarh | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Shree Sai JalaramG H Co | UlaweRaigarh | Dec 2023 | Dec 2024 | 2 yrs 11 mo late |
| Shree Sai SadanM.r.builders And Developers | Palghar | Dec 2023 | Dec 2025 | 2 yrs 11 mo late |
| Shri Puja Chs LimitedPrimespace Realty Group | Pune (M Corp.)Pune | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Shrimant YogiNilesh Kailasrao Jedhe | JalochiPune | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Shrisai HeightsVishwashri Developers | Kodoli (Ct)Satara | Dec 2023 | Aug 2025 | 2 yrs 11 mo late |
| Shrushti HeightsShrushti Developers | Pune (M Corp.)Pune | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Shubh Nilaya Phase IIShubh Realtors | LohgaonPune | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Shubham Galaxy - B WingNavkar Associates | DombivliThane | Dec 2023 | Mar 2024 | 2 yrs 11 mo late |
| Shubham Nagari - Sadguru Krupa Apt.plot No.5,6,7Shubham Infrastructure | Oras Bk.Sindhudurg | Dec 2023 | — | 2 yrs 11 mo late |
| Siddham HeightsBhoopendra Ghisulal Borana | Mirabhayandar (M Corp.)Thane | Dec 2023 | Dec 2025 | 2 yrs 11 mo late |
| Silver SpringsVision Developers | Sidhanathwadi (Rural)Satara | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Sitai ResidencyTouch Stone Property Builders And Developers | Aurangabad (M Corp.)Aurangabad | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| SivantaShiv Sai Constructions | WahalRaigarh | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Sky TowerRajyog Realtors | BorivaliMumbai Suburban | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Smriti HeightsSmriti Developer | VirarPalghar | Dec 2023 | Dec 2025 | 2 yrs 11 mo late |
| Space CornerSpace Enterprise | TargharRaigarh | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Spring Village 1 Affordable HousingPansare Infratech | TandulwadiPune | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Star PlazaStar Construction & Developers | ShringartaliRatnagiri | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Star Residency 1Starwood Developers Limited | VarangadePalghar | Dec 2023 | Dec 2025 | 2 yrs 11 mo late |
| Sun PalmsSun Corp | VarsoliPune | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Surabhi IconicaSurabhi Ventures | Nanekarwadi (Ct)Pune | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Suvela ApartmentsFengse Brothers | Karve NagarPune | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Suyojit Viridian VallisSun Infrastructures Pvt Ltd | Nashik | Dec 2023 | — | 2 yrs 11 mo late |
| Swami SankulSairam Developers | Sadashiv PethPune | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| SwapnapurtiSwapnapurti Housing | Karanje Tarf Satara (Ct)Satara | Dec 2023 | Dec 2024 | 2 yrs 11 mo late |
| SwarnimEss Gee Tradefin Pvt Ltd | BokadviraRaigarh | Dec 2023 | Dec 2024 | 2 yrs 11 mo late |
| Sai JivdaniHemanshu Bharat Kapadia | BolinjPalghar | Dec 2023 | Dec 2025 | 2 yrs 11 mo late |
| Sai ShraddhaP.b. Enterprises | Vadghar (Ct)Raigarh | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Samruddhi SnehSamruddhi Landmarks | KivalePune | Dec 2023 | Nov 2024 | 2 yrs 11 mo late |
| Sateri Legacy B Wing Phase I- 2nd and above floorsBindra Sateri Constructions | AndheriMumbai Suburban | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Sheltrex Smart Phone city ProjectSheltrex Karjat Pvt. Ltd. | KarjatRaigarh | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| ShivkrupaShivkrupa Developers | Ambarnath(M Cl)Thane | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Shree Kakasheth Telavane SadanMauli Construction | MurbadThane | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Shree Nivas ParkSiddhivinayak Tejas Associates | Pune (Cb)Pune | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Shree ResidencyDelta Buildcon | ChikhaliPune | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Shubh AtikaRavi Developments | Mirabhayandar (M Corp.)Thane | Dec 2023 | Dec 2024 | 2 yrs 11 mo late |
| Shubham Nagari -Samarth Krupa Apt. Plot No.04Shubham Infrastructure | Oras Bk.Sindhudurg | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Shubham Trident - Sundew, Sunrise and SunglowShubham Homes and Contractors Pvt. Ltd. | KurlaMumbai Suburban | Dec 2023 | Dec 2024 | 2 yrs 11 mo late |
| Siddh AmaraSiddh Housing | Bavdhan Kh.Pune | Dec 2023 | Jul 2024 | 2 yrs 11 mo late |
| Star ResidencyBramhachaitanya Developers through Proprietor Guruprasad Madhukar Vaidya | Satara | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Sukhsagar NagarSkyline Enterprises | Jamkhed (Ct)Ahmednagar | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Sukhwani HighlandsV.r.sukhwani Projects | SusPune | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Suvastu PrathamSavastu Buildcon | WarjePune | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Suzain AppartmentS N Developers | MamdapurRaigarh | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
Delayed projects by district
Pune · 2,215Thane · 1,158Raigarh · 1,042Mumbai Suburban · 994Nashik · 481Palghar · 362Nagpur · 323Aurangabad · 243Mumbai City · 242Satara · 228Ratnagiri · 192Sangli · 176Solapur · 155Kolhapur · 131Amravati · 72Sindhudurg · 72Ahmednagar · 69Chandrapur · 39Jalgaon · 39Latur · 28Akola · 23Beed · 21Nanded · 18Dhule · 17Wardha · 16Buldana · 14Jalna · 12Parbhani · 9Bhandara · 8Yavatmal · 6
SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology