RERA projects in Vimannagar
5 projects under 5 MahaRERA registrations, registered 2017–2018. 60% have a completion date extended beyond the one promised.
Locality
5RERA projects
5Registrations
0Completion still due5 past their completion date
18 monthsMedian extension beyond promised date60% of registrations extended
0Regulatory casesnone on MahaRERA's lists
6Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 4 |
| 2018 | 1 |
Projects in Vimannagar
5 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Suvidhi ApartmentCosmo Lifescapes LLP | P52100015773 | 26 Mar 2018 | 30 Jun 2022 | 31 Dec 2023 | Extended 18 mo | 0 |
| Srrinivas SskyDippak Ravindra Wani | P52100010603 | 13 Nov 2017 | 31 Dec 2017 | 31 Dec 2017 | Promised date passed | 0 |
| NikunjVastushilp housing | P52100010212 | 24 Aug 2017 | 1 Jul 2018 | 1 Jul 2018 | Promised date passed | 0 |
| Viman PlatinumArk Prem Constructions | P52100000914 | 25 Jul 2017 | 30 Dec 2023 | 29 Dec 2024 | Extended 12 mo | 0 |
| Alfa Premio Phase 1Ark Prem Constructions | P52100000855 | 23 Jul 2017 | 30 Sep 2018 | 31 Dec 2025 | Extended 87 mo | 0 |
Other localities in Haveli
Most active promoters
By projects registered here, as named on MahaRERA.
- Ark Prem Constructions2 projects
- Cosmo Lifescapes LLP1 project
- Dippak Ravindra Wani1 project
- Vastushilp housing1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology