RERA projects in Boisar
24 projects under 26 MahaRERA registrations, registered 2017–2026. 15% have a completion date extended beyond the one promised.
24RERA projects
26Registrationssome projects hold several
15Completion still due11 past their completion date
65 monthsMedian extension beyond promised date15% of registrations extended
0Regulatory casesnone on MahaRERA's lists
37Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 8 |
| 2018 | 2 |
| 2019 | 5 |
| 2020 | 2 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 1 |
| 2024 | 4 |
| 2025 | 3 |
| 2026 | 1 |
Projects in Boisar
24 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Shree GalaxyShree Infra | PM1240002601886 | 11 Sep 2026 | 31 Dec 2030 | — | Not yet due | 0 |
| Galaxy Emperia Phase-IIGalaxy Shine Developers | PR1240002501867 | 24 Dec 2025 | 30 Jun 2028 | — | Not yet due | 0 |
| Bafna Palatial VillasDiamond Developers | PR1240002501622 | 28 Nov 2025 | 31 Dec 2030 | — | Not yet due | 0 |
| Kekoo BaugFriends Realtors | PR1240002501301 | 20 Oct 2025 | 31 Mar 2027 | — | Not yet due | 0 |
| Ostwal ParamountShree Ostwal Builders Ltd | P99000078147 | 25 Nov 2024 | 31 Dec 2029 | — | Not yet due | 0 |
| 7 Star Horizon7 Star Developers | P99000055766 | 16 Apr 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Yash Padma Phase IISai Shraddha Enterprises | P99000055131 | 4 Mar 2024 | 31 Dec 2030 | — | Not yet due | 0 |
| Roop Rajat Park Building No 7a And 7bGaurav Ramashankar Singh | P99000054501 | 25 Jan 2024 | 31 Mar 2027 | — | Not yet due | 0 |
| Yosh EmpireYosh Infratech Private Limited | P99000048717 | 13 Jan 2023 | 31 Dec 2028 | — | Not yet due | 0 |
| Rk Complex 1Shree Enterprises | P99000026361 | 11 Sep 2020 | 31 Dec 2027 | — | Not yet due | 0 |
| Prajyot ApartmentM/s. Pratiksha Associates | P99000024447 | 13 Feb 2020 | 30 Jun 2027 | — | Not yet due | 0 |
| PalashInfra Crafts | P99000022425 | 20 Sep 2019 | 30 Dec 2027 | — | Not yet due | 0 |
| Nilsa HomesNilam Ramakant Sankhe | P99000021644 | 16 Jul 2019 | 30 May 2025 | 31 Dec 2030 | Extended 67 mo | 0 |
| Thakur Matruchaya Type CPawan Abhimanyu Singh | P99000019764 | 5 Mar 2019 | 30 Dec 2021 | — | Promised date passed | 0 |
| Narayan Shopping ParkPooja Group Of Company | P99000016863 | 20 Jun 2018 | 29 Mar 2025 | — | Promised date passed | 0 |
| Yash PadmaSai Shraddha Enterprises | P99000015545 | 8 Mar 2018 | 30 Dec 2026 | — | Not yet due | 0 |
| Gokuldham Zone 2Raj Shree Nirman Buiders Pvt Ltd | P99000012100 | 1 Sep 2017 | 31 Oct 2018 | — | Promised date passed | 0 |
| Horizon GardenHorizon Infracon | P99000011098 | 31 Aug 2017 | 31 Oct 2019 | 31 Dec 2024 | Extended 62 mo | 0 |
| Ostwal Dream LandShree Ostwal Builders Ltd | P99000008545, P99000021182 | 19 Aug 2017 | 31 Jul 2026 | 31 Dec 2019 | Promised date passed | 0 |
| Vakratunda EnterprisesVakratunda Enterprises LLP | P99000008100 | 18 Aug 2017 | 31 Dec 2026 | — | Not yet due | 0 |
| Hirani RegencyHirani Lifespaces | P99000007111 | 17 Aug 2017 | 31 Mar 2018 | 30 Nov 2024 | Extended 80 mo | 0 |
| Unity GardenUnity Land Developers | P99000007688 | 17 Aug 2017 | 31 Mar 2018 | — | Promised date passed | 0 |
| Vinayraj RegencyShubh Associates | P99000007254 | 17 Aug 2017 | 1 Oct 2018 | — | Promised date passed | 0 |
| Daulat GardensAhura Construction JV | P99000001241, P99000020674 | 27 Jul 2017 | 30 Dec 2025 | — | Promised date passed | 0 |
Other localities in Palghar
Most active promoters
By projects registered here, as named on MahaRERA.
- Sai Shraddha Enterprises2 projects
- Shree Ostwal Builders Ltd2 projects
- 7 Star Developers1 project
- Ahura Construction JV1 project
- Diamond Developers1 project
- Friends Realtors1 project
- Galaxy Shine Developers1 project
- Gaurav Ramashankar Singh1 project
- Hirani Lifespaces1 project
- Horizon Infracon1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology