Keystone Infrastructure Private Limited

Company or firm · 5 projects · 9 MahaRERA registrations

Projects59 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date22%2 of 9 past their proposed date, not extended
Median delay+12 movs RERA proposed date · 7 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Rustomjee Virar Avenue D1 Wing C And Wing DP99000017942Palghar2018Not reported30 Dec 2021—On date
Rustomjee Virar Avenue D1 Wing A And Wing B And Retail BuildingP99000018043Dongare2018Not reported30 Dec 2021—On date
Rustomjee Virar Avenue L1 L2 And L4P99000018622Dongare2018Not reported31 Jul 202231 Jul 2023+12 months
Rustomjee Virar Avenue L1 L2 And L4P99000018694Dongare2018Not reported31 Jul 202231 Jul 2023+12 months
Rustomjee Virar Avenue L1-L2 and L4 Wing I J and RetailP99000020216Dongare2019Not reported30 Sep 202331 Dec 2025+27 months
Rustomjee Virar Avenue L1 L2 And L4P99000020234Dongare2019Not reported28 Feb 202331 Dec 2025+34 months
Rustomjee Virar Avenue L1 L2 And L4P99000020235Dongare2019Not reported30 Sep 202329 Sep 2024+12 months
Rustomjee Virar Avenue L1 L2 And L4P99000020272Dongare2019Not reported28 Feb 202331 Dec 2025+34 months
Rustomjee Virar Avenue L1-L2 and L4 Wing GP99000020273Dongare2019Not reported28 Feb 202328 Feb 2024+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Rustomjee Virar Avenue D1 Wing C And Wing DOn date
  • Rustomjee Virar Avenue D1 Wing A And Wing B And Retail BuildingOn date
  • Rustomjee Virar Avenue L1 L2 And L4+12 mo
  • Rustomjee Virar Avenue L1 L2 And L4+12 mo
  • Rustomjee Virar Avenue L1-L2 and L4 Wing I J and Retail+27 mo
  • Rustomjee Virar Avenue L1 L2 And L4+34 mo
  • Rustomjee Virar Avenue L1 L2 And L4+12 mo
  • Rustomjee Virar Avenue L1 L2 And L4+34 mo
  • Rustomjee Virar Avenue L1-L2 and L4 Wing G+12 mo

Track record notes

  • 2 of 9 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 34 months, for Rustomjee Virar Avenue L1 L2 And L4 (P99000020234).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology