Project summary
As registered with MahaRERA and published on its project page
- Project type
- Commercial
- Status on MahaRERA
- Active
- Buildings
- 2
- Land area for this project
- 9,757 sq m (1,05,028 sq ft)
- Permissible built-up area
- 28,100 sq m (3,02,467 sq ft)
- Sanctioned built-up area
- 16,720 sq m (1,79,972 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Planning authority
- NANDED WAGHALA CITY MUNICIPAL CORPORATION
- Address
- Municipal House No 2-12-220, Shet Survey No 85, C.T.S No 3419, Vazirabad, Nanded - 431601, KALAMANDIR ROAD, KALAMANDIRPIN 431601
- Designated bank account
- Icici Bank Limited
- Litigation declared by promoter
- Yes
- Financial encumbrance declared
- None declared
Location
Coordinates as published by MahaRERA
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Dec 2029
- Registered
- 21 Mar 2025
- Promised
- 31 Dec 2029
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51100079717 | 21 Mar 2025 | 31 Dec 2029 | — | Shikhar Infra | Project page |
2 buildings
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Commercial Building A | 5 | — |
| Cultural Hall and Auditorium Building B | 6 | — |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
0 units registered
Parking
| Building | Type | Two-wheeler | Four-wheeler | Bus | Visitor | Total |
|---|---|---|---|---|---|---|
| Commercial Building A | Closed/Covered | 0 | 0 | 0 | 0 | 596 |
| Commercial Building A | Open Space | 0 | 0 | 0 | 0 | 0 |
| Cultural Hall and Auditorium Building B | Closed/Covered | 0 | 0 | 0 | 0 | 405 |
| Cultural Hall and Auditorium Building B | Open Space | 0 | 0 | 0 | 0 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Construction progress
Work completed, as the promoter reported it to MahaRERA (Form 1)
Commercial Building A
Cultural Hall and Auditorium Building B
Common areas and amenities
Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.
Documents
50 documents held by Deedo, 67 filings listed on MahaRERA's project page
Others
- Other20 Nov 2024ViewSource
- Other25 Nov 2024ViewSource
- Other25 Nov 2024ViewSource
- Other25 Nov 2024ViewSource
- Other25 Nov 2024ViewSource
- Other25 Nov 2024ViewSource
- Other25 Nov 2024ViewSource
- Other25 Nov 2024ViewSource
- Other25 Nov 2024ViewSource
- Other26 Nov 2024ViewSource
- Other30 Nov 2024ViewSource
- Other30 Nov 2024ViewSource
- Other14 Jan 2025ViewSource
- Other21 Jan 2025ViewSource
- Other21 Jan 2025ViewSource
- Other21 Jan 2025ViewSource
- Other22 Jan 2025ViewSource
- Other5 Feb 2025ViewSource
- Other5 Feb 2025ViewSource
- Other20 Feb 2025ViewSource
- Other31 Jul 2025ViewSource
- Other31 Jul 2025ViewSource
- Other31 Jul 2025ViewSource
- Other5 Aug 2025ViewSource
- Other6 Aug 2025ViewSource
- Other6 Aug 2025ViewSource
- Other6 Aug 2025ViewSource
- Other6 Aug 2025ViewSource
- Other17 Dec 2025ViewSource
- Other17 Dec 2025ViewSource
- Other24 Mar 2026ViewSource
- Other24 Mar 2026ViewSource
- Other25 May 2026ViewSource
- Other25 May 2026ViewSource
- Other20 Jul 2026ViewSource
- Other20 Jul 2026ViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
Document library
- Building Plan Approval / NA Order for plotted development2-8-FBF-Permission Drawing.pdf · uploaded 20 Nov 2024View
- Building Plan Approval / NA Order for plotted development1-8-SBF-Permission Drawing.pdf · uploaded 20 Nov 2024View
- Building Plan Approval / NA Order for plotted development8-8-Site Plan-Layout.pdf · uploaded 20 Nov 2024View
- Building Plan Approval / NA Order for plotted development7-8-area sheet-Permission Drawing.pdf · uploaded 20 Nov 2024View
- Building Plan Approval / NA Order for plotted development6-8-section and elevation-Permission Drawing.pdf · uploaded 20 Nov 2024View
- Building Plan Approval / NA Order for plotted development5-8-SF-Permission Drawing.pdf · uploaded 20 Nov 2024View
- Building Plan Approval / NA Order for plotted development3-8-GF-Permission Drawing.pdf · uploaded 20 Nov 2024View
- Building Plan Approval / NA Order for plotted development4-8-FF-Permission Drawing.pdf · uploaded 20 Nov 2024View
- Commencement Certificates / NA Order for plotted developmentKMT bldg permission.pdf · uploaded 20 Nov 2024View
- Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format-B-ICICI Bank (Latest).pdf · uploaded 20 Nov 2024View
- a Details of encumbrances concerned to Finance05 - CERSAI certificate legal.pdf · uploaded 25 Nov 2024View
- b Details of encumbrances concerned to Legal05 - CERSAI certificate legal.pdf · uploaded 25 Nov 2024View
- Declaration about Commencement CertificateFormat D declaration of commencement certificate.pdf · uploaded 25 Nov 2024View
- Declaration in FORM BShikhar - RERA - Form B.pdf · uploaded 25 Nov 2024View
- Copy of Layout Approval (in case of layout)KMT bldg permission.pdf · uploaded 25 Nov 2024View
- Disclosure for secured/unsecured finance availed for the project03 - Discl of finance availed.pdf · uploaded 25 Nov 2024View
- Disclosure of Interest in Other Real Estate OrganizationsCA Mayur Agrawal - Disclosure of Interest in other Real Estate Organisation.pdf · uploaded 25 Nov 2024View
- Declaration about all RERA Designated Bank Accounts (Format A)01 - Order_No_56_2024 (2)-14-17 (1).pdf · uploaded 25 Nov 2024View
- Deviation Report with respect to Allotment letter04 - Deviation Report.pdf · uploaded 25 Nov 2024View
- Other – TechnicalDeclaration landowner.pdf · uploaded 25 Nov 2024View
- CERSAI detailsCersai.pdf · uploaded 25 Nov 2024View
- Other – FinanceKMT-Self Declaration for 3 RERA AC.pdf · uploaded 26 Nov 2024View
- Commencement Certificates / NA Order for plotted developmentNWCMC Confirmation final.pdf · uploaded 30 Nov 2024View
- Deviation Report with respect to model copy of AgreementDeviation Report.pdf · uploaded 30 Nov 2024View
- Proforma of Agreement for saleRERA Latest Agreement to Lease SANMAN SHIKHAR 1.pdf · uploaded 30 Nov 2024View
- Proforma of Allotment letterAllotment letter.pdf · uploaded 30 Nov 2024View
- Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)01 - Order_No_56_2024 (2)-14-17 (1).pdf · uploaded 14 Jan 2025View
- Other – TechnicalANNEXURE ‘A’.pdf · uploaded 14 Jan 2025Source
- Other – TechnicalShikhar Infra - Declaration No of Units.pdf · uploaded 21 Jan 2025View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Shikhar - Architects Certificate.pdf · uploaded 21 Jan 2025View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Shikhar - RERA Engineer's Certificate31-12-24.pdf · uploaded 21 Jan 2025View
- a Details of encumbrances concerned to FinanceShikhar Infra - RERA Declaration on Legal Encumbrances.pdf · uploaded 22 Jan 2025View
- b Details of encumbrances concerned to LegalShikhar Infra - RERA Declaration on Legal Encumbrances.pdf · uploaded 22 Jan 2025View
- Copy of the legal title reportLEGAL TITLE REPORT FINAL.pdf · uploaded 5 Feb 2025View
- Other – TechnicalNWCMC Confirmation final.pdf · uploaded 5 Feb 2025View
- Other – TechnicalSelf declaration affidavit.pdf · uploaded 20 Feb 2025View
- Form 1Shikhar - Architect's Certificate20-4-25.pdf · uploaded 31 Jul 2025View
- Form 2Shikhar - Engineer's Certificate20-4-25.pdf · uploaded 31 Jul 2025View
- Disclosure of Sold and Booked InventoryShikhar - RERA Disclosure of Unsold Invertory31-3-25.pdf · uploaded 31 Jul 2025View
- Form 5 (FY 2024-2025)Shikhar - Form 5 CA Certificate5-8-25.pdf · uploaded 5 Aug 2025View
- Form 2A (FY 2024-2025)Shikhar - Form 2A Engineer's Certificate for Quality Assurance20-7-25 (1).pdf · uploaded 6 Aug 2025View
- Form 1Shikhar - Architect's Certificate20-7-25.pdf · uploaded 6 Aug 2025View
- Form 2Shikhar - Engineer's Certificate20-7-25.pdf · uploaded 6 Aug 2025View
- Disclosure of Sold and Booked InventoryShikhar - RERA Disclosure of Unsold Invertory30-6-25.pdf · uploaded 6 Aug 2025View
- Withdrawal Update Form 1Shikhar - Architectu0027s Certificate20-7-25.pdf · uploaded 30 Sep 2025View
- Withdrawal Update Form 2Shikhar - Engineeru0027s Certificate20-7-25.pdf · uploaded 30 Sep 2025View
- Withdrawal Update Form 1Architect Certificate Q2 25-26.pdf · uploaded 17 Dec 2025View
- Withdrawal Update Form 2Engineer Certificate Q2 25-26.pdf · uploaded 17 Dec 2025View
- Withdrawal Update Form 1Shikhar RERA Form-1 Architects Certificate 31-12-25.pdf · uploaded 24 Mar 2026View
- Withdrawal Update Form 2Shikhar RERA Form-2 Engineers Certificate 31-12-25.pdf · uploaded 24 Mar 2026View
- Withdrawal Update Form 1From-1 Architect Certificate.pdf · uploaded 25 May 2026View
- Withdrawal Update Form 2From-2 Engineer Certificate.pdf · uploaded 25 May 2026View
- Withdrawal Update Form 1Form 1- Architecture Certificate (Jun26).pdf · uploaded 20 Jul 2026View
- Withdrawal Update Form 2Form 2 - Engineer Certificate (Jun26).pdf · uploaded 20 Jul 2026View
Promoter documents
Technical documents
- Layout ApprovalKMT bldg permission.pdfView
- Building Plan Approval1-8-SBF-Permission Drawing.pdfView
- Building Plan Approval2-8-FBF-Permission Drawing.pdfView
- Building Plan Approval3-8-GF-Permission Drawing.pdfView
- Building Plan Approval4-8-FF-Permission Drawing.pdfView
- Building Plan Approval5-8-SF-Permission Drawing.pdfView
- Building Plan Approval6-8-section and elevation-Permission Drawing.pdfView
- Building Plan Approval7-8-area sheet-Permission Drawing.pdfView
- Building Plan Approval8-8-Site Plan-Layout.pdfView
Financial documents
- Other – FinanceKMT-Self Declaration for 3 RERA AC.pdf · uploaded 26 Nov 2024View
Proforma allotment letter
- Proforma allotment letterAllotment letter.pdfView
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Nanded Waghala (M Corp.), Nanded taluka
Survey, CTS, gat or plot numbers
As published on MahaRERA's project page
Municipal House No 2-12-220, Shet Survey No 85, C.T.S No 3419, Vazirabad, Nanded - 431601
Boundaries
- North
- Land Bearing Cts No 3422 3423
- South
- Somesh Colony Road
- East
- Workshop - Ayurvedic College Road
- West
- Land Bearing Cts No 3443 3444 3445
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ar. Hitesh Patel & Associates | — |
| Chartered accountant | Aditya Falor & Associates | — |
| Chartered accountant | Mayur Praful Agrawal | — |
| Engineer | A M Adil | — |
Source: MahaRERA project page. Contact details are not shown.