Evershine Developers

Company or firm · 3 projects · 4 MahaRERA registrations

Projects34 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date25%1 of 4 past their proposed date, not extended
Median delay+12 movs RERA proposed date · 3 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Evershine AmaviP99000024753Dongare2020Not reported30 Dec 202430 Dec 2025+12 months
Evershine Amavi 303 Phase 1P99000024780Dongare2020Not reported30 Dec 202329 Dec 2024+12 months
Evershine AmaviP99000024860Dongare2020Not reported30 Dec 202329 Dec 2024+12 months
Evershine 36 Turner RoadP99000053366Palghar2023Not reported31 Dec 2025—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Evershine Amavi+12 mo
  • Evershine Amavi 303 Phase 1+12 mo
  • Evershine Amavi+12 mo
  • Evershine 36 Turner RoadOn date

Track record notes

  • 1 of 4 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for Evershine Amavi (P99000024753).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology