RERA projects in Dongare
12 projects under 17 MahaRERA registrations, registered 2017–2026. 65% have a completion date extended beyond the one promised.
12RERA projects
17Registrationssome projects hold several
3Completion still due14 past their completion date
12 monthsMedian extension beyond promised date65% of registrations extended
0Regulatory casesnone on MahaRERA's lists
4Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 3 |
| 2018 | 4 |
| 2019 | 5 |
| 2020 | 3 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 0 |
| 2024 | 0 |
| 2025 | 1 |
| 2026 | 1 |
Projects in Dongare
12 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Cosmos Serenity Phase-IICosmos Prime Projects Ltd | PM1241012502317 | 10 Feb 2026 | 31 Mar 2031 | — | Not yet due | 0 |
| Pristine TowersParikh Bachraj Developers LLP | PM1240002500755 | 11 Sep 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Evershine Amavi 303 Phase 1Evershine Developers | P99000024780 | 5 Mar 2020 | 30 Dec 2023 | 29 Dec 2024 | Extended 12 mo | 0 |
| Evershine AmaviEvershine Developers | P99000024753, P99000024860 | 2 Mar 2020 | 30 Dec 2024 | 30 Dec 2025 | Extended 12 mo | 0 |
| Rustomjee Virar Avenue L1-L2 and L4 Wing GKeystone Infrastructure Private Limited | P99000020273 | 31 Mar 2019 | 28 Feb 2023 | 28 Feb 2024 | Extended 12 mo | 0 |
| Rustomjee Virar Avenue L1-L2 and L4 Wing I J and RetailKeystone Infrastructure Private Limited | P99000020216 | 29 Mar 2019 | 30 Sep 2023 | 31 Dec 2025 | Extended 27 mo | 0 |
| Rustomjee Virar Avenue L1 L2 And L4Keystone Infrastructure Private Limited | P99000018622, P99000018694, P99000020234 +2 | 22 Nov 2018 | 30 Sep 2023 | 31 Dec 2025 | Extended 27 mo | 0 |
| Rustomjee Virar Avenue D1 Wing A And Wing B And Retail BuildingKeystone Infrastructure Private Limited | P99000018043 | 10 Oct 2018 | 30 Dec 2021 | — | Promised date passed | 0 |
| Redbricks - Wing ARedbricks Landmark LLP | P99000017877 | 24 Sep 2018 | 30 Dec 2023 | — | Promised date passed | 0 |
| Bharat ArcadePankaj Chauhan | P99000013206 | 21 Sep 2017 | 31 Mar 2027 | — | Not yet due | 0 |
| Sumit Greendale NXSumit Pragati Shelters LLP | P99000004678 | 9 Aug 2017 | 31 Mar 2018 | 30 Apr 2019 | Extended 13 mo | 0 |
| Brooklyn ParkChandiwala Enterprises | P99000002745 | 4 Aug 2017 | 10 Jul 2025 | — | Promised date passed | 0 |
Other localities in Palghar
Most active promoters
By projects registered here, as named on MahaRERA.
- Keystone Infrastructure Private Limited4 projects
- Evershine Developers2 projects
- Chandiwala Enterprises1 project
- Cosmos Prime Projects Ltd1 project
- Pankaj Chauhan1 project
- Parikh Bachraj Developers LLP1 project
- Redbricks Landmark LLP1 project
- Sumit Pragati Shelters LLP1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology