Delayed projects in Pune
2,215 MahaRERA projects in Pune are past their promised completion date, and MahaRERA shows no completion for them.
Most overdue first
Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 36 of 45.
| Project | Locality | Promised | Revised | Delivery |
|---|---|---|---|---|
| Katraj SierraBright Infra | Mangadewadi | Oct 2025 | Oct 2025 | 1 yr 1 mo late |
| Sai NiwaraAmrutvel Buildcon | Chikhali | Oct 2025 | Oct 2025 | 1 yr 1 mo late |
| Gat No 833p Village- ShindavaneNilesh Gulab Choudhary | Shindvane | Oct 2025 | — | 1 yr 1 mo late |
| Maithili SquareMarne Group | Pimpri Chinchawad (M Corp.) | Oct 2025 | Oct 2025 | 1 yr 1 mo late |
| Mauli ParadiseMauli Developers | Ambegaon Bk | Oct 2025 | Oct 2025 | 1 yr 1 mo late |
| Jubilation A Wing Phase IIAakankssha Properties | Yawalewadi | Oct 2025 | Oct 2025 | 1 yr 1 mo late |
| PadmnabhHighrise Infra | Karve Nagar | Oct 2025 | Oct 2025 | 1 yr 1 mo late |
| Shankeshwar Gold PlazaSaiesh Properties | Pune (M Corp.) | Oct 2025 | Oct 2025 | 1 yr 1 mo late |
| Kalakunj CDVG Empires LLP | Kothrud | Oct 2025 | Oct 2025 | 1 yr 1 mo late |
| Sai Mai MansionSai Raj Developers | Akurdi | Oct 2025 | Oct 2025 | 1 yr 1 mo late |
| Trio HouseTrio Buildcon Pvt Ltd | Baramati (M Cl) | Oct 2025 | Oct 2025 | 1 yr 1 mo late |
| Avishkar HeightsMehetre Brothers | Rahatani | Nov 2025 | Nov 2025 | 1 yr late |
| Aishwarya Sahakari Gruharachna Sanstha MaryaditLJM Properties LLP | Shukrawar Peth | Nov 2025 | Nov 2025 | 1 yr late |
| AthashreeAthashree Enterprises | Talegaon Dabhade (R) | Nov 2025 | Nov 2025 | 1 yr late |
| GalaxyRaichandani Constructions Private Limited | Baner | Nov 2025 | Nov 2025 | 1 yr late |
| Shanti Heights AppartmentShaashwat Builders Promotersand Developoers | Lonavala (M Cl) | Nov 2025 | Nov 2025 | 1 yr late |
| Shital ChsSaransh Construction | Kothrud | Nov 2025 | Nov 2025 | 1 yr late |
| Swami KunjVaibhavlaxmi Infracon | Karve Nagar | Nov 2025 | Nov 2025 | 1 yr late |
| Dhananjay ApartmentNiwas Enterprises | Erandwana | Dec 2025 | Dec 2025 | 11 mo late |
| Metro PlazaRaskar Realtors Through Its Proprietor Vijay Nivrutti Raskar | Moshi | Dec 2025 | Dec 2025 | 11 mo late |
| Swati ApartmentNiwas Enterprises | Parvati | Dec 2025 | Dec 2025 | 11 mo late |
| KesarRaichandani Constructions Private Limited | Kondhwa Bk | Dec 2025 | Dec 2025 | 11 mo late |
| Sairam ResidencyManoj Harishchandra Kale | Ale | Dec 2025 | Dec 2025 | 11 mo late |
| Dwarka HeightsVinod Premchand Chandwani | Pimpale Saudagar | Dec 2025 | Dec 2025 | 11 mo late |
| MadhavkunjMadhav Developers | Chovisawadi | Dec 2025 | Dec 2025 | 11 mo late |
| Royal EmpireAmit Rajendra Kudale And Mayur Samirmal Jain | Dhayari (Part) | Dec 2025 | Dec 2025 | 11 mo late |
| The Back Water Residency Phase II - B BuildingLNK PROJECTS Through Proprietor Mr Narayan Baburao Khasnis | Khanapur | Dec 2025 | Dec 2025 | 11 mo late |
| AnandArchway Properties | Erandwana | Dec 2025 | Dec 2025 | 11 mo late |
| Avasa WoodlandNaiknavare Housing Development Pvt.ltd | Mahalunge | Dec 2025 | Dec 2025 | 11 mo late |
| Building - M - Navyangan Phase - IIAvior Merlin Venture LLP | Kasar Amboli | Dec 2025 | Dec 2025 | 11 mo late |
| Building No. A1 -Navyangan Phase - IIAvior Merlin Venture LLP | Kasar Amboli | Dec 2025 | Dec 2025 | 11 mo late |
| Building No. B1 - Navyangan Phase - IIAvior Merlin Venture LLP | Kasar Amboli | Dec 2025 | Dec 2025 | 11 mo late |
| BelshoreLavasa Corporation Ltd | Mugaon | Dec 2025 | Dec 2025 | 11 mo late |
| Boulevard Tower A1Bramhacorp Limited | Ghorpadi | Dec 2025 | Dec 2025 | 11 mo late |
| C Building - Golden Fortune, Nisarg RaghvendraNisarg Parivar AOP | Borhadewadi | Dec 2025 | Dec 2025 | 11 mo late |
| Cosmos ResidencyCosmos Buildcon | Kamshet | Dec 2025 | Dec 2025 | 11 mo late |
| Epic Phase 2Yashada World | Haveli | Dec 2025 | Dec 2025 | 11 mo late |
| Forest Trails Everglades H3 and H4Paranjape Schemes (Construction) Ltd | Bhugaon | Dec 2025 | Dec 2025 | 11 mo late |
| Ganesh Bella MontanaVeddant Shelters | Ravet | Dec 2025 | Dec 2025 | 11 mo late |
| Ganga Newtown Ph 02Shree Balaji Associates Pune LLP | Pune (M Corp.) | Dec 2025 | Dec 2025 | 11 mo late |
| Guruvista Phase IIGuruvista Aop | Kharadi | Dec 2025 | Dec 2025 | 11 mo late |
| Hillshore 1,2,3,4,5,6,7,8,9,10,11 LCL - 0012Lavasa Corporation Ltd | Mugaon | Dec 2025 | Dec 2025 | 11 mo late |
| Life Canvas Phase 1Vighnaharta Reality | Mamurdi | Dec 2025 | Dec 2025 | 11 mo late |
| Park AstraPride Purple Infrastructure | Marunji | Dec 2025 | Dec 2025 | 11 mo late |
| Prism city-VioletDiamond Swastik Infra | Charholi | Dec 2025 | Dec 2025 | 11 mo late |
| Ranjan Heights- Wing BRanu Mahadu Bhondve | Ravet | Dec 2025 | Dec 2025 | 11 mo late |
| Royal SaiiconShree Anand Venkateshwara Buildcon | Wakad | Dec 2025 | Dec 2025 | 11 mo late |
| Rohan AnanyaRohan & Atul Enterprises | Hinjavadi (Ct) | Dec 2025 | Dec 2025 | 11 mo late |
| Sai ShrushtiSai Construction | Indapur (M Cl) | Dec 2025 | Dec 2025 | 11 mo late |
| Shine City Phase IVNamoh Builders & developers | Chikhali | Dec 2025 | Dec 2025 | 11 mo late |
Delayed projects by district
All MaharashtraPune · 2,215Thane · 1,158Raigarh · 1,042Mumbai Suburban · 994Nashik · 483Palghar · 362Nagpur · 323Aurangabad · 243Mumbai City · 242Satara · 228Ratnagiri · 192Sangli · 176Solapur · 155Kolhapur · 131Amravati · 72Sindhudurg · 72Ahmednagar · 69Chandrapur · 39Jalgaon · 39Latur · 28Akola · 23Beed · 21Nanded · 18Dhule · 17Wardha · 16Buldana · 14Jalna · 12Parbhani · 9Bhandara · 8Yavatmal · 6
SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology