Registered with MahaRERAP99000020234Status on MahaRERA: Certificate Signed

Rustomjee Virar Avenue L1 L2 And L4

Dongare, Palghar · Promoter Keystone Infrastructure Private Limited · Registered 29 Mar 2019 · Proposed completion 28 Feb 2023

Open project page
Project type
Others
Revised completion
31 Dec 2025
Extension certificates
1
Last MahaRERA sync
22 Oct 2026, 01:49
On MahaRERA
Project page

What Deedo found with this number

Watch for

  • Completion date extended from 28 Feb 2023 to 31 Dec 2025 (1 extension certificate on record).
  • The latest completion date on record, 31 Dec 2025, has passed.

Documents

Stored copies of what MahaRERA published under this number.

Number not found? Deedo says “No record found in the sources Deedo currently covers” rather than guessing. It covers MahaRERA's statewide project register; new registrations appear after the next sync with MahaRERA.
Data through22 Oct 2026, 01:49SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology