Deedo IDDP-PAL-TX91Completion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 18% of its units are booked.
Boisar, Palghar 401501 · by Yosh Infratech Private Limited
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2029
- This projectRegistered 13 Jan 2023, completion promised 31 Dec 2028, revised to 30 Apr 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP99000048717
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P99000048717 | 13 Jan 2023 | 31 Dec 2028 | 30 Apr 2029 | Yosh Infratech Private Limited | Project page |
Documents113
1 document held by Deedo, 112 filings listed on MahaRERA's project page
Finance
- PAN CardYosh Infratech Private Limited PAN Card.pdf · uploaded 25 Nov 2022Source
Legal
Migrated
- 1 PAN CardYosh Infratech Private Limited PAN Card.pdf · uploaded 25 Nov 2022Source
- 1 a Details of encumbrances concerned to FinanceEncumbrance certificate.pdf · uploaded 25 Nov 2022Source
- 1 b Details of encumbrances concerned to LegalEncumbrance certificate.pdf · uploaded 25 Nov 2022Source
- 1 Copy of Layout Approval (in case of layout)Sheet-1_compressed.pdf · uploaded 25 Nov 2022Source
Show all 113 documentsShow fewer documents
Migrated
- 1 Building Plan Approval / NA Order for plotted developmentSheet-2_compressed.pdf · uploaded 25 Nov 2022Source
- 2 Building Plan Approval / NA Order for plotted developmentSheet-3_compressed.pdf · uploaded 25 Nov 2022Source
- 3 Building Plan Approval / NA Order for plotted developmentSheet-4_compressed.pdf · uploaded 25 Nov 2022Source
- 4 Building Plan Approval / NA Order for plotted developmentSheet-5_compressed.pdf · uploaded 25 Nov 2022Source
- 5 Building Plan Approval / NA Order for plotted developmentSheet-6_compressed.pdf · uploaded 25 Nov 2022Source
- 6 Building Plan Approval / NA Order for plotted developmentSheet-7_compressed.pdf · uploaded 25 Nov 2022Source
- 7 Building Plan Approval / NA Order for plotted developmentSheet-8_compressed.pdf · uploaded 25 Nov 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentCC_compressed.pdf · uploaded 25 Nov 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate Form 1-R1.pdf · uploaded 25 Nov 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER'S CERTIFICATE.pdf · uploaded 25 Nov 2022Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A-2.pdf · uploaded 25 Nov 2022Source
- 1 Copy of the legal title reportLegal Title Report.pdf · uploaded 5 Dec 2022Source
- 1 CERSAI detailsCERSAI_Search_Report_200254036362_For_Asset_Based_Search_06_12_2022_11_14_33_319.pdf · uploaded 6 Dec 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 6 Dec 2022Source
- 1 Proforma of Allotment letternEW ALLOTMENT LETTER DRAFT WITHOUT PREJUDICE.pdf · uploaded 20 Dec 2022Source
- 1 Deviation Report with respect to Allotment letterdeviation report allotment letter NEW.pdf · uploaded 20 Dec 2022Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure- Yogesh sir sign 1.pdf · uploaded 2 Jan 2023Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure- Heena signed.pdf · uploaded 2 Jan 2023Source
- 1 Declaration about Commencement CertificateDeclaration about Commencement Certificate- Sign.pdf · uploaded 3 Jan 2023Source
- 1 Declaration in FORM BForm B New.pdf · uploaded 3 Jan 2023Source
- 1 Proforma of Agreement for saleNEW AFS BY YOSH FILED WITH RERA.pdf · uploaded 11 Jan 2023Source
- 1 Deviation Report with respect to model copy of AgreementNEW DEVIATION REPORT SIGN.pdf · uploaded 11 Jan 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)2 Yosh Architect's Certificate 31-03-2023.pdf · uploaded 29 May 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)2 Engineer's Certificate.pdf · uploaded 29 May 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)2 Form 3 CA Certificate Yosh-sign.pdf · uploaded 29 May 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)2 updated Form 3 CA Certificate 31-03-2023 Revised Signed_11zon.pdf · uploaded 20 Feb 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 Fy 2022-23.pdf · uploaded 20 Feb 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sep-23.pdf · uploaded 22 Feb 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)dec-23.pdf · uploaded 22 Feb 2025Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)March-24.pdf · uploaded 22 Feb 2025Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)june-24.pdf · uploaded 22 Feb 2025Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)sept -24.pdf · uploaded 22 Feb 2025Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)dec -24.pdf · uploaded 22 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)June-23.pdf · uploaded 22 Feb 2025Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)24-25_Q2_Form3.pdf · uploaded 22 Feb 2025Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)24-25_Q3_Form3.pdf · uploaded 22 Feb 2025Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)24-25_Q1_Form3.pdf · uploaded 22 Feb 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)23-24_Q4_Form3.pdf · uploaded 22 Feb 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)23-24_Q3_Form3.pdf · uploaded 22 Feb 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)23-24_Q2_Form3.pdf · uploaded 22 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)23-24_Q1_Form3.pdf · uploaded 22 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)2324_Q1_Form 2.pdf · uploaded 22 Feb 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)2324_Q2_Form 2.pdf · uploaded 22 Feb 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)2324_Q3_Form 2.pdf · uploaded 22 Feb 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)2324_Q4_Form 2.pdf · uploaded 22 Feb 2025Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)2425_Q1_Form 2.pdf · uploaded 22 Feb 2025Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)2425_Q2_Form 2.pdf · uploaded 22 Feb 2025Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)2425_Q3_Form 2.pdf · uploaded 22 Feb 2025Source
- 1 Building Plan Approval / NA Order for plotted developmentjune-24.pdf · uploaded 22 Feb 2025Source
- 2 Building Plan Approval / NA Order for plotted developmentsept -24.pdf · uploaded 22 Feb 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A Quality Certificate.pdf · uploaded 22 Feb 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form5.pdf · uploaded 22 Feb 2025Source
- Withdrawal Update Form 1Form 1_June 25.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 1Form 1_Sep 25.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 1Form 1_Dec 25.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 2Form 2_June 25.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 2Form 2_Sep 25.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 2Form 2_Dec 25.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 3Form 3_June 25.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 3Form 3_Sep 25.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 3Form 3_Dec 25.pdf · uploaded 20 Jan 2026Source
- Form 2A (FY 2022-2023)Form 2A March 2023.pdf · uploaded 21 Jan 2026Source
- Form 2A (FY 2023-2024)Form 2A March 2023-2024.pdf · uploaded 22 Jan 2026Source
- Form 2A (FY 2024-2025)Form 2A March 2024-2025.pdf · uploaded 22 Jan 2026Source
- Form 1Form 1_March 25.pdf · uploaded 30 Jan 2026Source
- Form 2Form 2_March 25.pdf · uploaded 30 Jan 2026Source
- Form 3Form 3_March 25.pdf · uploaded 30 Jan 2026Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory_March 25.pdf · uploaded 30 Jan 2026Source
- Form 5 (FY 2022-2023)Form 5 FY 2022-23.pdf · uploaded 30 Jan 2026Source
- Form 5 (FY 2023-2024)Form 5 FY 2023-24.pdf · uploaded 30 Jan 2026Source
- Withdrawal Update Form 12526_Q4_Form 1.pdf · uploaded 22 Jun 2026Source
- Withdrawal Update Form 22526_Q4_Form 2.pdf · uploaded 22 Jun 2026Source
- Withdrawal Update Form 325-26_Q4_Form3.pdf · uploaded 22 Jun 2026Source
- Form 2A (FY 2025-2026)Form 2A_2025-26.pdf · uploaded 15 Jul 2026Source
- Withdrawal Update Form 1Form 1 Q1 2026-27.pdf · uploaded 9 Sep 2026Source
- Withdrawal Update Form 22627_Q1_Form 2.pdf · uploaded 9 Sep 2026Source
- Withdrawal Update Form 32627 Q1 Form 3.pdf · uploaded 9 Sep 2026Source
- Form 5 (FY 2024-2025)Form 5 FY 2024-25.pdf · uploaded 6 Oct 2026Source
- Form 5 (FY 2025-2026)Form 5 FY 2025-26.pdf · uploaded 6 Oct 2026Source
Technical
- DocumentSheet-1_compressed.pdf · uploaded 25 Nov 2022Source
- DocumentSheet-8_compressed.pdf · uploaded 25 Nov 2022Source
- DocumentSheet-2_compressed.pdf · uploaded 25 Nov 2022Source
- DocumentSheet-3_compressed.pdf · uploaded 25 Nov 2022Source
- DocumentSheet-4_compressed.pdf · uploaded 25 Nov 2022Source
- DocumentSheet-5_compressed.pdf · uploaded 25 Nov 2022Source
- DocumentSheet-6_compressed.pdf · uploaded 25 Nov 2022Source
- DocumentSheet-7_compressed.pdf · uploaded 25 Nov 2022Source
- Documentjune-24.pdf · uploaded 22 Feb 2025Source
- Documentsept -24.pdf · uploaded 22 Feb 2025Source
Technical (Architect)
- DocumentJune-23.pdf · uploaded 22 Feb 2025Source
- DocumentSep-23.pdf · uploaded 22 Feb 2025Source
- Documentdec-23.pdf · uploaded 22 Feb 2025Source
- DocumentMarch-24.pdf · uploaded 22 Feb 2025Source
- Documentjune-24.pdf · uploaded 22 Feb 2025Source
- Documentsept -24.pdf · uploaded 22 Feb 2025Source
- Documentdec -24.pdf · uploaded 22 Feb 2025Source
- DocumentForm 1 Q1 2026-27.pdf · uploaded 9 Sep 2026Source
Technical (Engineer)
- Document2324_Q1_Form 2.pdf · uploaded 22 Feb 2025Source
- Document2324_Q2_Form 2.pdf · uploaded 22 Feb 2025Source
- Document2324_Q3_Form 2.pdf · uploaded 22 Feb 2025Source
- Document2324_Q4_Form 2.pdf · uploaded 22 Feb 2025Source
- Document2425_Q1_Form 2.pdf · uploaded 22 Feb 2025Source
- Document2425_Q2_Form 2.pdf · uploaded 22 Feb 2025Source
- Document2425_Q3_Form 2.pdf · uploaded 22 Feb 2025Source
- Document2627_Q1_Form 2.pdf · uploaded 9 Sep 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel PLOT NO R1, T1 283-406
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- —195 units in all
- Address
- Plot No R1, T1 283-406, Tarapur Road, BoisarPIN 401501
- Village
- Boisar, Palghar taluka
- Location
- 19.78926, 72.73991
- Land area for this project
- 9,008 sq m (96,961 sq ft)
- Permissible built-up area
- 9,008 sq m (96,961 sq ft)
- Sanctioned built-up area
- 9,008 sq m (96,961 sq ft)
- Recreational open space
- 925 sq m (9,961 sq ft)
- Designated bank account
- 190
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
PLOT NO R1, T1 283-406
Boundaries
- North
- Plot No 1 And 2
- South
- Nala
- East
- Adj Existing CIDCO Garden
- West
- Existing 9m Wide Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking195 units
195 units registered
| Building | Type | Carpet area | Units |
|---|---|---|---|
| Commercial | — | — | 71 |
| Residential-Wing A and B | — | — | 124 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals5
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Deepak Thakare Deepak Thakre | — |
| Chartered accountant | Manish Kumar Gupta And Co Manishkumar Gupta | — |
| Chartered accountant | Ms DIPIKA PATEL & CO DIPIKA PATEL | — |
| Chartered accountant | Rajesh Murugan | — |
| Engineer | Structural Concept Designs Private Limited | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Boisar
- Shree GalaxyRERA PM1240002601886
- Galaxy Emperia Phase-IIRERA PR1240002501867
- Bafna Palatial VillasRERA PR1240002501622
- Kekoo BaugRERA PR1240002501301
- Ostwal ParamountRERA P99000078147
- 7 Star HorizonRERA P99000055766
- Yash Padma Phase IIRERA P99000055131
- Roop Rajat Park Building No 7a And 7bRERA P99000054501
All 28 projects in Boisar · Compare Yosh Empire with another project