RERA projects in Nanded Waghala (M Corp.)
64 projects under 66 MahaRERA registrations, registered 2017–2025. 5% have a completion date extended beyond the one promised.
Locality
64RERA projects
66Registrationssome projects hold several
23Completion still due43 past their completion date, 10 marked completed
12 monthsMedian extension beyond promised date5% of registrations extended
4Regulatory caseson 2 projects
215Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 18 |
| 2018 | 4 |
| 2019 | 2 |
| 2020 | 5 |
| 2021 | 3 |
| 2022 | 4 |
| 2023 | 12 |
| 2024 | 11 |
| 2025 | 7 |
Projects in Nanded Waghala (M Corp.)
64 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Palaksh ApartmentSatish Pralhadrao Mahamune | P51100080868 | 25 Jul 2025 | 31 Mar 2028 | — | Not yet due | 0 |
| DeepjyotiJyoti Deepak Pujari | P51100080553 | 16 Jun 2025 | 31 Mar 2030 | — | Not yet due | 0 |
| Gvc KesharbanShri Ganesh Gvc Buildcon | P51100080491 | 10 Jun 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Sanman ShikharShikhar Infra | P51100079717 | 21 Mar 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Anant EnclaveAnant Realty | P51100079499 | 10 Mar 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Sai EnclaveSiddhi Developers | P51100078770 | 13 Jan 2025 | 31 Mar 2032 | — | Not yet due | 2 |
| Siddhi EnclaveSiddhi Homes | P51100078724 | 8 Jan 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Vidyasagar Park A,b And CJain Buildcon | P51100077894 | 13 Nov 2024 | 31 Dec 2031 | — | Not yet due | 2 |
| Shivneri ParkDattatraya Bharat Patil | P51100077639 | 17 Oct 2024 | 31 Dec 2024 | — | Promised date passed | 0 |
| Shree Rama TownshipShree Rama Construction | P51100077486 | 20 Aug 2024 | 30 Apr 2030 | — | Not yet due | 0 |
| OsrOSR Infrastructure | P51100077249 | 31 Jul 2024 | 30 Sep 2024 | — | Promised date passed | 0 |
| DaffodilDeva Constructions | P51100077171 | 29 Jul 2024 | 5 Jan 2027 | — | Not yet due | 0 |
| RamanujShri Tirumala Civil Work Pvt Ltd | P51100077007 | 16 Jul 2024 | 31 Dec 2028 | — | Not yet due | 0 |
| Padmanabha ResidencyShree Samarth Builders And Developers | P51100055704 | 15 Apr 2024 | 31 Dec 2029 | — | Not yet due | 0 |
| Gvc Gangadham SkyilaGvc Developers | P51100055475 | 2 Apr 2024 | 31 Dec 2028 | — | Not yet due | 0 |
| Prayagraj Amsdevelopers | P51100055397 | 22 Mar 2024 | 30 Jun 2026 | — | Promised date passed | 0 |
| Gvc Siddhi SkyparkSidhi Developers | P51100054962 | 21 Feb 2024 | 31 Mar 2028 | — | Not yet due | 0 |
| Kamal ResidencyAkruti Constructions | P51100054294 | 15 Jan 2024 | 30 May 2026 | — | Promised date passed | 0 |
| Gvc Saptagiri SignatureGvc Developers | P51100051931 | 13 Jul 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Nabhangan ParkRamchandra Bhagwanrao Deshmukh | P51100051043 | 22 May 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Vrandawan ApartmentVisava Developers | P51100050996 | 19 May 2023 | 30 Dec 2025 | — | Promised date passed | 0 |
| Padmavati NagariJyoti Deepak Pujari | P51100050891 | 15 May 2023 | 31 Mar 2028 | — | Not yet due | 0 |
| Bharadiya TowerRaj Associates | P51100050694 | 28 Apr 2023 | 4 Aug 2025 | — | Promised date passed | 0 |
| Shri Swami Samarth HeightsShri Swami Samarth Estates | P51100050651 | 21 Apr 2023 | 31 Mar 2027 | — | Not yet due | 0 |
| Samartha ApartmentSatish Bhanudasrao More | P51100050487 | 17 Apr 2023 | 1 Aug 2028 | — | Not yet due | 0 |
| Krishna Kunj ResidencyShri Krishna Builders | P51100050370 | 5 Apr 2023 | 20 Feb 2026 | — | Promised date passed | 0 |
| Krushna KunjShri Builder | P51100050039 | 6 Mar 2023 | 4 Aug 2025 | — | Promised date passed | 0 |
| Omkar AppartmentDivyaamrit Constructions India Pvt Ltd | P51100050016 | 6 Mar 2023 | 1 Jan 2026 | — | Promised date passed | 0 |
| Anaika HeightsDarak Developers | P51100049655 | 22 Feb 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Infinate OneMayuresh Govind Bodke | P51100049246 | 3 Feb 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Gvc Shagun CityShagun Buildcon | P51100047425, P51100047816 | 31 Oct 2022 | 31 Dec 2025 | — | Promised date passed | 0 |
| Krupasindhu ArcadeKrupasindhu Properties | P51100045657 | 26 May 2022 | 31 Mar 2028 | — | Not yet due | 0 |
| RenukaR K Builders & Developers | P51100034604 | 11 Apr 2022 | 31 Dec 2024 | — | Promised date passed | 0 |
| R R Tilak NagarR K Builders & Developers | P51100031887 | 22 Nov 2021 | 31 Dec 2023 | 31 Mar 2024 | Extended 3 mo | 0 |
| Raj Park TwoMr Sanjay Balaprasad Biyani | P51100031680 | 3 Nov 2021 | 4 Mar 2024 | — | Promised date passed | 0 |
| Mahatma Phule MarketJai Sanman Pvt Ltd | P51100030968 | 29 Sep 2021 | 11 Aug 2025 | — | Promised date passed | 0 |
| Manthan ParkUnited Buildcon | P51100026409 | 17 Sep 2020 | 30 Sep 2022 | 31 Mar 2029 | Extended 78 mo | 0 |
| Shri Vyankatrao Tarodekar Mall Market Vazirabad By Bidder Raj DevelopersMr Sanjay Balaprasad Biyani | P51100024990 | 18 Mar 2020 | 11 Oct 2023 | — | Promised date passed | 0 |
| Shri Govindraj ResidencyShri Govindraj Construction | P51100024429 | 13 Feb 2020 | 30 Dec 2024 | — | Promised date passed | 0 |
| Raj Villa GPravin Balaprasad Biyani | P51100023920 | 14 Jan 2020 | 9 Dec 2020 | — | Promised date passed | 0 |
| Shri ApartmentKk Builders & Developers | P51100022944 | 5 Nov 2019 | 30 Jun 2022 | — | Promised date passed | 0 |
| Gokuldham City Part ARama Developers | P51100020534 | 18 Apr 2019 | 30 Dec 2030 | — | Not yet due | 0 |
| Gvc Gangadham Phase IGvc Developers | P51100018353 | 24 Oct 2018 | 30 Mar 2022 | — | Completed | 0 |
| Gvc Shagun CityShagun Associates | P51100017950, P51100026123 | 28 Sep 2018 | 30 Jun 2024 | — | Completed | 0 |
| Raghunath NagarR K Builders & Developers | P51100015354 | 20 Feb 2018 | 30 Dec 2023 | — | Completed | 0 |
| Gvc Shagun City Phase 1Shagun Associates | P51100015116 | 31 Jan 2018 | 30 Dec 2022 | — | Completed | 0 |
| Sanman WoodsJai Kedarnath Enterprises | P51100014290 | 20 Nov 2017 | 27 Jul 2019 | — | Completed | 0 |
| K K HeightsK K Developers | P51100014171 | 10 Nov 2017 | 30 Dec 2023 | — | Promised date passed | 0 |
| D L InfraGautam Suresh Nagda | P51100013123 | 14 Sep 2017 | 3 Sep 2019 | — | Completed | 0 |
| Raj ParkMr Sanjay Balaprasad Biyani | P51100012601 | 6 Sep 2017 | 29 Oct 2019 | — | Completed | 0 |
| Paldewar CityPraveen Nagnath Paldewar | P51100012289 | 1 Sep 2017 | 31 Jul 2023 | 30 Jul 2024 | Extended 12 mo | 0 |
| Raj Commercial Cum Residentail Building G -FMr Sanjay Balaprasad Biyani | P51100012323 | 1 Sep 2017 | 25 Mar 2019 | — | Completed | 0 |
| Sai HeightsM/S Jinen Developers | P51100012167 | 1 Sep 2017 | 30 Dec 2021 | — | Promised date passed | 0 |
| Apurv Plazamsdevelopers | P51100010599 | 31 Aug 2017 | 31 Jul 2018 | — | Completed | 0 |
| Kasliwal Kadam HeightsKasliwal Constructions | P51100007821 | 18 Aug 2017 | 30 Dec 2021 | — | Promised date passed | 0 |
| Vishwakarma LayoutVishwakarma Housing Pvt. Ltd | P51100008307 | 18 Aug 2017 | 30 Dec 2023 | — | Promised date passed | 0 |
| Kasliwal Infra ProjectsKasliwal Infra Projects | P51100007666 | 17 Aug 2017 | 30 Dec 2023 | — | Promised date passed | 0 |
| Digambar Sadanmsdevelopers | P51100006594 | 14 Aug 2017 | 30 Dec 2019 | — | Promised date passed | 0 |
| Parwati Sadanmsdevelopers | P51100006423 | 14 Aug 2017 | 31 Jul 2019 | — | Promised date passed | 0 |
| Raj Residency HMr Sanjay Balaprasad Biyani | P51100006613 | 14 Aug 2017 | 22 Oct 2018 | — | Completed | 0 |
| Tulsi DevelopersTulsi Developers | P51100005078 | 9 Aug 2017 | 18 Mar 2018 | — | Promised date passed | 0 |
| Center park residencyKetan Kulinkant Nagda | P51100003870 | 6 Aug 2017 | 30 Dec 2021 | — | Promised date passed | 0 |
| SaptagiriSaptagiri Developers | P51100002999 | 4 Aug 2017 | 31 Jan 2018 | — | Promised date passed | 0 |
| Vithai ApartmentsAmar Constructios | P51100002164 | 31 Jul 2017 | 15 Aug 2018 | — | Promised date passed | 0 |
Other localities in Nanded
Most active promoters
By projects registered here, as named on MahaRERA.
- Mr Sanjay Balaprasad Biyani5 projects
- msdevelopers4 projects
- Gvc Developers3 projects
- R K Builders & Developers3 projects
- Jyoti Deepak Pujari2 projects
- Shagun Associates2 projects
- Akruti Constructions1 project
- Amar Constructios1 project
- Anant Realty1 project
- Darak Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology