Siddham Heights
Deedo IDDP-THN-2PEECompletion was pushed back 2 years to Dec 2025, and that date has passed too; no MahaRERA orders on record; 77% of its units are booked.
Mirabhayandar (M Corp.), Thane 401101 · by Bhoopendra Ghisulal Borana
Buying a flat here?
See every deed registered on it.
Completion was pushed back 2 years to Dec 2025, and that date has passed too
- This projectRegistered 18 Aug 2017, completion promised 30 Dec 2023, revised to 31 Dec 2025, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700008037
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700008037 | 18 Aug 2017 | 30 Dec 2023 | 31 Dec 2025 | Bhoopendra Ghisulal Borana | Project page |
Documents97
2 documents held by Deedo, 95 filings listed on MahaRERA's project page
Finance
- PAN Cardpan.pdf · uploaded 24 Jan 2024Source
Show all 97 documentsShow fewer documents
Legal
- OtherConcern.pdf · uploaded 10 Oct 2019Source
- OtherBinder5- POWER OF ATTOREY-1.pdf · uploaded 10 Oct 2019Source
- OtherBinder5- POWER OF ATTOREY-16-30- 3.pdf · uploaded 10 Oct 2019Source
- Legal Title reportBinder2.pdf · uploaded 10 Oct 2019Source
- Declaration Form BForm b.pdf · uploaded 25 Jan 2024Source
- Declaration Form Bsiddham height affidavit cum declaration 2024-25_0001.pdf · uploaded 20 Feb 2025Source
Migrated
- 1 Copy of the legal title reportTitle 555.pdf · uploaded 30 Jul 2017Source
- 1 Details of encumbrancesDECLARATION.pdf · uploaded 30 Jul 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 30 Jul 2017Source
- 1 Declaration in FORM BFORM B.pdf · uploaded 30 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERTIFICATE.pdf · uploaded 30 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGG CERTIFCATE.pdf · uploaded 30 Jul 2017Source
- 1 Certificates of CA (Form 3)Form-3 C A Certificate.pdf · uploaded 30 Jul 2017Source
- 1 Proforma of Allotment letterDeclaration.pdf · uploaded 30 Jul 2017Source
- 1 Copy of Layout Approval (in case of layout)layout.pdf · uploaded 31 Jul 2017Source
- 1 Building Plan Approval (IOD)Authorization Letter.pdf · uploaded 31 Jul 2017Source
- 2 Copy of the legal title reportBinder2.pdf · uploaded 10 Oct 2019Source
- 2 Building Plan Approval (IOD)Binder1.pdf · uploaded 10 Oct 2019Source
- 2 Commencement Certificates / NA Order for plotted developmentBinder4- CC 2019.pdf · uploaded 10 Oct 2019Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 10 Oct 2019Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 10 Oct 2019Source
- 2 Certificates of CA (Form 3)Bhoopendra Borana (Form-3).pdf · uploaded 10 Oct 2019Source
- 1 Annual Audit Report of Statutory CA (Form 5)Bhoopendra Borana (Form-5)1.pdf · uploaded 10 Oct 2019Source
- 2 Annual Audit Report of Statutory CA (Form 5)Bhoopendra Borana (Form-5).pdf · uploaded 10 Oct 2019Source
- 1 OtherBinder8- NA.pdf · uploaded 10 Oct 2019Source
- 2 OtherBinder3- ULC.pdf · uploaded 10 Oct 2019Source
- 3 OtherBinder7-ULC.pdf · uploaded 10 Oct 2019Source
- 4 OtherConcern.pdf · uploaded 10 Oct 2019Source
- 5 OtherBinder5- POWER OF ATTOREY-1.pdf · uploaded 10 Oct 2019Source
- 6 OtherBinder5- POWER OF ATTOREY-16-30- 3.pdf · uploaded 10 Oct 2019Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)6(2).pdf · uploaded 28 Nov 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)BORANA 1.pdf · uploaded 9 Dec 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)BORANA.pdf · uploaded 9 Dec 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form5.pdf · uploaded 14 Dec 2023Source
- 1 PAN Cardpan.pdf · uploaded 24 Jan 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form5- 2022-23.pdf · uploaded 24 Jan 2024Source
- 2 Declaration in FORM BForm b.pdf · uploaded 25 Jan 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)form 2a-19-20.pdf · uploaded 25 Jan 2024Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)19-20.pdf · uploaded 25 Jan 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)20-21.pdf · uploaded 25 Jan 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)21-22.pdf · uploaded 25 Jan 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)22-23.pdf · uploaded 25 Jan 2024Source
- 1 Disclosure of sold/ booked inventorysOLD Unsold List.pdf · uploaded 25 Jan 2024Source
- 2 Details of encumbrancesfinance.pdf · uploaded 5 Feb 2024Source
- 3 a Details of encumbrances concerned to Financelegal.pdf · uploaded 5 Feb 2024Source
- 1 b Details of encumbrances concerned to Legallegal.pdf · uploaded 5 Feb 2024Source
- 1 Declaration about Commencement CertificateCC Declaration.pdf · uploaded 5 Feb 2024Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)fORM 1.pdf · uploaded 5 Feb 2024Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2.pdf · uploaded 5 Feb 2024Source
- 1 CERSAI detailscersai.pdf · uploaded 5 Feb 2024Source
- 3 Certificates of CA (Form 3)CA FORM 3.pdf · uploaded 5 Feb 2024Source
- 1 Disclosure of Interest in Other Real Estate Organizationsdisclosuer of interest.pdf · uploaded 5 Feb 2024Source
- 1 Proforma of Agreement for saleRERA - jainam siddham.pdf · uploaded 5 Feb 2024Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSeperate Bank.pdf · uploaded 5 Feb 2024Source
- 1 Deviation Report with respect to Allotment letterAllotment D.pdf · uploaded 5 Feb 2024Source
- 1 Deviation Report with respect to model copy of AgreementAgreement D.pdf · uploaded 5 Feb 2024Source
- 1 Other – TechnicalArchitect Other.pdf · uploaded 5 Feb 2024Source
- 2 Copy of Layout Approval (in case of layout)LAYOUT-2.pdf · uploaded 12 Feb 2024Source
- 3 Building Plan Approval (IOD)BLDG PLAN_11zon.pdf · uploaded 12 Feb 2024Source
- 1 Declaration in FORM Bsiddham height affidavit cum declaration 2024-25_0001.pdf · uploaded 20 Feb 2025Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)siddham height FORM 1 17-2-25_0001.pdf · uploaded 20 Feb 2025Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)siddham height FORM 2 17-2-25_0001.pdf · uploaded 20 Feb 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)borana-form 5_0001.pdf · uploaded 13 Mar 2025Source
- Withdrawal Update Form 1fORM 1.pdf · uploaded 30 Dec 2025Source
- Withdrawal Update Form 1fORM 1.pdf · uploaded 30 Dec 2025Source
- Withdrawal Update Form 2FORM 2.pdf · uploaded 30 Dec 2025Source
- Withdrawal Update Form 2FORM 2.pdf · uploaded 30 Dec 2025Source
- Withdrawal Update Form 3CA FORM 3.pdf · uploaded 30 Dec 2025Source
- Withdrawal Update Form 3CA FORM 3.pdf · uploaded 30 Dec 2025Source
- Form 5 (FY 2018-2019)1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19).pdf · uploaded 14 Mar 2026Source
- Form 5 (FY 2019-2020)1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20).pdf · uploaded 14 Mar 2026Source
- Form 5 (FY 2020-2021)1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21).pdf · uploaded 14 Mar 2026Source
- Form 5 (FY 2021-2022)1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22).pdf · uploaded 14 Mar 2026Source
- Form 5 (FY 2022-2023)1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23).pdf · uploaded 14 Mar 2026Source
- Form 5 (FY 2023-2024)1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24).pdf · uploaded 14 Mar 2026Source
- Withdrawal Update Form 1fORM 1.pdf · uploaded 15 Jun 2026Source
- Withdrawal Update Form 2FORM 2.pdf · uploaded 15 Jun 2026Source
- Withdrawal Update Form 3CA FORM 3.pdf · uploaded 15 Jun 2026Source
- Form 2A (FY 2025-2026)Form 2A.pdf · uploaded 21 Aug 2026Source
Technical
- DocumentAuthorization Letter.pdf · uploaded 31 Jul 2017Source
- Documentlayout.pdf · uploaded 31 Jul 2017Source
- DocumentBinder1.pdf · uploaded 10 Oct 2019Source
- Other – TechnicalArchitect Other.pdf · uploaded 5 Feb 2024Source
- DocumentBLDG PLAN_11zon.pdf · uploaded 12 Feb 2024Source
- DocumentLAYOUT-2.pdf · uploaded 12 Feb 2024Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 558/1, 5581
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 3BHK43 units in all
- Address
- Old Sno 5557, 5581, 5622, 5684 And 5685 Village Bhayander Thane, 30 M RoadPIN 401101
- Village
- Mira-Bhayandar (M Corp.), Thane taluka
- Location
- 19.30080, 72.84671
- Land area for this project
- 4,869 sq m (52,411 sq ft)
- Permissible built-up area
- 2,434 sq m (26,200 sq ft)
- Sanctioned built-up area
- 1,135 sq m (12,222 sq ft)
- Recreational open space
- 97 sq m (1,048 sq ft)
- Designated bank account
- 190
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
OLD SNO 5557,5581,5622,5684 AND 5685 VILLAGE BHAYANDER THANE
Boundaries
- North
- Fire Brigate Building
- South
- 18 M Wide Road
- East
- 30 M Road
- West
- Sno 566
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking43 units
33 of 43 units booked (77%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 34.51 sq m · 371 sq ft | 22 | 17 |
| 3BHK | 68.66 sq m · 739 sq ft | 21 | 16 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Bharat Patel | — |
| Chartered accountant | Ramesh D Lukad | — |
| Engineer | Bhavesh Patel | — |
| Other | Mohan T Rathod | — |
Source: MahaRERA project page. Contact details are not shown.