Skip to content
Residential / Group Housing · 1 building · 74 unitsRERA P52100077807

Akashparv C

Deedo IDDP-PUN-YJRD

Completion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 12% of its units are booked.

Bavdhan Kh., Pune 411021 · by Sharada Shrikalp Promoters & Builders

DeliveryExtended 4 moPromised Dec 2028 · now due Apr 2029RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales12% booked9 of 74 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2029

  • This projectRegistered 7 Nov 2024, completion promised 31 Dec 2028, revised to 30 Apr 2029.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100077807
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000778077 Nov 202431 Dec 202830 Apr 2029Sharada Shrikalp Promoters & BuildersProject page
Documents112

1 document held by Deedo, 111 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN Card.PDF · uploaded 25 Jul 2024Source
  • Other – FinanceDeclaration about Account Number.pdf · uploaded 9 Aug 2024Source
  • Other – FinanceLoan Sanction Letter 80 cr reduced.pdf · uploaded 17 Oct 2024Source
  • Other – FinanceDeclaration about Landowner share.pdf · uploaded 17 Oct 2024Source
  • Other – FinanceDeclaration about Land cost - Nil.pdf · uploaded 29 Oct 2024Source

Legal

  • Declaration Form BAffidavit Cum Declaration FORM B.pdf · uploaded 23 Jul 2024Source
  • Other – LegalBhagwan Mahavir Mandal Letter.pdf · uploaded 9 Aug 2024Source
Show all 112 documentsShow fewer documents

Legal

  • Legal Title reportNew Search Title_compressed.pdf · uploaded 7 Oct 2024Source

Migrated

  • 1 Declaration in FORM BAffidavit Cum Declaration FORM B.pdf · uploaded 23 Jul 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Akashparv C.pdf · uploaded 23 Jul 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentbuilding cc_compressed.pdf · uploaded 23 Jul 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentplan24.pdf · uploaded 23 Jul 2024Source
  • 2 Building Plan Approval / NA Order for plotted developmentplan25.pdf · uploaded 23 Jul 2024Source
  • 3 Building Plan Approval / NA Order for plotted developmentplan26.pdf · uploaded 23 Jul 2024Source
  • 4 Building Plan Approval / NA Order for plotted developmentplan27.pdf · uploaded 23 Jul 2024Source
  • 5 Building Plan Approval / NA Order for plotted developmentplan28.pdf · uploaded 23 Jul 2024Source
  • 6 Building Plan Approval / NA Order for plotted developmentplan29.pdf · uploaded 23 Jul 2024Source
  • 7 Building Plan Approval / NA Order for plotted developmentplan30.pdf · uploaded 23 Jul 2024Source
  • 8 Building Plan Approval / NA Order for plotted developmentplan31.pdf · uploaded 23 Jul 2024Source
  • 9 Building Plan Approval / NA Order for plotted developmentplan32.pdf · uploaded 23 Jul 2024Source
  • 1 Deviation Report with respect to Allotment letterDeviation - Allotement letter.pdf · uploaded 23 Jul 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation - Agreement to Sale.pdf · uploaded 23 Jul 2024Source
  • 1 PAN CardPAN Card.PDF · uploaded 25 Jul 2024Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrances.pdf · uploaded 30 Jul 2024Source
  • 1 Copy of Layout Approval (in case of layout)Layout plan.pdf · uploaded 30 Jul 2024Source
  • 1 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 30 Jul 2024Source
  • 1 Declaration about Commencement CertificateDECLARATION ABOUT COMMENCEMNT CERTIFICATE 2024- Akashparv C.pdf · uploaded 30 Jul 2024Source
  • 1 b Details of encumbrances concerned to LegalEncumbrances.pdf · uploaded 30 Jul 2024Source
  • 1 Other – TechnicalDeclaration about Plot Area.pdf · uploaded 30 Jul 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in other organization Sagar Yadav.pdf · uploaded 30 Jul 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in other organization Vilas Yadav.pdf · uploaded 30 Jul 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 7 Aug 2024Source
  • 2 Other – TechnicalScreenshot of Mail of CC.pdf · uploaded 7 Aug 2024Source
  • 1 Other – LegalBhagwan Mahavir Mandal Letter.pdf · uploaded 9 Aug 2024Source
  • 1 Other – FinanceDeclaration about Account Number.pdf · uploaded 9 Aug 2024Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B Bank Letter.pdf · uploaded 9 Aug 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A.pdf · uploaded 13 Aug 2024Source
  • 3 Other – TechnicalAnnexure A.pdf · uploaded 13 Aug 2024Source
  • 1 Copy of the legal title reportNew Search Title_compressed.pdf · uploaded 7 Oct 2024Source
  • 1 Proforma of Agreement for saleAgreement to Sale - C Wing.pdf · uploaded 7 Oct 2024Source
  • 4 Other – TechnicalCREDAI Membership Details.pdf · uploaded 8 Oct 2024Source
  • 2 a Details of encumbrances concerned to FinanceFinancial Encumbrance revised.pdf · uploaded 9 Oct 2024Source
  • 1 CERSAI detailsCERSAI Search Report - C Wing - Aditya Birla- 09-10-2024.pdf · uploaded 9 Oct 2024Source
  • 2 b Details of encumbrances concerned to LegalFinancial Encumbrance revised.pdf · uploaded 9 Oct 2024Source
  • 2 CERSAI detailsCERSAI_Search_Report_Akashparv 70 Cr.pdf · uploaded 16 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 New_compressed (1).pdf · uploaded 17 Oct 2024Source
  • 3 CERSAI detailsDeclaration of CERSAI.pdf · uploaded 17 Oct 2024Source
  • 3 Other – FinanceLoan Sanction Letter 80 cr reduced.pdf · uploaded 17 Oct 2024Source
  • 2 Other – FinanceDeclaration about Landowner share.pdf · uploaded 17 Oct 2024Source
  • 5 Other – TechnicalForm 2 Latest.pdf · uploaded 17 Oct 2024Source
  • 4 Other – FinanceDeclaration about Land cost - Nil.pdf · uploaded 29 Oct 2024Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDisclosure of Secured - Unsecured Finance with CA.pdf · uploaded 29 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Akashparv C Jan 25.pdf · uploaded 22 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Jan 25_compressed.pdf · uploaded 22 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Akashparv C Jan 25.pdf · uploaded 22 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Akashparv C Jan 25.pdf · uploaded 22 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Jan 25_compressed.pdf · uploaded 22 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Akashparv C Jan 25.pdf · uploaded 22 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Akashparv - April 25.pdf · uploaded 18 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Akashparv April 2025_compressed.pdf · uploaded 18 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 April 25.pdf · uploaded 18 Apr 2025Source
  • 1 Disclosure of sold/ booked inventorySold Book Inventory April 2025.pdf · uploaded 18 Apr 2025Source
  • Disclosure of Sold and Booked InventorySold or Booked Inventory.pdf · uploaded 29 Jul 2025Source
  • Form 3Form 3 July 25 Akashparv.pdf · uploaded 29 Jul 2025Source
  • Form 1Form 1 July 25 Akashparv.pdf · uploaded 29 Jul 2025Source
  • Form 2Form 2.pdf · uploaded 29 Jul 2025Source
  • Form 2A (FY 2024-2025)Form 2A Signed.pdf · uploaded 8 Oct 2025Source
  • Form 1Form 1 Akashparv - April 25.pdf · uploaded 21 Nov 2025Source
  • Form 2Form 2 April 25.pdf · uploaded 21 Nov 2025Source
  • Disclosure of Sold and Booked InventorySold Book Inventory April 2025.pdf · uploaded 21 Nov 2025Source
  • Form 3Form 3 Akashparv April 2025_compressed (1).pdf · uploaded 21 Nov 2025Source
  • Form 1Form 1 Nov 25.pdf · uploaded 1 Dec 2025Source
  • Form 2Form 2 Nov 25.pdf · uploaded 1 Dec 2025Source
  • Form 3Form 3 Nov25_compressed.pdf · uploaded 1 Dec 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold Inventory.pdf · uploaded 1 Dec 2025Source
  • Form 1FORM 1 AKASHPARV JAN 26.pdf · uploaded 16 Mar 2026Source
  • Form 2Form 2 Akashparv C Jan 26.pdf · uploaded 16 Mar 2026Source
  • Form 3Form 3 Akashparv Jan 26_compressed.pdf · uploaded 16 Mar 2026Source
  • Disclosure of Sold and Booked InventoryAKASHPARV - C WING - SOLD UNSOLD - DEC 2025.pdf · uploaded 16 Mar 2026Source
  • Form 1Form 1 April 2026.pdf · uploaded 30 Apr 2026Source
  • Form 2Form 2 April 2026 Akashparv.pdf · uploaded 30 Apr 2026Source
  • Form 3Form 3 April 26 Akashparv_compressed.pdf · uploaded 30 Apr 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Inventory April 2026.pdf · uploaded 30 Apr 2026Source
  • Form 2A (FY 2025-2026)Form 2A 2026.pdf · uploaded 29 Jun 2026Source
  • Form 5 (FY 2024-2025)Form 5 for 2024-25.pdf · uploaded 6 Jul 2026Source
  • Withdrawal Update Form 1Form 1 July 2026.pdf · uploaded 24 Jul 2026Source
  • Withdrawal Update Form 2Form 2 Akashparv C.pdf · uploaded 24 Jul 2026Source
  • Withdrawal Update Form 3Form 3 July 2026.pdf · uploaded 24 Jul 2026Source

Technical

  • Documentplan32.pdf · uploaded 23 Jul 2024Source
  • Documentplan31.pdf · uploaded 23 Jul 2024Source
  • Documentplan30.pdf · uploaded 23 Jul 2024Source
  • Documentplan29.pdf · uploaded 23 Jul 2024Source
  • Documentplan28.pdf · uploaded 23 Jul 2024Source
  • Documentplan27.pdf · uploaded 23 Jul 2024Source
  • Documentplan26.pdf · uploaded 23 Jul 2024Source
  • Documentplan25.pdf · uploaded 23 Jul 2024Source
  • Documentplan24.pdf · uploaded 23 Jul 2024Source
  • DocumentLayout plan.pdf · uploaded 30 Jul 2024Source
  • Other – TechnicalDeclaration about Plot Area.pdf · uploaded 30 Jul 2024Source
  • Other – TechnicalScreenshot of Mail of CC.pdf · uploaded 7 Aug 2024Source
  • Other – TechnicalAnnexure A.pdf · uploaded 13 Aug 2024Source
  • Other – TechnicalCREDAI Membership Details.pdf · uploaded 8 Oct 2024Source
  • Other – TechnicalForm 2 Latest.pdf · uploaded 17 Oct 2024Source

Technical (Architect)

  • DocumentForm 1 Akashparv C Jan 25.pdf · uploaded 22 Jan 2025Source
  • DocumentForm 1 Akashparv C Jan 25.pdf · uploaded 22 Jan 2025Source
  • DocumentForm 1 Akashparv - April 25.pdf · uploaded 18 Apr 2025Source
  • DocumentForm 1 July 2026.pdf · uploaded 14 Jul 2026Source

Technical (Engineer)

  • DocumentForm 2 Akashparv C.pdf · uploaded 23 Jul 2024Source
  • DocumentForm 2 Akashparv C Jan 25.pdf · uploaded 22 Jan 2025Source
  • DocumentForm 2 Akashparv C Jan 25.pdf · uploaded 22 Jan 2025Source
  • DocumentForm 2 April 25.pdf · uploaded 18 Apr 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 15/2/2A

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2 bhk to landowner, 3BHK, 4BHK, 5BHK & more74 units in all
Address
15/2/2A, Bavdhan Road, Chandani ChowkPIN 411021
Village
Bavdhan Kh., Haveli taluka
Land area for this project
3,047 sq m (32,799 sq ft)
Permissible built-up area
22,084 sq m (2,37,714 sq ft)
Sanctioned built-up area
22,084 sq m (2,37,714 sq ft)
Recreational open space
1,266 sq m (13,627 sq ft)
Designated bank account
85
Developed in phases
No

Survey, CTS, gat or plot numbers

15/2/2A

Land as published on MahaRERA's project page

15/2/2A

Boundaries

North
Adjacent Hissa Number 16
South
Part Adjacent Hissa Number 2
East
Open Space and adjacent hissa number 1
West
36m wide DP road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking74 units

9 of 74 units booked (12%), as the promoter reported to MahaRERA

2 bhk to landowner · 1 unit3BHK · 24 units4BHK · 22 units5BHK & more · 27 units
TypeCarpet areaUnitsBooked
2 bhk to landowner113.85 sq m · 1,225 sq ft10
3BHK157.24 sq m · 1,693 sq ft246
4BHK272.31 sq m · 2,931 sq ft142
4BHK286.87 sq m · 3,088 sq ft71
4BHK287.06 sq m · 3,090 sq ft10
5BHK & more312.18 sq m · 3,360 sq ft10
5BHK & more318.29 sq m · 3,426 sq ft90
5BHK & more325.91 sq m · 3,508 sq ft140
Show all 11 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
5BHK & more385.04 sq m · 4,145 sq ft10
5BHK & more490.29 sq m · 5,277 sq ft10
5BHK & more586 sq m · 6,308 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals8

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectCUBIX ARCHITECTS Imran Shaikh—
ArchitectSandeep Hardikar—
Chartered accountantP B Shah—
Chartered accountantPramod B. Shah—
Chartered accountantRishabh R Jain—
Chartered accountantRushabh Jain—
EngineerSandip Naise—
OtherSwarachana Infra—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Bavdhan Kh.

All 35 projects in Bavdhan Kh. · Compare Akashparv C with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology