Dongare, Palghar 401303 |Promoter: Keystone Infrastructure Private Limited

22 Nov 2018Registered with MahaRERAFirst of 5 registrations
30 Sep 2023Promised completionLatest across registrations
31 Dec 2025Revised completion5 of 5 registrations pushed back, by up to 2 years and 10 months
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

RERA registrations
5
Phases
5

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.47106, 72.80723
Rustomjee Virar Avenue L1 L2 And L4 is at latitude 19.47106, longitude 72.80723.

Also registered as

Rustomjee Virar Avenue L1-L2 and L4 Wing A B and Retail BuildingRustomjee Virar Avenue L1-L2 And L4 Wing C and DRustomjee Virar Avenue L1-L2 And L4 Wing E and F and Retail BuildingRustomjee Virar Avenue L1-L2 and L4 Wing H and RetailRustomjee Virar Avenue L1-L2 and L4 Wing K
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year

P99000018622

The latest completion date on record passed 3 years and 3 months ago.

Registered
22 Nov 2018
Promised
31 Jul 2022
Revised
31 Jul 2023

Completion pushed back 1 year

P99000018694

The latest completion date on record passed 3 years and 3 months ago.

Registered
27 Nov 2018
Promised
31 Jul 2022
Revised
31 Jul 2023

Completion pushed back 2 years and 10 months

P99000020234

The latest completion date on record passed 10 months ago.

Registered
29 Mar 2019
Promised
28 Feb 2023
Revised
31 Dec 2025

Completion pushed back 1 year

P99000020235

The latest completion date on record passed 2 years and 1 month ago.

Registered
29 Mar 2019
Promised
30 Sep 2023
Revised
29 Sep 2024
Show 1 more registrations

Completion pushed back 2 years and 10 months

P99000020272

The latest completion date on record passed 10 months ago.

Registered
31 Mar 2019
Promised
28 Feb 2023
Revised
31 Dec 2025

5 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P9900001862222 Nov 201831 Jul 202231 Jul 2023Keystone Infrastructure Private LimitedProject page
P9900001869427 Nov 201831 Jul 202231 Jul 2023Keystone Infrastructure Private LimitedProject page
P9900002023429 Mar 201928 Feb 202331 Dec 2025Keystone Infrastructure Private LimitedProject page
P9900002023529 Mar 201930 Sep 202329 Sep 2024Keystone Infrastructure Private LimitedProject page
P9900002027231 Mar 201928 Feb 202331 Dec 2025Keystone Infrastructure Private LimitedProject page

Documents

10 documents held by Deedo

Registration certificates

  • Registration certificateP99000018622 · 9 Sep 2021ViewSource
  • Registration certificateP99000018694 · 9 Sep 2021ViewSource
  • Registration certificateP99000020234 · 9 Sep 2021ViewSource
  • Registration certificateP99000020272 · 9 Sep 2021ViewSource
  • Registration certificateP99000020235 · 9 Sep 2021ViewSource

Extension certificates

  • Extension certificateP99000018694 · 15 Dec 2021ViewSource
  • Extension certificateP99000020235 · 18 May 2022ViewSource
  • Extension certificateP99000018622 · 12 Jan 2023ViewSource
  • Extension certificateP99000020234 · 21 Nov 2023ViewSource
  • Extension certificateP99000020272 · 4 Mar 2024ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Dongare

Survey, CTS, gat or plot numbers

part of Avenue L1L2 L4 being pt of larger layout bearing surve nos 5 5B 5D 5F 5G ofPart of Avenue L1L2L4 being pt of larger layout bearing survey nos. 5 5B 5D 5F 5G ofpt of Avenue L1 L2 L4 being pt of larger layout being sy no 5 5B 5D 5F 5G of