RERA projects in Dehu

61 projects under 67 MahaRERA registrations, registered 2017–2026. 22% have a completion date extended beyond the one promised.

61RERA projects
67Registrationssome projects hold several
31Completion still due36 past their completion date
21 monthsMedian extension beyond promised date22% of registrations extended
0Regulatory casesnone on MahaRERA's lists
8Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201718
20184
20194
20202
20213
20229
202312
20246
20255
20264

Projects in Dehu

61 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Dwarka HeightsB.G. Realty LLPPM12600026017824 Sep 202631 Dec 2032—Not yet due0
Trimurti Saroj HeightsNageshwar PropertiesPR126000260079915 Jun 202615 Mar 2029—Not yet due0
Shiv Ganesh HeightsPansare BuildconPM126000250269710 Mar 202631 Dec 2028—Not yet due0
Shrushti HeightsDinesh Shivaji HagawanePR12600025019771 Jan 202631 Dec 2027—Not yet due0
Harmony HillsM/s Z Con PropertiesPR126000250031018 Jul 202530 Jun 2029—Not yet due0
VighnahartaPandit Nanabhau MolakP521000804686 Jun 202531 Mar 2030—Not yet due0
Anant EmpireKulswamini Builders and DevelopersPM12600025000655 Jun 202531 Dec 2028—Not yet due0
Rivereast ResidencyKrushna Paradise DevelopersP5210007990529 Mar 20251 Mar 2029—Not yet due0
JDS ResidencyJ D S GroupP5210007984227 Mar 202531 Dec 2026—Not yet due0
Panorama DreamsPanorama VenturesP5210007857827 Dec 202431 Dec 2026—Not yet due0
Success IconSuccess Builders & DevelopersP5210007851019 Dec 202424 Jun 2027—Not yet due0
Kaustubh Realty Plot CSantosh Bhagwandas ZanwarP5210005520911 Mar 202430 Jun 2027—Not yet due0
GovindbaugMayur Manik MoreP5210005495121 Feb 202431 Dec 2027—Not yet due0
Sindhu ParkShubharambh Promoters And BuildersP5210005474512 Feb 202430 Jun 2027—Not yet due0
Aishwarya ParadiseKrushnai RealityP5210005428815 Jan 202431 Dec 2027—Not yet due0
Anandi ViharSanskruti DevelopersP5210005343431 Oct 202331 Dec 2028—Not yet due0
GathagramHarit Landmarks LLPP52100053002, P5210005345610 Oct 202330 Nov 2028—Not yet due0
Keshar ResidencySuccess Builders & DevelopersP5210005298710 Oct 202324 Dec 202424 Mar 2025Extended 3 mo0
AnandsagarMoraya Construction & DevelopersP5210005210024 Jul 20231 Apr 2024—Promised date passed0
Dev ResidencyShiv Pragati DevelopersP5210005172427 Jun 202331 Dec 2030—Not yet due0
KingdomM/S Kingdom BuildconP5210005151823 Jun 202331 Dec 2027—Not yet due0
Radhika ResidencyMybhoomi VastuspaceP5210005148623 Jun 202311 Aug 2026—Promised date passed0
Trimurti Santkrupa HeightsSambhaji Baban BorhadeP5210005015021 Mar 202331 Mar 2027—Not yet due0
GathagramHarit Landmarks LLPP52100049477, P5210004966115 Feb 202330 Mar 2028—Not yet due0
OvitirthRoyal Land DevelopersP521000494278 Feb 202331 Dec 2026—Not yet due0
Prime AvenueM/s Prasad DevelopersP521000478791 Dec 202229 Jun 2026—Promised date passed0
ShivkunjHr DevelopersP5210004708229 Sep 202231 Dec 2026—Not yet due0
Shubh Sangeet ComplexSubhash Eknath ThorveP521000467121 Sep 202231 Dec 2026—Not yet due0
Prithvi ResidencySuccess Builders And DevelopersP5210004540218 May 202224 Oct 2023—Promised date passed0
Sai ParadiseShree Sai Seva DevelopersP5210003490928 Apr 202231 Dec 2025—Promised date passed0
Gorakh HeightsAsanjo Infrastructure LimitedP521000337398 Mar 202231 Dec 2026—Not yet due0
Keshav KunjM/S Sanskruti Developers And BuildersP521000328562 Feb 202231 Dec 202431 Dec 2025Extended 12 mo0
Jagatguru HeightsAmarnath ConstructionP5210003272524 Jan 202230 Dec 202331 Dec 2024Extended 12 mo0
Vrundavan ParkBg AssociatesP521000317749 Nov 202131 Dec 2027—Not yet due0
Midas Regency A BuildingMidas ConstructionsP5210002864325 Mar 202130 Mar 2023—Promised date passed0
Indrayani VatikaSanskruti DevelopersP52100028191, P5210003244310 Feb 202130 Jun 202430 Jun 2025Extended 12 mo0
Laxmi HomesPokar RealtyP521000254633 Jun 20203 Jul 202330 Jun 2024Extended 11 mo0
V Uptown C WingTatvam Constructions Private LimitedP5210002100227 May 201930 Dec 202212 Jun 2024Extended 18 mo0
Royal CassiaMercury Artharaj Landmarks AOPP52100019483, P521000269396 Feb 201928 Feb 202531 Jul 2027Extended 29 mo0
Tathastu Paradise - IIMayur Manik MoreP5210001805810 Oct 201810 Apr 2023—Promised date passed0
Ovi Homes Phase 1Shubharambh RealitiesP5210001792125 Sep 201830 Dec 2024—Promised date passed0
Dwarkadheesh ResidencyHarichandra Rambhau SatavP521000173809 Aug 201830 Jun 202331 Dec 2026Extended 42 mo0
Vrundavan ResidenciesAnil Janardhan SarodeP521000159029 Apr 201828 Feb 2029—Not yet due0
ArunyaGM BuildconP5210001434623 Nov 201731 Dec 202031 Mar 2024Extended 39 mo0
Gurumauli ComplexSahyadri Constructions and Developer CompanyP5210001428220 Nov 201731 Dec 2017—Promised date passed0
IndrayaniMangalmurti Construction And DevelopersP521000129127 Sep 201730 Dec 2021—Promised date passed0
Sadguru ComplexJare Buildcon Pvt LtdP521000129577 Sep 201731 Dec 201930 May 2025Extended 65 mo0
Indrayani VatikaSanskruti DevelopersP5210001097731 Aug 201730 Dec 2023—Promised date passed0
AaradhyaAaradhya InfraP5210001013924 Aug 201730 Dec 2022—Promised date passed0
Abhilasha ParkSarovar Associates, Sarovar AssociatesP52100009755, P5210002352622 Aug 201731 Jul 202330 Apr 2025Extended 21 mo0
Sayali ComplexPandit Nanabhau MolakP5210000828318 Aug 201730 Sep 2020—Promised date passed0
Gulmohar ParkMercury Artharaj Landmarks AOPP52100007126, P5210002307317 Aug 201730 Dec 202329 Dec 2024Extended 12 mo0
Indrayani ComplexSaptshrungi AssocieatsP5210000762917 Aug 201731 Dec 201728 Feb 2022Extended 50 mo0
Shiromani HeightsSudarshan ConstructionP5210000717817 Aug 201730 Dec 2018—Promised date passed0
EktaraArtharaj RealtorsP5210000612914 Aug 201730 Oct 201929 Oct 2021Extended 24 mo0
Krishna ClassicPandurang Maruti KalokheP5210000596514 Aug 20171 Dec 2019—Promised date passed0
Midas RegencyMidas ConstructionsP5210000647314 Aug 201730 Dec 2021—Promised date passed0
Nageshwar PropertiesSambhaji Baban BoradeP5210000609814 Aug 201715 May 2022—Promised date passed0
Gatha AarambhSaffron PropertiesP521000034085 Aug 201730 Dec 2022—Promised date passed0
Tathastu ParadiseMayur Manik MoreP521000034905 Aug 201724 Mar 2019—Promised date passed0
Yashraj PradakshinaRajendra Murlidhar GodboleP5210000063319 Jul 20171 Jan 202130 Jun 2023Extended 29 mo0

Other localities in Haveli

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Mayur Manik More3 projects
  2. Sanskruti Developers3 projects
  3. Harit Landmarks LLP2 projects
  4. Mercury Artharaj Landmarks AOP2 projects
  5. Midas Constructions2 projects
  6. Pandit Nanabhau Molak2 projects
  7. Success Builders & Developers2 projects
  8. Aaradhya Infra1 project
  9. Amarnath Construction1 project
  10. Anil Janardhan Sarode1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology