Evershine Amavi
Completion date passedDongare, Palghar 401303 |Promoter: Evershine Developers
Project summary
As registered with MahaRERA
- RERA registrations
- 2
- Phases
- 2
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 1 year
P99000024753The latest completion date on record passed 10 months ago.
- Registered
- 2 Mar 2020
- Promised
- 30 Dec 2024
- Revised
- 30 Dec 2025
Completion pushed back 1 year
P99000024860The latest completion date on record passed 1 year and 10 months ago.
- Registered
- 9 Mar 2020
- Promised
- 30 Dec 2023
- Revised
- 29 Dec 2024
2 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P99000024753 | 2 Mar 2020 | 30 Dec 2024 | 30 Dec 2025 | Evershine Developers | Project page |
| P99000024860 | 9 Mar 2020 | 30 Dec 2023 | 29 Dec 2024 | Evershine Developers | Project page |
Documents
4 documents held by Deedo
Registration certificates
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Dongare
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.