Others · 17 buildings · 399 unitsRERA P52100021841

Shree Residency

Deedo IDDP-PUN-N8DN

Its promised completion date, Dec 2023, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 100% of its units are booked.

Chikhali, Pune 411062 · Property rates in Chikhali · by Delta Buildcon

Delivery2 yrs 11 mo past duePromised Dec 2023 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales100% booked399 of 399 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Dec 2023, has passed and MahaRERA does not show it completed

  • This projectRegistered 1 Aug 2019, completion promised 30 Dec 2023, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

  • Resale · Jul 2026
Latest registered deeds in this project
MonthFlatKindAreaPriceRecord
Jul 2026A1 Wing · 608Resale377 sq ftView Resale, Jul 2026

17 buildings

Open a building to see every flat, floor by floor.

Show all 17 buildingsShow fewer buildings

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100021841
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000218411 Aug 201930 Dec 202330 Dec 2023Delta BuildconProject page
Documents137

2 documents held by Deedo, 135 filings listed on MahaRERA's project page

Registration certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPAN CARD ORIGINAL.pdf · uploaded 6 Jul 2020Source

Legal

  • Legal Title reportlegal title report273.pdf · uploaded 16 Jul 2019Source
  • Declaration Form BFORMB.pdf · uploaded 16 Jul 2019Source
  • Legal Title reportlegal title report271.pdf · uploaded 23 Jul 2019Source
  • Legal Title reportlegal title report274_1.pdf · uploaded 23 Jul 2019Source
  • Legal Title reportlegal title report274_2.pdf · uploaded 23 Jul 2019Source
Show all 137 documentsShow fewer documents

Legal

  • OtherCERSAI_Search_Report_200218667038_For_Asset_Based_Search_14_08_2021_12_50_42_254 SBI.pdf · uploaded 14 Aug 2021Source

Migrated

  • 1 Copy of the legal title reportlegal title report273.pdf · uploaded 16 Jul 2019Source
  • 1 Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 16 Jul 2019Source
  • 1 Building Plan Approval (IOD)IOD.pdf · uploaded 16 Jul 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement1.pdf · uploaded 16 Jul 2019Source
  • 2 Commencement Certificates / NA Order for plotted developmentCommencement2.pdf · uploaded 16 Jul 2019Source
  • 1 Declaration in FORM BFORMB.pdf · uploaded 16 Jul 2019Source
  • 1 Details of encumbrancesEncumbrance.pdf · uploaded 17 Jul 2019Source
  • 2 Copy of the legal title reportlegal title report271.pdf · uploaded 23 Jul 2019Source
  • 3 Copy of the legal title reportlegal title report274_1.pdf · uploaded 23 Jul 2019Source
  • 4 Copy of the legal title reportlegal title report274_2.pdf · uploaded 23 Jul 2019Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate_compressed.pdf · uploaded 23 Jul 2019Source
  • 1 Certificates of CA (Form 3)ca cert delta.pdf · uploaded 23 Jul 2019Source
  • 1 Proforma of Allotment letterRERA ATS.pdf · uploaded 23 Jul 2019Source
  • 1 PAN CardPAN CARD ORIGINAL.pdf · uploaded 6 Jul 2020Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)30-12-2020.pdf · uploaded 29 Jan 2021Source
  • 2 Building Plan Approval (IOD)IOD Mar-21.pdf · uploaded 29 Jul 2021Source
  • 3 Commencement Certificates / NA Order for plotted developmentComm Cert.pdf · uploaded 29 Jul 2021Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)30-06-2021.pdf · uploaded 29 Jul 2021Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg Certificate_compressed.pdf · uploaded 29 Jul 2021Source
  • 2 Details of encumbrancesRERA-Encumbrance Declaration.pdf · uploaded 2 Aug 2021Source
  • 3 Details of encumbrancesCERSAI_Search_Report_200218667038_For_Asset_Based_Search_14_08_2021_12_50_42_254 SBI.pdf · uploaded 14 Aug 2021Source
  • 3 Building Plan Approval (IOD)IOD-23-06-2021.pdf · uploaded 14 Aug 2021Source
  • 4 Commencement Certificates / NA Order for plotted developmentCC-26-03-2021 1.pdf · uploaded 14 Aug 2021Source
  • 5 Commencement Certificates / NA Order for plotted developmentCC-30-07-2021.pdf · uploaded 14 Aug 2021Source
  • 1 Declaration about Commencement CertificateCircular 32 March-2021 01.pdf · uploaded 14 Aug 2021Source
  • 2 Declaration about Commencement CertificateCircular 32 July-2021.pdf · uploaded 14 Aug 2021Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Cerificate.pdf · uploaded 14 Aug 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)1 Form 2A 032019.pdf · uploaded 14 Aug 2021Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)2 Form 2A 042019.pdf · uploaded 14 Aug 2021Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)3 Form 2A 012020.pdf · uploaded 14 Aug 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)4 Form 2A 022020.pdf · uploaded 14 Aug 2021Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)5 Form 2A 032020.pdf · uploaded 14 Aug 2021Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)6 Form 2A 042020.pdf · uploaded 14 Aug 2021Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)7 Form 2A 012021.pdf · uploaded 14 Aug 2021Source
  • 1 Disclosure of sold/ booked inventoryCircular 29, March-2021 01.pdf · uploaded 14 Aug 2021Source
  • 2 Disclosure of sold/ booked inventoryCircular 29, July-2021 01.pdf · uploaded 14 Aug 2021View
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)Not Applicable.pdf · uploaded 14 Aug 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Not Applicable.pdf · uploaded 14 Aug 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)AUDIT F Y 2019-20.pdf · uploaded 14 Aug 2021Source
  • 1 OtherCERSAI_Search_Report_200218667038_For_Asset_Based_Search_14_08_2021_12_50_42_254 SBI.pdf · uploaded 14 Aug 2021Source
  • 4 Building Plan Approval (IOD)Scan 01.pdf · uploaded 15 Aug 2021Source
  • 5 Building Plan Approval (IOD)Scan 02.pdf · uploaded 15 Aug 2021Source
  • 6 Building Plan Approval (IOD)Scan 03.pdf · uploaded 15 Aug 2021Source
  • 7 Building Plan Approval (IOD)Scan 04.pdf · uploaded 15 Aug 2021Source
  • 8 Building Plan Approval (IOD)Scan 05.pdf · uploaded 15 Aug 2021Source
  • 9 Building Plan Approval (IOD)Scan 06.pdf · uploaded 15 Aug 2021Source
  • 10 Building Plan Approval (IOD)Scan 07.pdf · uploaded 15 Aug 2021Source
  • 11 Building Plan Approval (IOD)Scan 08.pdf · uploaded 15 Aug 2021Source
  • 12 Building Plan Approval (IOD)Scan 09.pdf · uploaded 15 Aug 2021Source
  • 13 Building Plan Approval (IOD)Scan 10.pdf · uploaded 15 Aug 2021Source
  • 14 Building Plan Approval (IOD)Scan 11.pdf · uploaded 15 Aug 2021Source
  • 15 Building Plan Approval (IOD)IMG_0001.pdf · uploaded 15 Aug 2021Source
  • 16 Building Plan Approval (IOD)IMG_0002.pdf · uploaded 15 Aug 2021Source
  • 17 Building Plan Approval (IOD)IMG_0003.pdf · uploaded 15 Aug 2021Source
  • 18 Building Plan Approval (IOD)IMG_0004.pdf · uploaded 15 Aug 2021Source
  • 19 Building Plan Approval (IOD)IMG_0005.pdf · uploaded 15 Aug 2021Source
  • 20 Building Plan Approval (IOD)IMG_0006.pdf · uploaded 15 Aug 2021Source
  • 21 Building Plan Approval (IOD)IMG_0006.pdf · uploaded 15 Aug 2021Source
  • 22 Building Plan Approval (IOD)IMG_0007.pdf · uploaded 15 Aug 2021Source
  • 23 Building Plan Approval (IOD)IMG_0009.pdf · uploaded 15 Aug 2021Source
  • 24 Building Plan Approval (IOD)IMG_0010.pdf · uploaded 15 Aug 2021Source
  • 6 Commencement Certificates / NA Order for plotted developmentIMG_0008.pdf · uploaded 15 Aug 2021Source
  • 7 Commencement Certificates / NA Order for plotted developmentIMG_0011.pdf · uploaded 15 Aug 2021Source
  • 1 CERSAI detailsCERSAI_Search_Report_200225316269_For_Asset_Based_Search_05_12_2021_11_20_47_536.pdf · uploaded 5 Dec 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)audit 2020-21.pdf · uploaded 29 Dec 2021Source
  • 8 Commencement Certificates / NA Order for plotted developmentCC-15-02-2022.pdf · uploaded 6 Mar 2022Source
  • 25 Building Plan Approval (IOD)IMG_0001_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • 26 Building Plan Approval (IOD)IMG_0001_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • 27 Building Plan Approval (IOD)IMG_0002_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • 28 Building Plan Approval (IOD)IMG_0003_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • 29 Building Plan Approval (IOD)IMG_0005_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • 30 Building Plan Approval (IOD)IMG_0006_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • 31 Building Plan Approval (IOD)IMG_0007_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • 32 Building Plan Approval (IOD)IMG_0008_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • 33 Building Plan Approval (IOD)IMG_0009_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • 34 Building Plan Approval (IOD)IMG_0010_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • 35 Building Plan Approval (IOD)IMG_0011_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • 36 Building Plan Approval (IOD)IMG_0012_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • 37 Building Plan Approval (IOD)IMG_0013_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • 38 Building Plan Approval (IOD)IMG_0004_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)RERA AUDIT F Y 2021-22.pdf · uploaded 30 Sep 2022Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Society Registration Certificate C-Wing.pdf · uploaded 8 Mar 2023Source
  • 4 Details of encumbrancesSBI Reconveyance Deed 21-03-2023 1-3_compressed.pdf · uploaded 23 Mar 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q3-2023.pdf · uploaded 11 Oct 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)RERA AUDIT -1-2.pdf · uploaded 26 Oct 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q4-2023.pdf · uploaded 3 Jan 2024Source
  • 2 Status of Formation of Legal Entity (Society/Co Op etc.)Society Registration Certificate A, A1, B-Wing.pdf · uploaded 13 Jan 2024Source

Technical

  • DocumentIOD.pdf · uploaded 16 Jul 2019Source
  • DocumentLAYOUT.pdf · uploaded 16 Jul 2019Source
  • DocumentIOD Mar-21.pdf · uploaded 29 Jul 2021Source
  • DocumentIOD-23-06-2021.pdf · uploaded 14 Aug 2021Source
  • DocumentScan 01.pdf · uploaded 15 Aug 2021Source
  • DocumentScan 02.pdf · uploaded 15 Aug 2021Source
  • DocumentScan 03.pdf · uploaded 15 Aug 2021Source
  • DocumentScan 04.pdf · uploaded 15 Aug 2021Source
  • DocumentScan 05.pdf · uploaded 15 Aug 2021Source
  • DocumentScan 06.pdf · uploaded 15 Aug 2021Source
  • DocumentScan 07.pdf · uploaded 15 Aug 2021Source
  • DocumentScan 08.pdf · uploaded 15 Aug 2021Source
  • DocumentScan 09.pdf · uploaded 15 Aug 2021Source
  • DocumentScan 10.pdf · uploaded 15 Aug 2021Source
  • DocumentScan 11.pdf · uploaded 15 Aug 2021Source
  • DocumentIMG_0001.pdf · uploaded 15 Aug 2021Source
  • DocumentIMG_0002.pdf · uploaded 15 Aug 2021Source
  • DocumentIMG_0003.pdf · uploaded 15 Aug 2021Source
  • DocumentIMG_0004.pdf · uploaded 15 Aug 2021Source
  • DocumentIMG_0005.pdf · uploaded 15 Aug 2021Source
  • DocumentIMG_0006.pdf · uploaded 15 Aug 2021Source
  • DocumentIMG_0006.pdf · uploaded 15 Aug 2021Source
  • DocumentIMG_0007.pdf · uploaded 15 Aug 2021Source
  • DocumentIMG_0009.pdf · uploaded 15 Aug 2021Source
  • DocumentIMG_0010.pdf · uploaded 15 Aug 2021Source
  • DocumentIMG_0001_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • DocumentIMG_0001_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • DocumentIMG_0002_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • DocumentIMG_0003_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • DocumentIMG_0005_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • DocumentIMG_0006_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • DocumentIMG_0007_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • DocumentIMG_0008_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • DocumentIMG_0009_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • DocumentIMG_0010_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • DocumentIMG_0011_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • DocumentIMG_0012_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • DocumentIMG_0013_11zon_11zon.pdf · uploaded 7 Mar 2022Source
  • DocumentIMG_0004_11zon_11zon.pdf · uploaded 7 Mar 2022Source

Technical (Architect)

  • DocumentQ4-2023.pdf · uploaded 3 Jan 2024Source

Technical (Engineer)

  • DocumentEngg Certificate_compressed.pdf · uploaded 29 Jul 2021Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 271, 273

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, 3BHK, Hall, Restroom, Shop399 units in all
Address
271, 273, 274, Jadhavwadi, ChikhaliPIN 411062
Village
Pimpri Chinchawad (M Corp.), Haveli taluka
Land area for this project
6,750 sq m (72,656 sq ft)
Permissible built-up area
25,133 sq m (2,70,529 sq ft)
Sanctioned built-up area
14,224 sq m (1,53,106 sq ft)
Recreational open space
675 sq m (7,270 sq ft)
Designated bank account
171
Developed in phases
Yes

Survey, CTS, gat or plot numbers

271273274

Land as published on MahaRERA's project page

271, 273, 274

Boundaries

North
Gat No 272
South
Gat No 274
East
Gat No 276
West
Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking399 units

399 of 399 units booked (100%), as the promoter reported to MahaRERA

1BHK · 110 units2BHK · 263 units3BHK · 20 unitsHall · 1 unitRestroom · 2 unitsShop · 3 units
BuildingTypeCarpet areaUnitsBooked
A1 Wing1BHK33.35 sq m · 359 sq ft1010
A1 Wing1BHK35 sq m · 377 sq ft1111
A1 Wing2BHK43.74 sq m · 471 sq ft1111
A1 Wing2BHK43.75 sq m · 471 sq ft1111
A1 Wing2BHK47.35 sq m · 510 sq ft1111
A1 Wing2BHK47.38 sq m · 510 sq ft1111
A1 Wing2BHK47.49 sq m · 511 sq ft1111
A1 Wing2BHK47.52 sq m · 512 sq ft1111
Show all 75 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
A Wing1BHK33.31 sq m · 359 sq ft1111
A Wing1BHK34.94 sq m · 376 sq ft88
A Wing2BHK43.74 sq m · 471 sq ft1111
A Wing2BHK47.33 sq m · 509 sq ft1111
A Wing2BHK47.52 sq m · 512 sq ft1111
A Wing3BHK68.65 sq m · 739 sq ft99
A Wing3BHK68.73 sq m · 740 sq ft99
A WingHall159.55 sq m · 1,717 sq ft11
A WingRestroom15.79 sq m · 170 sq ft22
A WingShop24.7 sq m · 266 sq ft11
A WingShop25 sq m · 269 sq ft11
A WingShop52 sq m · 560 sq ft11
B Wing1BHK33.4 sq m · 360 sq ft1212
B Wing1BHK34.92 sq m · 376 sq ft1111
B Wing2BHK43.74 sq m · 471 sq ft1212
B Wing2BHK43.75 sq m · 471 sq ft1212
B Wing2BHK47.16 sq m · 508 sq ft1212
B Wing2BHK47.31 sq m · 509 sq ft1212
B Wing2BHK47.41 sq m · 510 sq ft1212
B Wing2BHK47.48 sq m · 511 sq ft1212
C Wing1BHK29.18 sq m · 314 sq ft33
C Wing1BHK29.41 sq m · 317 sq ft33
C Wing1BHK31.25 sq m · 336 sq ft11
C Wing1BHK32.5 sq m · 350 sq ft66
C Wing1BHK32.79 sq m · 353 sq ft33
C Wing1BHK32.83 sq m · 353 sq ft33
C Wing1BHK33.53 sq m · 361 sq ft33
C Wing1BHK33.58 sq m · 361 sq ft33
C Wing1BHK35.37 sq m · 381 sq ft33
C Wing1BHK35.41 sq m · 381 sq ft22
C Wing1BHK35.43 sq m · 381 sq ft22
C Wing1BHK35.46 sq m · 382 sq ft33
C Wing1BHK36.57 sq m · 394 sq ft33
C Wing1BHK36.69 sq m · 395 sq ft66
C Wing1BHK36.71 sq m · 395 sq ft33
C Wing2BHK40.12 sq m · 432 sq ft33
C Wing2BHK40.19 sq m · 433 sq ft33
C Wing2BHK40.23 sq m · 433 sq ft33
C Wing2BHK40.47 sq m · 436 sq ft22
C Wing2BHK41.36 sq m · 445 sq ft44
C Wing2BHK41.37 sq m · 445 sq ft22
C Wing2BHK41.4 sq m · 446 sq ft33
C Wing2BHK41.42 sq m · 446 sq ft22
C Wing2BHK42.92 sq m · 462 sq ft33
C Wing2BHK42.96 sq m · 462 sq ft55
C Wing2BHK43.04 sq m · 463 sq ft22
C Wing2BHK43.89 sq m · 472 sq ft33
C Wing2BHK43.99 sq m · 474 sq ft33
C Wing2BHK44.03 sq m · 474 sq ft33
C Wing2BHK44.1 sq m · 475 sq ft33
C Wing2BHK44.66 sq m · 481 sq ft22
C Wing2BHK44.68 sq m · 481 sq ft44
C Wing2BHK44.72 sq m · 481 sq ft44
C Wing2BHK44.75 sq m · 482 sq ft22
C Wing2BHK45.14 sq m · 486 sq ft33
C Wing2BHK45.15 sq m · 486 sq ft33
C Wing2BHK45.19 sq m · 486 sq ft33
C Wing2BHK45.21 sq m · 487 sq ft33
C Wing2BHK47.16 sq m · 508 sq ft33
C Wing2BHK47.22 sq m · 508 sq ft33
C Wing2BHK47.23 sq m · 508 sq ft44
C Wing2BHK47.27 sq m · 509 sq ft33
C Wing2BHK48.9 sq m · 526 sq ft33
C Wing2BHK48.92 sq m · 527 sq ft33
C Wing2BHK48.97 sq m · 527 sq ft55
C Wing3BHK47.3 sq m · 509 sq ft11
C Wing3BHK49.11 sq m · 529 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals28

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectKimaya Associates—
Chartered accountantV C A N Associates—
EngineerSarvasiddhant Structural Engineers Pvt Ltd—
OtherAjinkya Lahigude—
OtherKavya Enterprises—
OtherSalini Costrucion—
Registered real estate agentAb Housing Realty Private Limited—
Registered real estate agentAkash Krishna Surwase—
Show all 28 professionalsShow fewer professionals
RoleNameRegistration no.
Registered real estate agentAnton David Balid—
Registered real estate agentBhanwarlal Seervi—
Registered real estate agentCorazon Homes Private Limited—
Registered real estate agentDattatrya Maruti Pawar—
Registered real estate agentGurunath Suresh Kurhade—
Registered real estate agentHemant Sanjay Phuge—
Registered real estate agentManisha Rameshwar Bole—
Registered real estate agentPooja Shriram Talekar—
Registered real estate agentPradip Ajinath Mohite—
Registered real estate agentPrashant Uddhavrao Thorat—
Registered real estate agentRaju Tukaram Hosmani—
Registered real estate agentRameshwar Kashinathrao Bole—
Registered real estate agentRohil Kumar Narayanrao Muley—
Registered real estate agentShyam Kishor—
Registered real estate agentSnehal Mahesh Masulkar—
Registered real estate agentSwapnil Maruti Mhaske—
Registered real estate agentSwapnil Sahebrao Kshirsagar—
Registered real estate agentUmeash Vasant Gaikwad—
Registered real estate agentVijaykumar Ramanjani Bhandari—
Registered real estate agentVivek Suresh Pataskar—

Source: MahaRERA project page. Contact details are not shown.

Shree Residency in numbers

Registered deals, summarised

Deedo has 1 registered document at Shree Residency, from Jul 2026 to Jul 2026: 1 sale.

How many properties have been sold at Shree Residency?
1 sale is registered at Shree Residency, 1 of them a resale.
Where does this data come from?
The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Shree Residency by Deedo, last updated with deals registered in Jul 2026.

Latest deal · Resale · Jul 2026

₹25–50 L

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · registered documents (Index II)Data through is when MahaRERA's project page was last read.Report a problemMethodology