9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects38
Registrations39some projects hold several
Completion still due1524 past their date
Median extension4 months41% of registrations extended
Regulatory cases1on 1 project

9 in 10 registrations run late here

39 MahaRERA registrations in Sadashiv Peth

5 not yet due10 extended, not yet due24 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Sadashiv Peth

38 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Anika EleganceArun Sheth PropertiesDue Apr 2029, extended 4 mo——
GulmoharRama Erande and AssociatesDue Feb 2030, extended 4 mo——
The CapitalMz DevelopersDue Apr 2028, extended 4 mo——
LaxminiwasShubhankar Kalpak Builders Private LimitedDue Dec 2028, extended 4 mo——
ImperiaAtharva BuildersDue Apr 2029——
All 38 projects →
Sadashiv Peth market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Archway Properties3 projects
  2. A And D Construction1 project
  3. Abhivruddhi Housing Llp1 project
  4. Akshay Group1 project
  5. Akshay Properties1 project
  6. Arun Sheth Properties1 project
  7. Ashainfra1 project
  8. Atharva Builders1 project
  9. Avadhoot Constructions1 project
  10. Chinchore Khinvasara Associates Llp1 project

Sadashiv Peth, in questions

How many projects in Sadashiv Peth run late?

9 in 10 MahaRERA registrations (34 of 39): their completion date was extended or has passed, data through 6 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Sadashiv Peth by Deedo. Medians on fewer than 3 deeds are not shown.

Data through6 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology