Skip to content

Vithu Apartment

Certificate Signed

Saravali, Palghar 401501 |Promoter: Pandurang Developers

Residential / Group HousingRERAP99000079583
17 Mar 2025Registered with MahaRERA
31 Dec 2030Promised completion
30 Apr 2031Revised completionPushed back 4 months
2Buildings
47Units registered0 booked (0%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
2
Unit types
1BHK, LANDOWNER 1BHK, LANDOWNER 1RK47 units in all
Address
139/4, Saravali, SaravaliPIN 401501
Designated bank account
227
Developed in phases
Yes

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
17 Mar 2025
Promised
31 Dec 2030
Revised
30 Apr 2031

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P9900007958317 Mar 202531 Dec 203030 Apr 2031Pandurang DevelopersProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Building No 1 Wing A727
Building No 1 Wing B620

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 of 47 units booked (0%), as the promoter reported to MahaRERA

1BHK · 28 unitsLANDOWNER 1BHK · 18 unitsLANDOWNER 1RK · 1 unit
BuildingTypeCarpet areaUnitsBooked
Building No 1 Wing A1BHK29.77 sq m · 320 sq ft80
Building No 1 Wing ALANDOWNER 1BHK29.77 sq m · 320 sq ft180
Building No 1 Wing ALANDOWNER 1RK22.34 sq m · 240 sq ft10
Building No 1 Wing B1BHK48.57 sq m · 523 sq ft200

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 62 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Card1 PAN Card (1).pdf · uploaded 30 Jan 2025Source

Legal

  • Legal Title reportLegal Title Report ( 139-4).pdf · uploaded 30 Jan 2025Source
  • Declaration Form BFORM B O 500.pdf · uploaded 8 Mar 2025Source
  • Other – LegalCC Issued by collector Palghar at village Saravali ser no 139_4Area 2980sq MTR order date 1March 2024.pdf · uploaded 11 Mar 2025Source
  • Other – LegalGmail - CC Issued by collector Palghar at village Saravali ser no 139_4Area 2980sq MTR order date 1March 2024.pdf · uploaded 11 Mar 2025Source

Migrated

  • 1 PAN Card1 PAN Card (1).pdf · uploaded 30 Jan 2025Source
  • 1 Copy of the legal title reportLegal Title Report ( 139-4).pdf · uploaded 30 Jan 2025Source
Show all 63 documentsShow fewer documents

Migrated

  • 1 a Details of encumbrances concerned to FinanceLOE-FINANCE.pdf · uploaded 30 Jan 2025Source
  • 2 a Details of encumbrances concerned to FinanceLOE-LEGAL.pdf · uploaded 30 Jan 2025Source
  • 1 Proforma of Allotment letterALLOTMENT.pdf · uploaded 30 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 30 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 30 Jan 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC LATEST.pdf · uploaded 30 Jan 2025Source
  • 1 CERSAI detailsCERSAI.pdf · uploaded 30 Jan 2025Source
  • 1 b Details of encumbrances concerned to LegalLOE-FINANCE.pdf · uploaded 30 Jan 2025Source
  • 2 b Details of encumbrances concerned to LegalLOE-LEGAL.pdf · uploaded 30 Jan 2025Source
  • 1 Proforma of Agreement for saleAFS.pdf · uploaded 30 Jan 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INT.pdf · uploaded 30 Jan 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDISCLOSURE OF FINANCE AVAILED.pdf · uploaded 30 Jan 2025Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)FORMAT-A BANK.pdf · uploaded 31 Jan 2025Source
  • 1 Deviation Report with respect to Allotment letterDEVIATION-ALLOTMENT.pdf · uploaded 31 Jan 2025Source
  • 1 Deviation Report with respect to model copy of AgreementDEVIATION-AGREEMENT.pdf · uploaded 31 Jan 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)FORMAT B.pdf · uploaded 31 Jan 2025Source
  • 1 Copy of Layout Approval (in case of layout)1-4_compressed.pdf · uploaded 3 Feb 2025Source
  • 1 Building Plan Approval / NA Order for plotted development2-4_compressed.pdf · uploaded 3 Feb 2025Source
  • 2 Building Plan Approval / NA Order for plotted development3-4_compressed.pdf · uploaded 3 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 13 Feb 2025Source
  • 1 Declaration in FORM BFORM B O 500.pdf · uploaded 8 Mar 2025Source
  • 1 Declaration about Commencement Certificateform d revised.pdf · uploaded 8 Mar 2025Source
  • 2 Declaration about all RERA Designated Bank Accounts (Format A)landowner bank ac declaration REVISED.pdf · uploaded 8 Mar 2025Source
  • 1 Other – Technical50-2024.pdf · uploaded 8 Mar 2025Source
  • 1 Other – LegalCC Issued by collector Palghar at village Saravali ser no 139_4Area 2980sq MTR order date 1March 2024.pdf · uploaded 11 Mar 2025Source
  • 2 Other – LegalGmail - CC Issued by collector Palghar at village Saravali ser no 139_4Area 2980sq MTR order date 1March 2024.pdf · uploaded 11 Mar 2025Source
  • 2 Other – TechnicalCC Issued by collector Palghar at village Saravali ser no 139_4Area 2980sq MTR order date 1March 2024.pdf · uploaded 11 Mar 2025Source
  • 3 Other – TechnicalGmail - CC Issued by collector Palghar at village Saravali ser no 139_4Area 2980sq MTR order date 1March 2024.pdf · uploaded 11 Mar 2025Source
  • Form 1FORM 1.pdf · uploaded 10 Apr 2026Source
  • Form 2FORM 2.pdf · uploaded 10 Apr 2026Source
  • Form 3FORM 3.pdf · uploaded 10 Apr 2026Source
  • Disclosure of Sold and Booked InventoryFORM 3.pdf · uploaded 10 Apr 2026Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 22 Apr 2026Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 22 Apr 2026Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 22 Apr 2026Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 22 Apr 2026Source
  • Withdrawal Update Form 2Form 2 Vithu Apartment.pdf · uploaded 22 Apr 2026Source
  • Withdrawal Update Form 2Form 2 Vithu Apartment.pdf · uploaded 22 Apr 2026Source
  • Withdrawal Update Form 3FORM 3.pdf · uploaded 22 Apr 2026Source
  • Withdrawal Update Form 3FORM 3 NOV 2025.pdf · uploaded 22 Apr 2026Source
  • Withdrawal Update Form 3FORM 3 DEC 2025.pdf · uploaded 22 Apr 2026Source
  • Withdrawal Update Form 1Vithu Apartment Form I.pdf · uploaded 23 Apr 2026Source
  • Withdrawal Update Form 2Vithu Apartment Form II.pdf · uploaded 23 Apr 2026Source
  • Withdrawal Update Form 3form 3 mar 26.pdf · uploaded 23 Apr 2026Source
  • Withdrawal Update Form 1Vithu Apartment Form 1.pdf · uploaded 11 Aug 2026Source
  • Withdrawal Update Form 2Vithu Apartment Form 2.pdf · uploaded 11 Aug 2026Source
  • Withdrawal Update Form 3Form 3 JULY 26.pdf · uploaded 11 Aug 2026Source

Technical

  • Document1-4_compressed.pdf · uploaded 3 Feb 2025Source
  • Document2-4_compressed.pdf · uploaded 3 Feb 2025Source
  • Document3-4_compressed.pdf · uploaded 3 Feb 2025Source
  • Other – Technical50-2024.pdf · uploaded 8 Mar 2025Source
  • Other – TechnicalCC Issued by collector Palghar at village Saravali ser no 139_4Area 2980sq MTR order date 1March 2024.pdf · uploaded 11 Mar 2025Source
  • Other – TechnicalGmail - CC Issued by collector Palghar at village Saravali ser no 139_4Area 2980sq MTR order date 1March 2024.pdf · uploaded 11 Mar 2025Source

Technical (Architect)

  • DocumentVithu Apartment Form 1.pdf · uploaded 8 Aug 2026Source

Technical (Engineer)

  • DocumentVithu Apartment Form 2.pdf · uploaded 8 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Saravali, Palghar taluka

Survey, CTS, gat or plot numbers

139/4

Boundaries

North
Building
South
Road
East
Building
West
Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectA P Associates—
Chartered accountantAshwin Nair—
EngineerVinay Kania—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology