Deedo IDDL-NAN-NANDED6 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects105in 10 localities
Registrations109some projects hold several
Completion still due4053 past their date
Median extension4 months25% of registrations extended
Regulatory cases10on 8 projects
6 in 10 registrations run late here
109 MahaRERA registrations in Nanded and the places within it
10 completed19 not yet due21 extended, not yet due43 past even the latest date16 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Nanded
105 projects registered with MahaRERA in this district and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Madhaswad Realty Phase-1Madhaswad Realty LLP | Due Dec 2033 | — | — |
| Padmavati Empire B1Padmavati Developers | Due Aug 2029, extended 4 mo | — | — |
| Lotus HeightsM. M. Developers | Due Jul 2029, extended 4 mo | — | — |
| Jinen SquareJinen Infra | Due Apr 2031, extended 4 mo | — | — |
| Kuber ResidencyNeev Enterprises | Due Jul 2030, extended 4 mo | — | — |
Localities in Nanded
- Nanded Waghala (M Corp.)37 projects
- Wadi Bk.29 projects
- Koutha12 projects
- Nanded11 projects
- Dharmabad (M Cl)2 projects
- Nanded2 projects
- Deglur (M Cl)1 project
- Taroda Kh.1 project
- Vasarni1 project
- Wajirabad1 project
Other districts
Most active promoters
- Gvc Developers5 projects
- Mr Sanjay Balaprasad Biyani5 projects
- Msdevelopers4 projects
- Pharande Developers3 projects
- R K Builders & Developers3 projects
- Divyaamrit Constructions India Pvt Ltd2 projects
- Jyoti Deepak Pujari2 projects
- Osr Infrastructure2 projects
- Padmavati Developers2 projects
- Shagun Associates2 projects
Nanded, in questions
How many projects in Nanded run late?
6 in 10 MahaRERA registrations (64 of 109): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nanded by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology