Delayed projects in Maharashtra

8,417 MahaRERA projects in 36 districts are past their promised completion date, and MahaRERA shows no completion for them.

Most overdue first

Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 80 of 169.

ProjectLocalityPromisedRevisedDelivery
Takshila ResidencyDelux AssociatesTemgharThaneDec 2023Jun 20252 yrs 11 mo late
Tanishq ResidencyPrathamesh DevelopersKurlaMumbai SuburbanDec 2023Dec 20252 yrs 11 mo late
Teachers ColonyM S Patel ConstructionSawantwadi (M Cl)SindhudurgDec 2023Dec 20232 yrs 11 mo late
Terra GreensBhagwati GroupSangavadePuneDec 2023Dec 20242 yrs 11 mo late
The Golden MileGracelands HabitatsMoharaiThaneDec 2023Dec 20232 yrs 11 mo late
The SpectrumFuturistic HomesTathwadePuneDec 2023Dec 20232 yrs 11 mo late
Tina ApartmentTina EnterprisesPalgharDec 2023Dec 20232 yrs 11 mo late
Trident BlissTrident InfraconUlaweRaigarhDec 2023Dec 20232 yrs 11 mo late
Trillion PrideTrillion Square Developers LLPUlaweRaigarhDec 2023Dec 20252 yrs 11 mo late
Trinity GreensTrinity Housing Projects LLPMakanePalgharDec 2023Dec 20242 yrs 11 mo late
Tulsi Aangan NxTulsi Gruh Nirman & AssociatesKarjatRaigarhDec 2023Dec 20232 yrs 11 mo late
Taj City Centre and Taj ResidencyK. M. DevelopersLanja (Ct)RatnagiriDec 2023Dec 20232 yrs 11 mo late
Tanaya ResidencyGanesh Sadashiv SoygaonkarGarkhedaAurangabadDec 2023Dec 20232 yrs 11 mo late
Tembhurni Prime City Mall - Wing A - Smart Office - Phase A2Dhariwal And Chhoriya Buildcon Pvt LtdTembhurniSolapurDec 2023Dec 20232 yrs 11 mo late
The AutographOzone Homes Pvt LtdWard FnorthMumbai CityDec 2023Dec 20232 yrs 11 mo late
The Primordial houseSambhavparshva Developers Pvt Ltd.Ward AbcdMumbai CityDec 2023Dec 20232 yrs 11 mo late
Trident 9Yashoda DevelopersSusPuneDec 2023Dec 20232 yrs 11 mo late
Tridhaatu KshitijTridhaatu Construction Private LimitedMumbai CityDec 2023Dec 20232 yrs 11 mo late
Ujjwal VastuVastu Developers and PromotorsTalegaon Dabhade (R)PuneDec 2023Dec 20232 yrs 11 mo late
UK IridiumDamodar Suruchi Developers Pvt. Ltd.BorivaliMumbai SuburbanDec 2023Oct 20242 yrs 11 mo late
V SankalpAtharva DevelopersVadghar (Ct)RaigarhDec 2023Dec 20232 yrs 11 mo late
Vande Mataram DivineSadguru ShelterPashaneRaigarhDec 2023Dec 20252 yrs 11 mo late
Varad EnclaveVarad InfraSangliDec 2023Dec 20242 yrs 11 mo late
Vardhaman Bhoomi ResidencyGandhi & Samani AssociatesBhiwandi (M Corp.)ThaneDec 2023Dec 20242 yrs 11 mo late
Vastu SiddhiVastu DevelopersWadagaon (Ct)PuneDec 2023Dec 20232 yrs 11 mo late
Vrindavan CornerManish Satyadev RaiPanvelRaigarhDec 2023Dec 20232 yrs 11 mo late
Vaishnav Sai 2Matoshree InfrastructureNagpur (M Corp.)NagpurDec 2023Dec 20232 yrs 11 mo late
Vardhaman ResidencySuresh Ghewarchand JainBhuwaneshwar (Ct)RaigarhDec 2023Dec 20232 yrs 11 mo late
Viman PlatinumArk Prem ConstructionsVimannagarPuneDec 2023Dec 20242 yrs 11 mo late
Vishwakarma LayoutVishwakarma Housing Pvt. LtdNanded Waghala (M Corp.)NandedDec 2023—2 yrs 11 mo late
WadalaSurana Developers (wadala) LLPWard FnorthMumbai CityDec 2023Dec 20232 yrs 11 mo late
Windsor ParkKumar BuildersBhoseSataraDec 2023Dec 20232 yrs 11 mo late
Yashashree IIAashish Promoters & BuildersKatrajPuneDec 2023Dec 20232 yrs 11 mo late
Zeus Residency Sale Bldg No.6Balwant DoshiWard FnorthMumbai CityDec 2023Dec 20232 yrs 11 mo late
ZynergyMaa Ashapura DevelopersKurlaMumbai SuburbanDec 2023Nov 20242 yrs 11 mo late
anjaneri heightsSakhare Patil Builders And DevelopersSatara (Ct)AurangabadDec 2023Dec 20232 yrs 11 mo late
jewel heightsJewel Builders and Infraprojects LtdBadlapur (M Cl)ThaneDec 2023Dec 20232 yrs 11 mo late
12eliteVastushree InfraMawalPuneDec 2023Dec 20232 yrs 11 mo late
15cosmoVastushree Infra RealityMawalPuneDec 2023Dec 20232 yrs 11 mo late
AanganAbh Developers Private LimitedAanandwaliNashikDec 2023Dec 20232 yrs 11 mo late
Aashirwad AppartmentAashirwad GroupVaralePuneDec 2023Dec 20232 yrs 11 mo late
Abhiraj BlossomAbhijeet Ashok HembadeAanandwaliNashikDec 2023Dec 20232 yrs 11 mo late
Agrawal DreamsVighnesh Nilesh AgrawalSangli Miraj Kupwad (M Corp.)SangliDec 2023Dec 20232 yrs 11 mo late
Ajinkya HeightsSangita Dattatray BobadePhaltan (M Cl)SataraDec 2023Dec 20232 yrs 11 mo late
Anand HeightsGuru Ganesh DevelopersKondhwa BkPuneDec 2023Dec 20232 yrs 11 mo late
Anantganga Housingg Project Antargat Royal Stone ApartmentBaban Anant PatilUran Islampur (M Cl)SangliDec 2023Dec 20232 yrs 11 mo late
Aniketshree Co. Op. Housing Society LtdSudhir Ashok MandaleKothrudPuneDec 2023Dec 20232 yrs 11 mo late
Anmol Industrial EstateSkf Enterprises Builders & DevelopersVasaiPalgharDec 2023Dec 20232 yrs 11 mo late
Arihant BungalowsMumbai Periphery Projects Development Private LimitedSangli Miraj Kupwad (M Corp.)SangliDec 2023Dec 20242 yrs 11 mo late
Amber ApartmentsChandrakant BatheBanerPuneDec 2023Dec 20232 yrs 11 mo late

Delayed projects by district

SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology