Completion was pushed back 4 months, to Apr 2031; no MahaRERA orders on record; 0% of its units are booked.

Boisar, Palghar 401405 · by Diamond Developers

DeliveryExtended 4 moPromised Dec 2030 · now due Apr 2031RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 40 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2031

  • This projectRegistered 28 Nov 2025, completion promised 31 Dec 2030, revised to 30 Apr 2031.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

69 buildings

Open a building to see every flat, floor by floor.

Show all 69 buildingsShow fewer buildings

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPR1240002501622
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PR124000250162228 Nov 202531 Dec 203030 Apr 2031Diamond DevelopersProject page
Documents45

1 document held by Deedo, 44 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardDiamond developers pan card.pdf · uploaded 30 Jul 2025Source
  • OthersDiamond Form 3 Final.pdf · uploaded 30 Oct 2025Source

Legal

  • Declaration Form BDimond Developers - Affidavit Cum Declaration.pdf · uploaded 18 Jun 2025Source
  • Declaration Form BKhaira Gutno 66-1-3 Boisar.pdf · uploaded 18 Jun 2025Source
  • OthersPARESH SHAH.pdf · uploaded 29 Sep 2025Source
  • OthersParesh Shah Annexure A 26-10-25.pdf · uploaded 30 Oct 2025Source
  • OthersSatish Shah Annexure A 26-10-25.pdf · uploaded 30 Oct 2025Source
Show all 45 documentsShow fewer documents

Legal

  • OthersShilpa Nayak Annexure A 26-10-25.pdf · uploaded 30 Oct 2025Source
  • OthersMeenal Shah Annexure A 26-10-25.pdf · uploaded 30 Oct 2025Source
  • OthersNew PD-2014.pdf · uploaded 30 Oct 2025Source
  • OthersDeclaration - Partner.pdf · uploaded 30 Oct 2025Source
  • Declaration Form BDeclaration - Partner.pdf · uploaded 30 Oct 2025Source
  • OthersDiamond new title_compressed.pdf · uploaded 22 Nov 2025Source
  • Declaration Form BDeclaration - Gut & Survey 1.pdf · uploaded 22 Nov 2025Source

Migrated

  • Withdrawal Update Form 1Dec25-Form1-Palatial Villas_compressed.pdf · uploaded 5 May 2026Source
  • Withdrawal Update Form 1Mar26-Form1-Palatial Villas.pdf · uploaded 5 May 2026Source
  • Withdrawal Update Form 2Dec25-Form2-Palatial Villas.pdf · uploaded 5 May 2026Source
  • Withdrawal Update Form 2MAR26-FORM2-PALATIAL VILLAS.pdf · uploaded 5 May 2026Source
  • Withdrawal Update Form 3DEC25-DIAMOND DEVELOPERS-FORM3_compressed.pdf · uploaded 5 May 2026Source
  • Withdrawal Update Form 3MAR26-DIAMOND DEVELOPERS-FORM3.pdf · uploaded 5 May 2026Source
  • Withdrawal Update Form 1JUN26-FORM1-BOISAR.pdf · uploaded 4 Aug 2026Source
  • Withdrawal Update Form 2JUN26-FORM2-PALATIAL VILLAS.pdf · uploaded 4 Aug 2026Source
  • Withdrawal Update Form 3JUN26-FORM-3-PALATIAL VILLAS_compressed.pdf · uploaded 4 Aug 2026Source
  • Form 2A (FY 2025-2026)Form 2A- Palatial Villas.pdf · uploaded 28 Sep 2026Source

Technical

  • DocumentBuilding No 1 Type G (1).pdf · uploaded 13 Jun 2025Source
  • DocumentBuilding No 1 Type G.pdf · uploaded 13 Jun 2025Source
  • DocumentBuilding No 2 Type H.pdf · uploaded 13 Jun 2025Source
  • DocumentBunglow no 1-10 Type A.pdf · uploaded 13 Jun 2025Source
  • DocumentBunglow No 11-15 Type B.pdf · uploaded 13 Jun 2025Source
  • DocumentBunglow No 16-19 Type C.pdf · uploaded 13 Jun 2025Source
  • DocumentBunglow no 20-23, 26-29 Type D.pdf · uploaded 13 Jun 2025Source
  • DocumentBunglow No 24 & 25 Type E.pdf · uploaded 13 Jun 2025Source
  • DocumentBunglow No 30-32 Type F.pdf · uploaded 13 Jun 2025Source
  • DocumentN A Order Khaira Boisar.pdf · uploaded 18 Jun 2025Source
  • DocumentDeclaration Cum Undertaking.pdf · uploaded 24 Jun 2025Source
  • DocumentLAYOUT AND PARKING PLAN.pdf · uploaded 29 Sep 2025Source
  • OthersBuilding Layout Approval - Parking_page-0001.pdf · uploaded 30 Oct 2025Source
  • OthersBuilding Layout Approval - Proforma With Sign.pdf · uploaded 30 Oct 2025Source
  • OthersCC Issued by collector Palghar at village Khira Boisar.pdf · uploaded 30 Oct 2025Source
  • OthersCC Verification.pdf · uploaded 30 Oct 2025Source
  • OthersDeclaration - Gut & Survey.pdf · uploaded 30 Oct 2025Source
  • OthersDeclaration - Partner.pdf · uploaded 30 Oct 2025Source

Technical (Architect)

  • DocumentJUN26-FORM1-BOISAR.pdf · uploaded 1 Aug 2026Source

Technical (Engineer)

  • DocumentJUN26-FORM2-PALATIAL VILLAS.pdf · uploaded 4 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Gut No.66/1 Plot No.3

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
—40 units in all
Address
Teens World School Road, Khaira Boisar EastPIN 401405
Village
Boisar, Palghar taluka
Land area for this project
12,267 sq m (1,32,042 sq ft)
Approved layout area
13,213 sq m (1,42,218 sq ft)
Permissible built-up area
7,576 sq m (81,552 sq ft)
Sanctioned built-up area
7,576 sq m (81,552 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
76
Developed in phases
Yes

Survey, CTS, gat or plot numbers

Gut No.66/1 Plot No.3

Land as published on MahaRERA's project page

Gut No.66/1 Plot No.3

Boundaries

North
Gut no 66/1/Plot No 2
South
Gut no 66/1/Plot No 6&4
East
Internal Layout 15M Wide Road
West
Gut no 114

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking40 units

40 units registered

— · 40 units
BuildingTypeCarpet areaUnits
Bungalow No 01 Type A——1
Bungalow No 02 Type A——1
Bungalow No 03 Type A——1
Bungalow no 04 Type A——1
Bungalow No 05 Type A——1
Bungalow No 06 Type A——1
Bungalow No 07 Type A——1
Bungalow No 08 Type A——1
Show all 34 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnits
Bungalow No 09 Type A——1
Bungalow No 10 Type A——1
Bungalow No 11 Type B——1
Bungalow No 12 Type B——1
Bungalow No 13 Type B——1
Bungalow No 14 Type B——1
Bungalow No 15 Type B——1
Bungalow No 16 Type C——1
Bungalow No 17 Type C——1
Bungalow No 18 Type C——1
Bungalow No 19 Type C——1
Bungalow No 20 Type D——1
Bungalow No 21 Type D——1
Bungalow No 22 Type D——1
Bungalow No 23 Type D——1
Bungalow No 24 Type E——1
Bungalow No 25 Type E——1
Bungalow No 26 Type D——1
Bungalow No 27 Type D——1
Bungalow No 28 Type D——1
Bungalow No 29 Type D——1
Bungalow No 30 Type F——1
Bungalow No 31 Type F——1
Bungalow No 32 Type F——1
Wing A——4
Wing B——4

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
Chartered accountantNandish J Salot—
EngineerHimanshu M Raut—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Boisar

All 28 projects in Boisar · Compare Bafna Palatial Villas with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology