Its promised completion date, Dec 2023, has passed and MahaRERA does not show it completed; no MahaRERA orders on record.

Nanded Waghala (M Corp.), Nanded 431603 · by Vishwakarma Housing Pvt. Ltd

Delivery2 yrs 11 mo past duePromised Dec 2023 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has read

Buying a flat here?

See every deed registered on it.

Its promised completion date, Dec 2023, has passed and MahaRERA does not show it completed

  • This projectRegistered 18 Aug 2017, completion promised 30 Dec 2023, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.
Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51100008307
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5110000830718 Aug 201730 Dec 2023—Vishwakarma Housing Pvt. LtdProject page
Documents25

11 documents held by Deedo, 14 filings listed on MahaRERA's project page

Title report

Encumbrance details

Form B

Form 1

Form 2

Commencement certificate

Registration certificate

Other (2)

Show all 25 documentsShow fewer documents

Other (2)

Layout plan

Allotment letter

Document library

  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Vishwakarma Architect Certificate.pdf · uploaded 29 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Vishwakarma Engineeer Certificate.pdf · uploaded 29 Jul 2017View
  • Details of encumbrancesVishwakarma Non Encumbrance Declaration.pdf · uploaded 29 Jul 2017View
  • Declaration in FORM BAffadavit cum declaration.pdf · uploaded 29 Jul 2017View
  • Copy of the legal title reportVishwakarma Title Report.pdf · uploaded 29 Jul 2017View
  • Copy of Layout Approval (in case of layout)Layout Clear2.pdf · uploaded 29 Jul 2017View
  • Proforma of Allotment letterVishwakarma Kararnama Copy with correction.pdf · uploaded 29 Jul 2017View
  • Building Plan Approval (IOD)Layout Clear2.pdf · uploaded 29 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentNA Order.pdf · uploaded 13 Apr 2018View

Promoter documents

  • Declaration Form BAffadavit cum declaration.pdf · uploaded 29 Jul 2017View
  • Legal Title reportVishwakarma Title Report.pdf · uploaded 29 Jul 2017View

Technical documents

  • Layout ApprovalLayout Clear2.pdfView
  • NA Order for Plotted DevelopmentLayout Clear2.pdfView

Proforma allotment letter

  • Proforma allotment letterVishwakarma Kararnama Copy with correction.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 49/1/2 Pt

As registered with MahaRERA and published on its project page

Project type
Plotted
Status on MahaRERA
Lapsed
Address
49/1/2 PtPIN 431603
Village
Nanded Waghala (M Corp.), Nanded taluka
Land area for this project
20,905 sq m (2,25,015 sq ft)
Permissible built-up area
0 sq m (0 sq ft)
Sanctioned built-up area
0 sq m (0 sq ft)
Recreational open space
4,205 sq m (45,262 sq ft)
Designated bank account
Yes Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Survey, CTS, gat or plot numbers

49/1/2 Pt

Land as published on MahaRERA's project page

49/1/2 Pt

Boundaries

North
S no 49 Pt
South
18 m wide Road
East
S no 49 Pt and 48
West
S no 50

Source: registration certificates and MahaRERA's project page, as stated there.

Construction progress2 buildings and areas

Work completed, as the promoter reported it to MahaRERA (Form 1)

Building

  • ExcavationNot applicable
  • Basement (if any)Not applicable
  • Podiums (if any)Not applicable
  • PlinthNot applicable
  • Stilt FloorNot applicable
  • Slabs of Super StructureNot applicable
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
  • Sanitary Fittings within the flats / premisesNot applicable
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Common areas and amenities

  • Internal Roads & FootpathsWBM Road27%
  • Water SupplyNot applicable
  • Sewerage (Chamber, Lines, Septic Tank , STP)Not applicable
  • Storm Water DrainsWork in Progress90%
  • Landscaping & Tree PlantingTree Plantation50%
  • Street LightingWorking Area50%
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPurohit & Associates—
EngineerMadanant Vastu Consultancy—

Source: MahaRERA project page. Contact details are not shown.