Vadgaonsheri, Pune

4 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects33
Registrations39some projects hold several
Completion still due1425 past their date
Median extension4 months38% of registrations extended
Regulatory cases4on 2 projects
Vadgaonsheri market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

9 in 10 registrations run late here

39 MahaRERA registrations in Vadgaonsheri

4 not yet due10 extended, not yet due25 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Vadgaonsheri

33 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Sai Crystal CourtImpact Builders and DevelopersDue Mar 2030—0%
Eagle NestIlika Realtors4 mo late—0%
Triton ResidencyM/S Sankalp Vastu LLPDue Apr 2030, extended 4 mo—38%
Well Home RiversideSanjay Prabhakar ChaudharyDue Apr 2029, extended 4 mo—0%
Nyati EvoqueNyati Builders Private LimitedDue Apr 2028, extended 4 mo—16%
Signature BelitasSignature Promoters2 yrs 7 mo late—50%
Tower of VisionariesYucca Promoters LLPDue Jul 2028, extended 4 mo——
Royal ResidencyAbdul Rehman Durrani2 yrs 4 mo late—0%
EvanaRohan Karan InfraDue Dec 2027, extended 4 mo—87%
Maitri ResidencyDhamale Thorat Associates10 mo late—60%
Anshul IraS.v. AssociatesDue Apr 2027, extended 4 mo——
Shubh Ganesh IconShubh Ganesh Associates2 yrs 7 mo late—0%
The Collection PremiumBramhacorp LimitedDue Apr 2027, extended 4 mo——
Silicon Bay Phase IIIKaran Janhavi Development Coroporation2 yrs 3 mo late—65%
The Collection - W2 and W7Bramhacorp LimitedDue Jan 2027, extended 4 mo——
Kumar Palaash A1Kumar & Potnis Associates1 yr 3 mo late—100%
Kumar Palaash BKumar & Potnis Associates2 yrs 4 mo late—96%
SamarthNagarArihant Associates7 mo late—43%
Pradnyaraj BudsPradnyaraj Properties2 yrs 10 mo late—71%
Shubh Global StreetShubh Capital2 yrs 4 mo late—0%
Bramhacorp Business Park T9-A2Bramhacorp LimitedDue Apr 2030, extended 4 mo——
The Collection - Residential W8Bramhacorp LimitedDue Apr 2030, extended 4 mo——
The Collection - Commercial W1Bramhacorp LimitedDue Dec 2029——
The Collection - Residential W1Bramhacorp LimitedDue Dec 2029——
Primavera - B6 and S1Kewal Real Estate Developers Private Limited2 yrs 9 mo late—89%

Most active promoters

  1. Bramhacorp Limited8 projects
  2. Kumar & Potnis Associates3 projects
  3. Karan Janhavi Development Coroporation2 projects
  4. Nyati Builders Private Limited2 projects
  5. Abdul Rehman Durrani1 project
  6. Arihant Associates1 project
  7. Balaji Realty1 project
  8. Dhamale Thorat Associates1 project
  9. Ilika Realtors1 project
  10. Impact Builders and Developers1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology