RERA projects in Bavdhan Kh.

32 projects under 33 MahaRERA registrations, registered 2017–2025. 42% have a completion date extended beyond the one promised.

Locality
32RERA projects
33Registrationssome projects hold several
10Completion still due23 past their completion date
5 monthsMedian extension beyond promised date42% of registrations extended
2Regulatory caseson 2 projects
54Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20178
20182
20192
20204
20210
20226
20235
20244
20252

Projects in Bavdhan Kh.

32 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Vishwanath Apartment C WINGSamarthshree DevelopersPR126000250178115 Dec 202530 Nov 202730 Mar 2028Extended 4 mo0
Fortune AuraSk Fortune GroupP521000804676 Jun 20252 Jun 20282 Oct 2028Extended 4 mo0
Akashparv CSharada Shrikalp Promoters & BuildersP521000778077 Nov 202431 Dec 202830 Apr 2029Extended 4 mo0
K Pune Phase 2Vmc Landmark Realty LLPP521000773016 Aug 202431 Mar 202931 Jul 2029Extended 4 mo0
Seraph Supremus B WingRishikesh RealtyP5210005489715 Feb 202431 Dec 202730 Apr 2028Extended 4 mo0
Anant ParvatiSamarthshree DevelopersP5210005445125 Jan 202431 Dec 202631 Dec 2026Not yet due0
The OrchidsSurana Sanghvi DevelopersP5210005413629 Dec 202331 Dec 202930 Apr 2030Extended 4 mo0
Siddh Amara Phase IISiddh HousingP5210005362421 Nov 202331 Dec 202630 Apr 2027Extended 4 mo0
Infinia Spring HillsSunil Wamanrao ShindeP5210005212224 Jul 20231 Jul 20251 Jul 2025Promised date passed0
ShantaiVeer BuildconP5210004883124 Jan 202331 Dec 202631 Dec 2026Not yet due0
Elite RegencyKavya BuildconP5210004814412 Dec 20221 Jul 202430 Jun 2026Extended 23 mo0
NandanvanWh Constructions Through Its Proprietor Mr Anil Wamanrao ShindeP521000474862 Nov 202231 Dec 202431 Dec 2024Promised date passed0
Ra CasaLohia Jain Realty LLPP521000343444 Apr 202231 Mar 202531 Mar 2025Promised date passed0
Green ValleyMosiac Land Developers Private LimitedP5210003401817 Mar 202230 Jun 202830 Jun 2028Not yet due0
Flow BavdhanVmc Landmark Realty LLPP5210003394214 Mar 202231 Mar 202631 Mar 2026Promised date passed0
Rising HillsPravin Keshav BadhekarP5210003349522 Feb 202231 Mar 202531 Aug 2026Extended 17 mo0
Sai KunjChoulwar ConstructionP5210002593931 Jul 202031 Jan 202331 Jul 2023Extended 6 mo0
Unika D WingLohia Jain Realty Unit No. 2P5210002533730 Apr 202030 Dec 202230 Dec 2022Promised date passed0
Silver Brook Wing ABehede Properties LLPP5210002438310 Feb 202030 Mar 202330 Mar 2023Promised date passed0
AnandvanAnil WamanRao ShindeP521000237936 Jan 202030 Dec 202330 Dec 2023Promised date passed0
Angelle Hills Version T- 9-12 FloorButtepatil Project Pvt LtdP521000218738 Aug 201930 Dec 202331 Aug 2025Extended 20 mo0
Siddh AmaraSiddh HousingP5210001997215 Mar 201930 Dec 202311 Jul 2024Extended 7 mo0
FortunaKetan RuikarP5210001856513 Nov 201830 Sep 202030 Sep 2020Promised date passed0
VrindavanAnil WamanRao ShindeP5210001685320 Jun 201830 Jun 202230 Jun 2022Promised date passed0
OdelaLohia Jain Housing Company LLPP5210001470626 Dec 201730 Jan 202530 Jan 2025Promised date passed0

Other localities in Haveli

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Anil WamanRao Shinde2 projects
  2. Behede Properties LLP2 projects
  3. Marvel Omega Builders Pvt Ltd2 projects
  4. Samarthshree Developers2 projects
  5. Saniket Infrastructures2 projects
  6. Sharada Shrikalp Promoters & Builders2 projects
  7. Siddh Housing2 projects
  8. Vmc Landmark Realty LLP2 projects
  9. Buttepatil Project Pvt Ltd1 project
  10. Choulwar Construction1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology