Evershine Developers
Company or firm · 3 projects · 4 MahaRERA registrations
Projects34 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date25%1 of 4 past their proposed date, not extended
Median delay+12 movs RERA proposed date · 3 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Evershine AmaviP99000024753 | Dongare | 2020 | Not reported | 30 Dec 2024 | 30 Dec 2025 | +12 months |
| Evershine Amavi 303 Phase 1P99000024780 | Dongare | 2020 | Not reported | 30 Dec 2023 | 29 Dec 2024 | +12 months |
| Evershine AmaviP99000024860 | Dongare | 2020 | Not reported | 30 Dec 2023 | 29 Dec 2024 | +12 months |
| Evershine 36 Turner RoadP99000053366 | Palghar | 2023 | Not reported | 31 Dec 2025 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 4 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 12 months, for Evershine Amavi (P99000024753).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology