RERA projects in Saravali
18 projects under 19 MahaRERA registrations, registered 2017–2026. 53% have a completion date extended beyond the one promised.
Locality
18RERA projects
19Registrationssome projects hold several
11Completion still due8 past their completion date
4 monthsMedian extension beyond promised date53% of registrations extended
0Regulatory casesnone on MahaRERA's lists
64Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 7 |
| 2018 | 1 |
| 2019 | 3 |
| 2020 | 0 |
| 2021 | 0 |
| 2022 | 2 |
| 2023 | 2 |
| 2024 | 1 |
| 2025 | 2 |
| 2026 | 1 |
Projects in Saravali
18 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Sai Shraddha ApartmentSai Mauli Infra Vision LLP | PM1240002601925 | 15 Sep 2026 | 31 Dec 2029 | 31 Dec 2029 | Not yet due | 0 |
| Kinjal BlissKinjal Homes | PR1240002500161 | 30 Jun 2025 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Vithu ApartmentPandurang Developers | P99000079583 | 17 Mar 2025 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Saravali ClassicMaverick Builders And Developers | P99000055349 | 18 Mar 2024 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Sai Nath ApartmentSai Mauli Developers | P99000049382 | 7 Feb 2023 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Sai Ram ApartmentSai Mauli Developers | P99000049165 | 3 Feb 2023 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Mauli ApartmentPandurang Developers | P99000047313 | 19 Oct 2022 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Shivom ApartmentShreenath Construction | P99000046849 | 14 Sep 2022 | 31 Dec 2030 | 31 Dec 2030 | Not yet due | 0 |
| Hari Om MatoshreeHari Om Enterprise | P99000020549 | 22 Apr 2019 | 30 Mar 2025 | 30 Mar 2025 | Promised date passed | 0 |
| PandurangparkChaitanya Builders & Developers | P99000020314 | 5 Apr 2019 | 30 Jun 2026 | 30 Oct 2026 | Extended 4 mo | 0 |
| Mahavir NiwasRajesh Enterprises | P99000017806, P99000021942 | 17 Sep 2018 | 30 Jun 2022 | 30 Jun 2022 | Promised date passed | 0 |
| Siddhivinayak ComplexSugandhi Realtors | P99000011924 | 1 Sep 2017 | 30 Dec 2023 | 31 Dec 2026 | Extended 36 mo | 0 |
| TulipMahalaxmi Infra | P99000012111 | 1 Sep 2017 | 31 Jul 2019 | 31 Jul 2019 | Promised date passed | 0 |
| Pragati TulipPragati Corporation | P99000011793 | 31 Aug 2017 | 31 May 2019 | 30 Nov 2020 | Extended 18 mo | 0 |
| JasminMahalaxmi Infra | P99000009167 | 19 Aug 2017 | 31 Jan 2021 | 31 Jan 2021 | Promised date passed | 0 |
| Shadawal Impression Building C1 C2Kailash Builders | P99000008322 | 18 Aug 2017 | 30 Dec 2018 | 30 Dec 2018 | Promised date passed | 0 |
| Sunrise Apt.Paradise Developers | P99000008059 | 18 Aug 2017 | 11 Dec 2019 | 12 Dec 2026 | Extended 84 mo | 0 |
| Mahavir Krupa DRajesh Construction | P99000000244 | 10 Jul 2017 | 31 Dec 2017 | 31 Dec 2017 | Promised date passed | 0 |
Other localities in Palghar
Most active promoters
By projects registered here, as named on MahaRERA.
- Mahalaxmi Infra2 projects
- Pandurang Developers2 projects
- Sai Mauli Developers2 projects
- Chaitanya Builders & Developers1 project
- Hari Om Enterprise1 project
- Kailash Builders1 project
- Kinjal Homes1 project
- Maverick Builders And Developers1 project
- Paradise Developers1 project
- Pragati Corporation1 project
Data through18 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology