15 projects under 16 MahaRERA registrations, registered 2017–2026. 69% have a completion date extended beyond the one promised.
Locality
15RERA projects
16Registrationssome projects hold several
6Completion still due10 past their completion date
4 monthsMedian extension beyond promised date69% of registrations extended
2Regulatory caseson 2 projects
33Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 6 |
| 2018 | 1 |
| 2019 | 1 |
| 2020 | 0 |
| 2021 | 0 |
| 2022 | 2 |
| 2023 | 0 |
| 2024 | 1 |
| 2025 | 4 |
| 2026 | 1 |
Projects in Saphale
15 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Parivar Ashish GalaxyParivar Ashish Developers | PR1240002502722 | 12 Mar 2026 | 30 Jun 2029 | 30 Oct 2029 | Extended 4 mo | 0 |
| Jivdani HeightsJivdani Developers | PR1240002501645 | 2 Dec 2025 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Gavkar ParadiseKunjraj Enterprises | P99000080717 | 27 Jun 2025 | 31 Mar 2028 | 31 Jul 2028 | Extended 4 mo | 0 |
| Janki ParkJanki Developers | P99000078780, P99000079925 | 13 Jan 2025 | 30 May 2028 | 30 Sep 2028 | Extended 4 mo | 0 |
| Vrindavan Complex Phase IIIPatil Builders | P99000054219 | 3 Jan 2024 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Shree Kurlai ComplexShree Mangalmurti Associates | P99000032754 | 24 Jan 2022 | 30 Jun 2025 | 30 Jun 2025 | Promised date passed | 0 |
| Narayani Darshan Building No-7Narayani | P99000032475 | 4 Jan 2022 | 31 Oct 2023 | 30 Oct 2025 | Extended 24 mo | 0 |
| Shree Sankalp Apartment Building No 5 A And B WingBhoomi Sankalp Developers | P99000019829 | 5 Mar 2019 | 31 Jul 2023 | 31 Jul 2023 | Promised date passed | 0 |
| VRINDAVAN COMPLEX Phase IIPatil Builders | P99000018246 | 16 Oct 2018 | 30 Oct 2024 | 30 Oct 2024 | Promised date passed | 0 |
| Navkar ComplexVansh Developers | P99000010670 | 31 Aug 2017 | 30 Jun 2021 | 29 Dec 2022 | Extended 18 mo | 0 |
| Shamik Ashtavinayak Second PhaseShamik Enterprises Pvt Ltd. | P99000010348 | 24 Aug 2017 | 31 Jul 2019 | 30 Jan 2021 | Extended 18 mo | 1 |
| Shamik Ashtavinayak First PhaseShamik Enterprises Pvt Ltd. | P99000008801 | 19 Aug 2017 | 31 Jul 2018 | 31 Jul 2019 | Extended 12 mo | 1 |
| Vidya Sagar VillaRavindra Shankar Sawant | P99000008038 | 18 Aug 2017 | 15 Dec 2022 | 15 Dec 2022 | Promised date passed | 0 |
| Mithila DhamNaval Rambahadur Singh | P99000006624 | 14 Aug 2017 | 30 Mar 2022 | 30 Mar 2022 | Promised date passed | 0 |
| Vrindavan ComplexPatil Builders | P99000000827 | 23 Jul 2017 | 31 May 2019 | 30 Nov 2020 | Extended 18 mo | 0 |
Other localities in Palghar
Most active promoters
By projects registered here, as named on MahaRERA.
- Patil Builders3 projects
- Shamik Enterprises Pvt Ltd.2 projects
- Bhoomi Sankalp Developers1 project
- Janki Developers1 project
- Jivdani Developers1 project
- Kunjraj Enterprises1 project
- Narayani1 project
- Naval Rambahadur Singh1 project
- Parivar Ashish Developers1 project
- Ravindra Shankar Sawant1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology