Deedo IDDL-NAN-NANDEDWAGHALA5 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects37
Registrations37
Completion still due1225 past their date
Median extension4 months14% of registrations extended
Regulatory cases2on 1 project
5 in 10 registrations run late here
37 MahaRERA registrations in Nanded Waghala (M Corp.)
8 completed9 not yet due3 extended, not yet due17 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Nanded Waghala (M Corp.)
37 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Palaksh ApartmentSatish Pralhadrao Mahamune | Due Jul 2028, extended 4 mo | — | — |
| Gvc KesharbanShri Ganesh Gvc Buildcon | Due Apr 2030, extended 4 mo | — | — |
| Sanman ShikharShikhar Infra | Due Dec 2029 | — | — |
| Anant EnclaveAnant Realty | Due Dec 2027 | — | — |
| Vidyasagar Park A, B And CJain Buildcon | Due Dec 2031 | — | — |
Nearby: other municipal areas in Nanded
Most active promoters
- Msdevelopers4 projects
- Mr Sanjay Balaprasad Biyani3 projects
- R K Builders & Developers3 projects
- Gvc Developers2 projects
- Amar Constructios1 project
- Anant Realty1 project
- Darak Developers1 project
- Gautam Suresh Nagda1 project
- Jai Kedarnath Enterprises1 project
- Jain Buildcon1 project
Nanded Waghala (M Corp.), in questions
How many projects in Nanded Waghala (M Corp.) run late?
5 in 10 MahaRERA registrations (20 of 37): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nanded Waghala (M Corp.) by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology