2,215 MahaRERA projects in Pune are past their promised completion date, and MahaRERA shows no completion for them.

Most overdue first

Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 38 of 45.

ProjectLocalityPromisedRevisedDelivery
Krushna IconGanesh Dnyanoba BhagatTandulwadiDec 2025Dec 202511 mo late
Krishnakunj Phase 1Heera DevlopersShindvaneDec 2025Dec 202511 mo late
Krushna KunjMNM DevelopersHaveliDec 2025Dec 202511 mo late
Kushal Sagar VatikaKushal Sagar BuildersDhayari (Part)Dec 2025Dec 202511 mo late
Laxmi HeightsPraaj DevelopersPimpri Chinchawad (M Corp.)Dec 2025Dec 202511 mo late
Little NestArma Apc HousingllpKeshavnagarmundwaDec 2025Dec 202511 mo late
Lotus ShineDreamhomes DevelopersMoshiDec 2025Dec 202511 mo late
Life Republic / Sector R10 / 10th Avenue / Universe / Phase IVKolte-Patil Planet Real Estate Private LimitedJambeDec 2025Dec 202511 mo late
Life Republic Sector R17A/17A Avenue-Sound of Soul/Phase-IKolte-Patil Developers LimitedJambeDec 2025Dec 202511 mo late
Mai ResidencyYashaswi LandmarksKiwaleDec 2025Dec 202511 mo late
Maitri ResidencyDhamale Thorat AssociatesVadgaonsheriDec 2025Dec 202511 mo late
Mangal MurtiJai Ganesh EnterprisesPune (M Corp.)Dec 2025Dec 202511 mo late
MarvelShelter 24KiwaleDec 2025Dec 202511 mo late
MarvellaNew Front Eps VenturesDhayari (Part)Dec 2025Dec 202511 mo late
Mauli PlazaMauli DevelopersPune (M Corp.)Dec 2025Dec 202511 mo late
Metro Vrundavan B BuildingMetro RealtorsPimpriDec 2025Dec 202511 mo late
Mk CrestMk BuildconPimpale GuravDec 2025Dec 202511 mo late
Madni MaskanPride Builders and DevelopersSwargateDec 2025Dec 202511 mo late
MangalmurtiTrimurti PropertiesPune (M Corp.)Dec 2025Dec 202511 mo late
Manoj VillaDream Forge Infra Private LimitedSadashiv PethDec 2025Dec 202511 mo late
Marvel Ribera A BuildingRibera Projects LLPPune (M Corp.)Dec 2025Dec 202511 mo late
Muktai Park Phase IShivshakti BuildconLonikalbhorDec 2025Dec 202511 mo late
Nb CrystalNanasaheb Bhintade Spacess Pvt LtdAmbegaon BkDec 2025Dec 202511 mo late
Nobel PrideNobel ConstructionsPune (M Corp.)Dec 2025Dec 202511 mo late
Noble HeightsNoble DevelopersPune CityDec 2025Dec 202511 mo late
Orrion CapitalAmit Rajendra KudaleNarheDec 2025Dec 202511 mo late
Ozone 24kMilind Bhagwat PokharkarTalegaon Dabhade (M Cl)Dec 2025Dec 202511 mo late
Park Landmark Phase IIIPride Purple Landmark LLPPune (M Corp.)Dec 2025Dec 202511 mo late
Pearl UniconShree Vijayalaxmi DevelopersChakan (Ct)Dec 2025Dec 202511 mo late
PragatiSigma RealtyNereDec 2025Dec 202511 mo late
PresidentiaYellowstone Skyscrapers LLPPune (M Corp.)Dec 2025Dec 202511 mo late
Prisma L Building Cprisma realty pvt ltdBorhadewadiDec 2025Dec 202511 mo late
Priti NirvanaBenyel EngineeringKothrudDec 2025Dec 202511 mo late
Padmavati Hills K WingSuyog City DevelopersBavadhan BkDec 2025Dec 202511 mo late
Pinnacle Neelanchal Phase IIIPinnacle Vastunirman Private LimitedSusDec 2025Dec 202511 mo late
Prabha HeightsAvadhoot ConstructionPimple NilakhDec 2025Dec 202511 mo late
Raghukul ResidencyJai Ganesh DevelopersNarheDec 2025Dec 202511 mo late
Rajashree SerenityRajashree RealtorRahatwadeDec 2025Dec 202511 mo late
Rajgruhi Residency Tower C1Atria ConstructionsPune CityDec 2025Dec 202511 mo late
RamaramanShree Bhawani ConstructionsPune (M Corp.)Dec 2025Dec 202511 mo late
RavikesharNestconKothrudDec 2025Dec 202511 mo late
Ridhisha PrideRandhirsinh Jaywantrao JachakBaramati (M Cl)Dec 2025Dec 202511 mo late
SaffronMs A B Kokate Developers Through Its Proprietor Ambadas Bhairu KokatePashanDec 2025Dec 202511 mo late
Sai ParadiseShree Sai Seva DevelopersDehuDec 2025Dec 202511 mo late
Sai PlanetJsk AssociatesMamurdiDec 2025Dec 202511 mo late
Sai PlazaAditya AssociatesTalegaon Dabhade (R)Dec 2025Dec 202511 mo late
Saksham ApartmentAniket Ravindra PatilMoshiDec 2025Dec 202511 mo late
Sankalp ResidencyMachindra Ganpat PateVarulwadiDec 2025Dec 202511 mo late
Saptasajai Aangan Phse IIGandharva LandmarkKadamwak WastiDec 2025Dec 202511 mo late
Sentosa EkamSai PromotersPunawaleDec 2025Dec 202511 mo late

Delayed projects by district

SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology