Skip to content
Deedo home
Menu

RERA projects in Dhansar

29 projects under 29 MahaRERA registrations, registered 2017–2026. 28% have a completion date extended beyond the one promised.

29RERA projects
29Registrations
21Completion still due8 past their completion date
39 monthsMedian extension beyond promised date28% of registrations extended
0Regulatory casesnone on MahaRERA's lists
21Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20172
20181
20195
20205
20211
20220
20232
20243
20258
20262

Projects in Dhansar

29 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Mayank Height Type 2cCity Space DevelopersPM12400026011139 Jul 202631 Dec 2031—Not yet due0
Royal PalacesUnited Aasraa RealtyPR124000250287717 Mar 202631 Dec 2029—Not yet due0
Shree Dayaram Residency 1fParshiv Builders & DevelopersPR12400025016663 Dec 202531 Dec 2029—Not yet due0
Mayank HeightsShree Dayaram HomesPR124000250159827 Nov 202531 Dec 2030—Not yet due0
Shree Dayaram Residency 1eCity Space DevelopersPR124000250030017 Jul 202531 Dec 2029—Not yet due0
Dayaram Residency Building No 1cShree Dayaram ConstructionP990000807787 Jul 202531 Dec 2028—Not yet due0
Indraprasth VillasGurukrupa InfraP990000804515 Jun 202531 Mar 2030—Not yet due0
Shree Salasar Row VillasRadha Krishna RealtyP990000804203 Jun 202531 Jan 2028—Not yet due0
Shree Salasar Row VillasDilip EnterprisesP990000801946 May 202531 Dec 2029—Not yet due0
Dayaram ResidencyRajeshwar HousingP9900007972621 Mar 202531 May 2028—Not yet due0
Royal Residency - Building No 2aZoya Build Homes LLPP9900006649711 Jun 202431 Dec 2026—Not yet due0
Fair Township Building No 1Om Value HomesP990000556184 Apr 202431 Dec 2026—Not yet due0
Santosh ApartmentFuture Star ConstructionP9900005497821 Feb 202431 Dec 2028—Not yet due0
Anant DivyaAnanta DevelopersP9900005150323 Jun 202331 Dec 2027—Not yet due0
Highness HomesOm Jai Kavish RealtorsP990000491903 Feb 202331 Dec 2028—Not yet due0
Ishi HomesIshi Developers Pvt LtdP9900003115911 Oct 202131 Dec 202431 Dec 2025Extended 12 mo0
New EraCrystal RealtyP9900002524723 Mar 202030 Dec 2026—Not yet due0
Star KwalityEarth Builder & DevelopersP990000247152 Mar 202029 Aug 2024—Promised date passed0
Sapphire Enclaves Bldg No 5 Type FPushpa Vijay GholapP9900002443413 Feb 202030 Jun 2027—Not yet due0
Star Roshan - A WingStar Roshan BuildersP9900002439611 Feb 202030 Dec 2023—Promised date passed0
New Rajendra Nagar, Balaji Residency 3,4Balaji InfraP990000243345 Feb 202030 Dec 202431 Dec 2029Extended 60 mo0
Star Roshan City Building No-5 Wing GManibhadraa Parivar InfraprojectsP9900002114110 Jun 201930 May 202331 Dec 2026Extended 43 mo0
Star Roshan City Building No-6 Wing IM/s Sumaira EnterprisesP9900002114710 Jun 201930 May 202331 Dec 2026Extended 43 mo0
New Rajendra Nagar- Shyam EnclaveShree Shyam DevlopersP9900002111031 May 201930 Dec 202431 Dec 2025Extended 12 mo0
New Rajendra NagarAmit Suresh SharmaP9900001944030 Jan 201930 Dec 202430 Sep 2025Extended 9 mo0
Sarkar HomesSarkar RealtyP9900001924314 Jan 201930 Dec 2022—Promised date passed0
Green ParkM/S Sai Siddhi DevelopersP990000170234 Jul 201830 Dec 202231 Dec 2026Extended 48 mo0
Shyam Regency Phase 2Shree Balaji RealtyP990000124521 Sep 201731 Jan 201930 Dec 2021Extended 35 mo0
Shyam RegencyShobha RelatorsP9900000797418 Aug 201730 May 2023—Promised date passed0

Other localities in Palghar

Most active promoters

By projects registered here, as named on MahaRERA.

  1. City Space Developers2 projects
  2. Amit Suresh Sharma1 project
  3. Ananta Developers1 project
  4. Balaji Infra1 project
  5. Crystal Realty1 project
  6. Dilip Enterprises1 project
  7. Earth Builder & Developers1 project
  8. Future Star Construction1 project
  9. Gurukrupa Infra1 project
  10. Ishi Developers Pvt Ltd1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology