Elite Regency
Deedo IDDP-PUN-BSFPCompletion was pushed back 1 year and 11 months to Jun 2026, and that date has passed too; no MahaRERA orders on record; 17% of its units are booked.
Bavdhan Kh., Pune 411021 · by Kavya Buildcon
Buying a flat here?
See every deed registered on it.
Completion was pushed back 1 year and 11 months to Jun 2026, and that date has passed too
- This projectRegistered 12 Dec 2022, completion promised 1 Jul 2024, revised to 30 Jun 2026, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100048144
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100048144 | 12 Dec 2022 | 1 Jul 2024 | 30 Jun 2026 | Kavya Buildcon | Project page |
Documents151
2 documents held by Deedo, 149 filings listed on MahaRERA's project page
Finance
- PAN CardPAN.pdf · uploaded 3 Sep 2022Source
Legal
Show all 151 documentsShow fewer documents
Migrated
- 1 Building Plan Approval / NA Order for plotted developmentBuilding Plan.PDF · uploaded 3 Sep 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentCC_compressed.pdf · uploaded 3 Sep 2022Source
- 2 Commencement Certificates / NA Order for plotted developmentCC 1_compressed.pdf · uploaded 3 Sep 2022Source
- 1 CERSAI detailsCersai Report.pdf · uploaded 3 Sep 2022Source
- 1 a Details of encumbrances concerned to FinanceSELF DECLRATION REGARDING ENCUMBRANCES CONCERNED TO FINANCE.pdf · uploaded 7 Sep 2022Source
- 1 b Details of encumbrances concerned to LegalSELF DECLRATION REGARDING ENCUMBRANCES CONCERNED TO LEGAL.pdf · uploaded 7 Sep 2022Source
- 1 Declaration about Commencement CertificateDECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf · uploaded 7 Sep 2022Source
- 1 Declaration in FORM BForm B_Authority.pdf · uploaded 7 Sep 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_compressed.pdf · uploaded 7 Sep 2022Source
- 1 Deviation Report with respect to Allotment letterDEVIATION REPORT WITH RESPECT TO ALLOTMENT LETTER.pdf · uploaded 7 Sep 2022Source
- 1 Deviation Report with respect to model copy of AgreementDEVIATION REPORT WITH RESPECT TO MODEL DRAFT AGREEMENT.pdf · uploaded 7 Sep 2022Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration about Separate Bank Account for real estate projects.pdf · uploaded 15 Sep 2022Source
- 1 Proforma of Agreement for saleRera Allotment Letter.pdf · uploaded 20 Sep 2022Source
- 1 Proforma of Allotment letterRera Allotment Letter.pdf · uploaded 20 Sep 2022Source
- 2 Proforma of Allotment letterDraft Agreement as per RERA.pdf · uploaded 20 Sep 2022Source
- 2 Proforma of Agreement for saleDraft Agreement as per RERA.pdf · uploaded 20 Sep 2022Source
- 1 Copy of the legal title reportSearch Title Report Latest_compressed.pdf · uploaded 8 Nov 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 dec 2022.pdf · uploaded 24 Dec 2024Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 sep 2024.pdf · uploaded 24 Dec 2024Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 june 2024.pdf · uploaded 24 Dec 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 march 2024.pdf · uploaded 24 Dec 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 sep 2023.pdf · uploaded 24 Dec 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 june 2023.pdf · uploaded 24 Dec 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 march 2023.pdf · uploaded 24 Dec 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 dec 2023.pdf · uploaded 24 Dec 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 dec 2023.pdf · uploaded 24 Dec 2024Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 sep 2024.pdf · uploaded 24 Dec 2024Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 june 2024.pdf · uploaded 24 Dec 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 march 2024.pdf · uploaded 24 Dec 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 sep 2023.pdf · uploaded 24 Dec 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 june 2023.pdf · uploaded 24 Dec 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 march 2023.pdf · uploaded 24 Dec 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 dec 2022.pdf · uploaded 24 Dec 2024Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 sep 2024.pdf · uploaded 24 Dec 2024Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 june 2024.pdf · uploaded 24 Dec 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 march 2024.pdf · uploaded 24 Dec 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 dec 2023.pdf · uploaded 24 Dec 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 sep 2023.pdf · uploaded 24 Dec 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 march 2023.pdf · uploaded 24 Dec 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 dec 2022.pdf · uploaded 24 Dec 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 june 2023.pdf · uploaded 24 Dec 2024Source
- 7 Disclosure of sold/ booked inventoryInventory Disclosure march 2024.pdf · uploaded 24 Dec 2024Source
- 9 Disclosure of sold/ booked inventoryInventory Disclosure sep 2024.pdf · uploaded 24 Dec 2024Source
- 8 Disclosure of sold/ booked inventoryInventory Disclosure june 2024.pdf · uploaded 24 Dec 2024Source
- 6 Disclosure of sold/ booked inventoryinventory disclosure dec 2023.pdf · uploaded 24 Dec 2024Source
- 5 Disclosure of sold/ booked inventoryInventory disclosure sep 2023.pdf · uploaded 24 Dec 2024Source
- 4 Disclosure of sold/ booked inventoryInventory disclosure june 2023.pdf · uploaded 24 Dec 2024Source
- 3 Disclosure of sold/ booked inventoryInventory disclosure march 2023.pdf · uploaded 24 Dec 2024Source
- 2 Disclosure of sold/ booked inventoryInventory disclosure dec 2022.pdf · uploaded 24 Dec 2024Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 FY 2022-2023.pdf · uploaded 24 Dec 2024Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)form 5 FY 2023-2024.pdf · uploaded 24 Dec 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form- 1 Dec 2024.pdf · uploaded 5 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 Dec 2024.pdf · uploaded 5 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form- 2 Dec 2024.pdf · uploaded 5 Feb 2025Source
- 1 Disclosure of sold/ booked inventoryDisclosure of Inventory Dec 2024.pdf · uploaded 5 Feb 2025Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest Sumit.pdf · uploaded 5 Feb 2025Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest Ganesh.pdf · uploaded 5 Feb 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A F Y 2022 23.pdf · uploaded 5 Feb 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form- 5 FY 2022-2023.pdf · uploaded 5 Feb 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A F Y 2023 24.pdf · uploaded 5 Feb 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form- 5 FY 2023-2024.pdf · uploaded 5 Feb 2025Source
- Form 1Form 1 dec 2022.pdf · uploaded 28 Jul 2026Source
- Form 2Form 2 dec 2022.pdf · uploaded 28 Jul 2026Source
- Form 3Form 3 dec 2022.pdf · uploaded 28 Jul 2026Source
- Disclosure of Sold and Booked InventoryInventory disclosure dec 2022.pdf · uploaded 28 Jul 2026Source
- Form 1Form 1 march 2023.pdf · uploaded 28 Jul 2026Source
- Form 2Form 2 march 2023.pdf · uploaded 28 Jul 2026Source
- Form 3Form 3 march 2023.pdf · uploaded 28 Jul 2026Source
- Disclosure of Sold and Booked InventoryInventory disclosure march 2023.pdf · uploaded 28 Jul 2026Source
- Form 1Form 1 june 2023.pdf · uploaded 28 Jul 2026Source
- Form 2Form 2 june 2023.pdf · uploaded 28 Jul 2026Source
- Form 3Form 3 june 2023.pdf · uploaded 28 Jul 2026Source
- Disclosure of Sold and Booked InventoryInventory disclosure june 2023.pdf · uploaded 28 Jul 2026Source
- Form 1Form 1 sep 2023.pdf · uploaded 28 Jul 2026Source
- Form 2Form 2 sep 2023.pdf · uploaded 28 Jul 2026Source
- Form 3Form 3 sep 2023.pdf · uploaded 28 Jul 2026Source
- Disclosure of Sold and Booked InventoryInventory disclosure sep 2023.pdf · uploaded 28 Jul 2026Source
- Form 1Form 1 dec 2023.pdf · uploaded 28 Jul 2026Source
- Form 2Form 2 dec 2023.pdf · uploaded 28 Jul 2026Source
- Form 3Form 3 dec 2023.pdf · uploaded 28 Jul 2026Source
- Disclosure of Sold and Booked Inventoryinventory disclosure dec 2023.pdf · uploaded 28 Jul 2026Source
- Form 1Form 1 march 2024.pdf · uploaded 28 Jul 2026Source
- Form 2Form 2 march 2024.pdf · uploaded 28 Jul 2026Source
- Form 3Form 3 march 2024.pdf · uploaded 28 Jul 2026Source
- Disclosure of Sold and Booked InventoryInventory Disclosure march 2024.pdf · uploaded 28 Jul 2026Source
- Form 1Form 1 june 2024.pdf · uploaded 28 Jul 2026Source
- Form 2Form 2 june 2024.pdf · uploaded 28 Jul 2026Source
- Form 3Form 3 june 2024.pdf · uploaded 28 Jul 2026Source
- Disclosure of Sold and Booked InventoryInventory Disclosure june 2024.pdf · uploaded 28 Jul 2026Source
- Form 1Form- 1 Dec 2024.pdf · uploaded 28 Jul 2026Source
- Form 2Form- 2 Dec 2024.pdf · uploaded 28 Jul 2026Source
- Form 3Form-3 Dec 2024.pdf · uploaded 28 Jul 2026Source
- Disclosure of Sold and Booked InventoryInventory Disclosure sep 2024.pdf · uploaded 28 Jul 2026Source
- Form 5 (FY 2022-2023)Form- 5 FY 2022-2023.pdf · uploaded 28 Jul 2026Source
- Form 5 (FY 2023-2024)Form- 5 FY 2023-2024.pdf · uploaded 28 Jul 2026Source
- Form 1Form 1 March 25.pdf · uploaded 7 Sep 2026Source
- Form 2Form 2 March 25.pdf · uploaded 7 Sep 2026Source
- Form 3Form 3 march 25.pdf · uploaded 7 Sep 2026Source
- Disclosure of Sold and Booked InventoryInventory.pdf · uploaded 7 Sep 2026Source
- Withdrawal Update Form 1Form- 1 Dec 2024.pdf · uploaded 7 Sep 2026Source
- Withdrawal Update Form 2Form 2 June 25.pdf · uploaded 7 Sep 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 7 Sep 2026Source
- Withdrawal Update Form 1Form 1 June 25.pdf · uploaded 8 Sep 2026Source
- Withdrawal Update Form 1Form 1 Sept 25.pdf · uploaded 8 Sep 2026Source
- Withdrawal Update Form 1Form 1 Dec 25.pdf · uploaded 8 Sep 2026Source
- Withdrawal Update Form 1Form 1 Mar 26.pdf · uploaded 8 Sep 2026Source
- Withdrawal Update Form 1Form 1 June 26.pdf · uploaded 8 Sep 2026Source
- Withdrawal Update Form 2Form 2 June 25.pdf · uploaded 8 Sep 2026Source
- Withdrawal Update Form 2Form 2 Sept 25.pdf · uploaded 8 Sep 2026Source
- Withdrawal Update Form 2Form 2 Dec 25.pdf · uploaded 8 Sep 2026Source
- Withdrawal Update Form 2Form 2 March 26.pdf · uploaded 8 Sep 2026Source
- Withdrawal Update Form 2Form 2 June 26.pdf · uploaded 8 Sep 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 8 Sep 2026Source
- Withdrawal Update Form 3Form 3 Sep 25.pdf · uploaded 8 Sep 2026Source
- Withdrawal Update Form 3Form 3 Dec 25.pdf · uploaded 8 Sep 2026Source
- Withdrawal Update Form 3Form 3 March 26.pdf · uploaded 8 Sep 2026Source
- Withdrawal Update Form 3Form 3 June 2026.pdf · uploaded 8 Sep 2026Source
- Form 2A (FY 2022-2023)FORM 2A F Y 2022 23.pdf · uploaded 9 Oct 2026Source
- Form 2A (FY 2023-2024)FORM 2A F Y 2023 24.pdf · uploaded 9 Oct 2026Source
- Form 2A (FY 2024-2025)Form 2A.pdf · uploaded 9 Oct 2026Source
- Form 2A (FY 2025-2026)Form 2A.pdf · uploaded 9 Oct 2026Source
- Form 5 (FY 2025-2026)Form 5.pdf · uploaded 10 Oct 2026Source
Technical
Technical (Architect)
- DocumentForm 1 dec 2022.pdf · uploaded 24 Dec 2024Source
- DocumentForm 1 march 2023.pdf · uploaded 24 Dec 2024Source
- DocumentForm 1 june 2023.pdf · uploaded 24 Dec 2024Source
- DocumentForm 1 sep 2023.pdf · uploaded 24 Dec 2024Source
- DocumentForm 1 dec 2023.pdf · uploaded 24 Dec 2024Source
- DocumentForm 1 march 2024.pdf · uploaded 24 Dec 2024Source
- DocumentForm 1 june 2024.pdf · uploaded 24 Dec 2024Source
- DocumentForm 1 sep 2024.pdf · uploaded 24 Dec 2024Source
- DocumentForm 1 June 26.pdf · uploaded 8 Sep 2026Source
Technical (Engineer)
- DocumentForm 2 dec 2022.pdf · uploaded 24 Dec 2024Source
- DocumentForm 2 march 2023.pdf · uploaded 24 Dec 2024Source
- DocumentForm 2 june 2023.pdf · uploaded 24 Dec 2024Source
- DocumentForm 2 sep 2023.pdf · uploaded 24 Dec 2024Source
- DocumentForm 2 dec 2023.pdf · uploaded 24 Dec 2024Source
- DocumentForm 2 march 2024.pdf · uploaded 24 Dec 2024Source
- DocumentForm 2 june 2024.pdf · uploaded 24 Dec 2024Source
- DocumentForm 2 sep 2024.pdf · uploaded 24 Dec 2024Source
- DocumentForm 2 June 26.pdf · uploaded 8 Sep 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 22/3/3A Plot No. 3, 4 Bavdhan Khurd
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, 3BHK18 units in all
- Address
- 22/3/3A Plot No. 3 and 4 Bavdhan Khurd, LMD Chowk, Opposite Bhagwati Maestros SocietyPIN 411021
- Village
- Bavdhan Kh., Haveli taluka
- Location
- 18.51230, 73.77658
- Land area for this project
- 512 sq m (5,511 sq ft)
- Permissible built-up area
- 1,640 sq m (17,649 sq ft)
- Sanctioned built-up area
- 1,104 sq m (11,879 sq ft)
- Designated bank account
- 229
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
22/3/3A Plot No. 3 and 4 Bavdhan Khurd
Boundaries
- North
- By Plot No2
- South
- part area from S No 22
- East
- By Plot No 4
- West
- By Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking18 units
3 of 18 units booked (17%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 41.31 sq m · 445 sq ft | 6 | 0 |
| 2BHK | 86.48 sq m · 931 sq ft | 6 | 1 |
| 3BHK | 114.93 sq m · 1,237 sq ft | 6 | 2 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Pushan Anand Limaye | — |
| Chartered accountant | Vinay Khambe | — |
| Engineer | Dipak Dattatry Jadhav | — |
| Other | Jeevan Maruti Wagaskar | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Bavdhan Kh.
- Vishwanath Apartment C WINGRERA PR1260002501781
- Fortune AuraRERA P52100080467
- Akashparv CRERA P52100077807
- K Pune Phase 2RERA P52100077301
- Seraph Supremus B WingRERA P52100054897
- Anant ParvatiRERA P52100054451
- The OrchidsRERA P52100054136
- Siddh Amara Phase IIRERA P52100053624
All 35 projects in Bavdhan Kh. · Compare Elite Regency with another project