Prisma L Building C
Deedo IDDP-PUN-QPRDIts promised completion date, Dec 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 62% of its units are booked.
Borhadewadi, Pune 412105 · by Prisma Realty Pvt Ltd · 33% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed
- This projectRegistered 5 Oct 2023, completion promised 31 Dec 2025, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100052934
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100052934 | 5 Oct 2023 | 31 Dec 2025 | 31 Dec 2025 | prisma realty pvt ltd | Project page |
Documents56
1 document held by Deedo, 55 filings listed on MahaRERA's project page
Finance
- PAN Card1 PAN Card.pdf · uploaded 19 Jul 2023Source
Legal
Migrated
- 1 PAN Card1 PAN Card.pdf · uploaded 19 Jul 2023Source
- 1 Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 19 Jul 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentfinal 2.pdf · uploaded 19 Jul 2023Source
- 2 Building Plan Approval / NA Order for plotted developmentfinal 3.pdf · uploaded 19 Jul 2023Source
Show all 56 documentsShow fewer documents
Migrated
- 3 Building Plan Approval / NA Order for plotted developmentfinal 4.pdf · uploaded 19 Jul 2023Source
- 4 Building Plan Approval / NA Order for plotted developmentfinal 5.pdf · uploaded 19 Jul 2023Source
- 5 Building Plan Approval / NA Order for plotted developmentfinal 6.pdf · uploaded 19 Jul 2023Source
- 6 Building Plan Approval / NA Order for plotted developmentfinal 7.pdf · uploaded 19 Jul 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 19 Jul 2023Source
- 1 Declaration about Commencement CertificateDECLARATION ABOUT COMMENCEMENT CETIFICATE.pdf · uploaded 19 Jul 2023Source
- 2 Commencement Certificates / NA Order for plotted developmentNA ORDER 1.pdf · uploaded 21 Jul 2023Source
- 1 Declaration in FORM BForm B CO PROMOTOR.pdf · uploaded 21 Jul 2023Source
- 1 a Details of encumbrances concerned to FinanceEncumbrance certificate land.pdf · uploaded 24 Jul 2023Source
- 1 b Details of encumbrances concerned to LegalEncumbrance certificate land.pdf · uploaded 24 Jul 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate_.pdf · uploaded 24 Jul 2023Source
- 1 CERSAI detailsCERSAI_Search_Report_200275257773_For_Asset_Based_Search_24_07_2023_13_43_07_657.pdf · uploaded 24 Jul 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM3 Compress.pdf · uploaded 24 Jul 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of interest in other real estate organization kaustubh wable.pdf · uploaded 24 Jul 2023Source
- 2 Disclosure of Interest in Other Real Estate Organizationsdisclosure of interest in other real estate organizations aharv.pdf · uploaded 24 Jul 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the samedeclaration about seperate bank account for real estate projects.pdf · uploaded 24 Jul 2023Source
- 1 Deviation Report with respect to Allotment letterDeviation report with respect to agreement to sale.pdf · uploaded 24 Jul 2023Source
- 1 Deviation Report with respect to model copy of AgreementDeviation report with respect to agreement to sale.pdf · uploaded 24 Jul 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Architect’s Certificate on Completion of Project (Form 4).pdf · uploaded 26 Jul 2023Source
- 1 Proforma of Allotment letterALLOTMENT LETTER PRISMA L.pdf · uploaded 26 Jul 2023Source
- 1 Copy of the legal title reportSEARCH REPORT.pdf · uploaded 11 Aug 2023Source
- 1 Proforma of Agreement for saleDRAFT.pdf · uploaded 11 Aug 2023Source
- 2 a Details of encumbrances concerned to Financeencumbrance certificate land (1).pdf · uploaded 12 Aug 2023Source
- 2 b Details of encumbrances concerned to Legalencumbrance certificate land (1).pdf · uploaded 12 Aug 2023Source
- 3 a Details of encumbrances concerned to FinanceEncumbrance Certificate.pdf · uploaded 23 Aug 2023Source
- 3 b Details of encumbrances concerned to LegalEncumbrance Certificate.pdf · uploaded 23 Aug 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECTS CERTIFICATE - PRISMA L C BUILDING.pdf · uploaded 17 Apr 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECTS CERTIFICATE - PRISMA L C BUILDING 2.pdf · uploaded 17 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA - PRISMA L C BUILDING.pdf · uploaded 17 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certifie - PRISMA L C BUILDING.pdf · uploaded 17 Apr 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certifie - PRISMA L C BUILDING 2.pdf · uploaded 17 Apr 2025Source
- Form 2engineer certifie - prisma l c building.pdf · uploaded 11 Jun 2025Source
- Form 1ARCHITECT'S CERTIFICATE - prisma l c building 2024.pdf · uploaded 11 Jun 2025Source
- Form 3CA - prisma l c building (2).pdf · uploaded 11 Jun 2025Source
- Disclosure of Sold and Booked Inventoryprisma L completion letter (1).pdf · uploaded 11 Jun 2025Source
Technical
- DocumentLAYOUT.pdf · uploaded 19 Jul 2023Source
- Documentfinal 2.pdf · uploaded 19 Jul 2023Source
- Documentfinal 3.pdf · uploaded 19 Jul 2023Source
- Documentfinal 4.pdf · uploaded 19 Jul 2023Source
- Documentfinal 5.pdf · uploaded 19 Jul 2023Source
- Documentfinal 6.pdf · uploaded 19 Jul 2023Source
- Documentfinal 7.pdf · uploaded 19 Jul 2023Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel GAT NO. 79 (P) AT BORHADEWADI
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —21 units in all
- Address
- Gat No. 79 (P) At Borhadewadi, Mngl Gas Pump, BorhadewadiPIN 412105
- Village
- Pimpri Chinchawad (M Corp.), Haveli taluka
- Location
- 18.66446, 73.83043
- Land area for this project
- 596 sq m (6,419 sq ft)
- Permissible built-up area
- 1,855 sq m (19,963 sq ft)
- Sanctioned built-up area
- 1,060 sq m (11,408 sq ft)
- Designated bank account
- 86
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
GAT NO. 79 (P) AT BORHADEWADI
Boundaries
- North
- Remaining Property Of Gat No 79
- South
- Remaining Property Of Gat No 79
- East
- Prisma L
- West
- Remaining Property Of Gat No 79
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking21 units
21 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 21 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.