Mayank Height Type 2c

Certificate Signed

Dhansar, Palghar 401404 |Promoter: City Space Developers

9 Jul 2026Registered with MahaRERA
31 Dec 2031Promised completion
30 Apr 2032Revised completionPushed back 4 months
1Building
34Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Mixed
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
—34 units in all
Address
Old Satpati Road, DhansarPIN 401404
Designated bank account
19
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.69712, 72.74212
Mayank Height Type 2c is at latitude 19.69712, longitude 72.74212.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
9 Jul 2026
Promised
31 Dec 2031
Revised
30 Apr 2032

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PM12400026011139 Jul 202631 Dec 203130 Apr 2032City Space DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsFloors with CCUnits
Building 2c8834

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

34 units registered

— · 34 units
TypeCarpet areaUnits
——34

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 19 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPANCARD.pdf · uploaded 16 May 2026Source
  • GSTIN DocumentGST CERTIFICATE CITY SPACE.pdf · uploaded 16 May 2026Source
  • OthersDeclaration Project Feasibilty.pdf · uploaded 22 May 2026Source

Legal

  • Declaration Form BForm-B Developer.pdf · uploaded 17 Apr 2026Source
  • OthersPARTNERSHIP DEED.pdf · uploaded 12 May 2026Source
  • Othersdisclosure of interest in other rera estate organizations-Vinay Singh.pdf · uploaded 22 May 2026Source
  • OthersDisclosure Yashpal Singh.pdf · uploaded 22 May 2026Source
Show all 20 documentsShow fewer documents

Legal

  • OthersDisclosure Rekha Singh.pdf · uploaded 22 May 2026Source
  • Declaration Form BLegal Title report_compressed.pdf · uploaded 22 May 2026Source
  • Otherssatbara.pdf · uploaded 17 Jun 2026Source

Technical

  • OthersForm-1.pdf · uploaded 12 May 2026Source
  • OthersForm-2.pdf · uploaded 12 May 2026Source
  • DocumentLAYOUT PLAN Highlighted.pdf · uploaded 22 May 2026Source
  • DocumentBuilding Plan Highlighted.pdf · uploaded 22 May 2026Source
  • DocumentAnnexure-A.pdf · uploaded 22 May 2026Source
  • OthersParking Statement.pdf · uploaded 22 May 2026Source
  • OthersPlot Area Declaration.pdf · uploaded 22 May 2026Source
  • OthersCC verification mail screnshot.pdf · uploaded 22 May 2026Source
  • OthersCC verification mail SS with mail date.pdf · uploaded 11 Jun 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Dhansar, Palghar taluka

Survey, CTS, gat or plot numbers

GUT NO. 232/5/1

Boundaries

North
Open Parking
South
Building 2b
East
Gut No. 232/5/3
West
Adj Plot No 4

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
EngineerMukesh Arjun Singh Kumar—

Source: MahaRERA project page. Contact details are not shown.