Skip to content
Residential / Group Housing · 5 buildings · 47 unitsRERA P99000021578

Star Residency 1

Deedo IDDP-PAL-C7EM

Completion was pushed back 2 years to Dec 2025, and that date has passed too; no MahaRERA orders on record; 15% of its units are booked.

Varangade, Palghar 401501 · by Starwood Developers Limited

Delivery2 yrs 11 mo latePromised Dec 2023 · revised Dec 2025 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales15% booked7 of 47 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 2 years to Dec 2025, and that date has passed too

  • This projectRegistered 9 Jul 2019, completion promised 30 Dec 2023, revised to 31 Dec 2025, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

5 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP99000021578
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P990000215789 Jul 201930 Dec 202331 Dec 2025Starwood Developers LimitedProject page
Documents74

3 documents held by Deedo, 71 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardSTARWOOD Pan Card.pdf · uploaded 2 Jul 2019Source
  • Other – Financefinance letter.pdf · uploaded 19 Apr 2023Source

Legal

  • Legal Title reportTITLE CERTIFICATE.pdf · uploaded 2 Jul 2019Source
  • Declaration Form BForm B Promoter.pdf · uploaded 6 Jul 2019Source
  • OtherJoint declaration G 2.pdf · uploaded 24 Nov 2020Source
Show all 74 documentsShow fewer documents

Legal

  • Declaration Form BFORM B.pdf · uploaded 26 Jan 2024Source

Migrated

  • 1 PAN CardSTARWOOD Pan Card.pdf · uploaded 2 Jul 2019Source
  • 1 Copy of the legal title reportTITLE CERTIFICATE.pdf · uploaded 2 Jul 2019Source
  • 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 2 Jul 2019Source
  • 1 Building Plan Approval (IOD)Type_3 Final.pdf · uploaded 2 Jul 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC - NA.pdf · uploaded 2 Jul 2019Source
  • 1 Proforma of Allotment letterSTAR RESIDENCY 1 DRAFT AGREEMENT.pdf · uploaded 2 Jul 2019Source
  • 2 Proforma of Allotment letterDRAFT ALLOTMENT LETTER.pdf · uploaded 2 Jul 2019Source
  • 1 Details of encumbrancesSELF DECLARATION OF ENCUMBERANCE.pdf · uploaded 6 Jul 2019Source
  • 1 Declaration in FORM BForm B Promoter.pdf · uploaded 6 Jul 2019Source
  • 1 Certificates of CA (Form 3)FORM 3 BUILDING NO 4 fi.pdf · uploaded 6 Jul 2019Source
  • 1 OtherJoint declaration G 2.pdf · uploaded 24 Nov 2020Source
  • 2 Copy of Layout Approval (in case of layout)Project Layout.pdf · uploaded 14 Aug 2021Source
  • 2 Building Plan Approval (IOD)Bld 4 Layout Plan.pdf · uploaded 14 Aug 2021Source
  • 1 Declaration about Commencement CertificateFORMAT D - CC Decleration- Bldg 4.pdf · uploaded 14 Aug 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - Architech Certificate.pdf · uploaded 14 Aug 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Quality Assurance 2021.pdf · uploaded 14 Aug 2021Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Quality Assurance 2020.pdf · uploaded 14 Aug 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Quality Assurance 2021.pdf · uploaded 14 Aug 2021Source
  • 1 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD - UNSOLD INVENTORY - BLDG 4.pdf · uploaded 14 Aug 2021Source
  • 2 Certificates of CA (Form 3)CA BLD 4.pdf · uploaded 14 Aug 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM-5 BLDG 04.pdf · uploaded 14 Aug 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM-5 BLDG 04.pdf · uploaded 14 Aug 2021Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 15 Aug 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 starresidency 1.pdf · uploaded 15 Aug 2021Source
  • 2 Declaration about Commencement CertificateDECLARATION OF CC.pdf · uploaded 3 Dec 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5.pdf · uploaded 3 Dec 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBANK LETTER.pdf · uploaded 3 Dec 2022Source
  • 1 Deviation Report with respect to Allotment letterNO DEVIATION ALLOTMENT.pdf · uploaded 3 Dec 2022Source
  • 1 Deviation Report with respect to model copy of AgreementNO DEVIATION AGREEMENT.pdf · uploaded 3 Dec 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 5 Dec 2022Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 5 Dec 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A.pdf · uploaded 5 Dec 2022Source
  • 2 Disclosure of sold/ booked inventorySOLD_UNSOLD_merged.pdf · uploaded 10 Dec 2022Source
  • 3 Certificates of CA (Form 3)CA RAHUL STARWOOD.pdf · uploaded 22 Feb 2023Source
  • 3 Declaration about Commencement Certificatedcc star 1.pdf · uploaded 19 Apr 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 star recidency 1 bldg no 4.pdf · uploaded 19 Apr 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 19 Apr 2023Source
  • 1 Disclosure of Interest in Other Real Estate Organizationsannexure a final.pdf · uploaded 19 Apr 2023Source
  • 2 Deviation Report with respect to Allotment letterno deviation allotment.pdf · uploaded 19 Apr 2023Source
  • 2 Deviation Report with respect to model copy of Agreementno deviation agreement.pdf · uploaded 19 Apr 2023Source
  • 1 Other – Financefinance letter.pdf · uploaded 19 Apr 2023Source
  • 3 Disclosure of sold/ booked inventoryilovepdf_merged (8).pdf · uploaded 12 May 2023Source
  • 4 Certificates of CA (Form 3)FORM 3 - CA CERTIFICATE EXCEL VERSION - 10-05-2023.pdf · uploaded 22 Dec 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch.pdf · uploaded 18 Jan 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng.pdf · uploaded 18 Jan 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 18 Jan 2024Source
  • 4 Disclosure of sold/ booked inventorySOLD UNSOLD FINAL.pdf · uploaded 18 Jan 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)STARWOOD CERTIFICATE .pdf · uploaded 18 Jan 2024Source
  • 2 Declaration in FORM BFORM B.pdf · uploaded 26 Jan 2024Source
  • 5 Certificates of CA (Form 3)CA 2601.pdf · uploaded 26 Jan 2024Source
  • Form 1Form 01 March 2025.pdf · uploaded 3 Sep 2025Source
  • Form 2Form 02 March 2025.pdf · uploaded 3 Sep 2025Source
  • Form 3Form 03 March 2025.pdf · uploaded 3 Sep 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold March 2025.pdf · uploaded 3 Sep 2025View
  • Form 1FORM 1.pdf · uploaded 25 Sep 2025Source
  • Form 2FORM 2.pdf · uploaded 25 Sep 2025Source
  • Form 3FORM 3.pdf · uploaded 25 Sep 2025Source
  • Disclosure of Sold and Booked InventorySOLD AND UNSOLD.pdf · uploaded 25 Sep 2025View
  • Form 2A (FY 2024-2025)FORM 2A.pdf · uploaded 25 Sep 2025Source

Technical

  • DocumentType_3 Final.pdf · uploaded 2 Jul 2019Source
  • DocumentLayout.pdf · uploaded 2 Jul 2019Source
  • DocumentProject Layout.pdf · uploaded 14 Aug 2021Source
  • DocumentBld 4 Layout Plan.pdf · uploaded 14 Aug 2021Source

Technical (Architect)

  • DocumentArch.pdf · uploaded 18 Jan 2024Source

Technical (Engineer)

  • DocumentEng.pdf · uploaded 18 Jan 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, Shop47 units in all
Address
101/1pt, 142/1pt, Varangade Road, Boisar EastPIN 401501
Village
varangade, Palghar taluka
Land area for this project
904 sq m (9,727 sq ft)
Permissible built-up area
1,868 sq m (20,107 sq ft)
Sanctioned built-up area
1,868 sq m (20,107 sq ft)
Designated bank account
85
Developed in phases
No

Land as published on MahaRERA's project page

101/1PT, 142/1PT

Boundaries

North
B No 5
South
S No 101pt
East
Road
West
Open Space

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking47 units

7 of 47 units booked (15%), as the promoter reported to MahaRERA

1BHK · 37 unitsShop · 10 units
TypeCarpet areaUnitsBooked
1BHK26.67 sq m · 287 sq ft377
Shop13.48 sq m · 145 sq ft10
Shop13.48 sq m · 145 sq ft10
Shop15.53 sq m · 167 sq ft10
Shop17.29 sq m · 186 sq ft20
Shop17.29 sq m · 186 sq ft20
Shop23.44 sq m · 252 sq ft10
Shop23.47 sq m · 253 sq ft20

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMorph Design Studio—
EngineerVishnu Jadhav—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Varangade

All 8 projects in Varangade · Compare Star Residency 1 with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology