RERA projects in Varangade

6 projects under 6 MahaRERA registrations, registered 2017–2023. 67% have a completion date extended beyond the one promised.

Locality
6RERA projects
6Registrations
2Completion still due4 past their completion date
48 monthsMedian extension beyond promised date67% of registrations extended
0Regulatory casesnone on MahaRERA's lists
14Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20173
20181
20191
20200
20210
20220
20231

Projects in Varangade

6 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Narendra EnclaveBrijeshkumar Narendra SinghP9900005270022 Sep 202331 May 202630 Sep 2026Extended 4 mo0
Narendra ParadiseBrijeshkumar Narendra SinghP9900002142628 Jun 20198 Jul 20228 Jul 2022Promised date passed0
Avani HillviewAvani hill ViewP9900001827922 Oct 201830 Dec 202230 Dec 2022Promised date passed0
Dharti ComplexDharti BuildwellP990000124961 Sep 201730 Jun 202131 Dec 2025Extended 54 mo0
Avani ResidencyAvani ResidencyP9900000626314 Aug 201730 Dec 202131 Dec 2026Extended 60 mo0
Spring FieldM/S. Shyam Sagar DevelopersP990000042509 Aug 201730 Dec 202330 Jun 2027Extended 42 mo0

Other localities in Palghar

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Brijeshkumar Narendra Singh2 projects
  2. Avani hill View1 project
  3. Avani Residency1 project
  4. Dharti Buildwell1 project
  5. M/S. Shyam Sagar Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology