Building No 24 · Evershine Amavi
Dongare · RERA P99000024753
IDBLD_06288814 floorsExtended 12 mo
14Sanctioned habitable floorsregistration certificate
30 Dec 2025Revised completionpromised 30 Dec 2024
64 of 110Units bookedMahaRERA project page
Floors
14 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P99000024753 · registered 2 Mar 2020
- Promised completion
- 30 Dec 2024
- Revised completion
- 30 Dec 2025
- Sanctioned habitable floors
- 14
- ProjectId
- 32,059
- ProjectName
- EVERSHINE AMAVI 303 PHASE 3
- TotalUnitCount
- 110
- ProjectBuildingId
- 1,49,166
- BuildingNameNumber
- BUILDING NO 24
- FsiWithSanctionSqmts
- 14
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 110
- ProjectRegistartionNo
- P99000024753
- ProjectBuildingWingsId
- 1,52,583
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- BUILDING NO 24
- NoOfBuildingWingFloorProposed
- 16
- NoOfBuildingWingFloorHabitable
- 14
- NoOfBuildingWingFloorSanctioned
- 16
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 33.4 m² (359 sq.ft) | 28 | 22 |
| 1BHK | 33.5 m² (361 sq.ft) | 28 | 11 |
| 1BHK | 37.4 m² (402 sq.ft) | 54 | 31 |
| Total | 110 | 64 |