Its promised completion date, Nov 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record.

Kothrud, Pune 411038 · Property rates in Kothrud · by Saransh Construction

Delivery1 yr past duePromised Nov 2025 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has read

Buying a flat here?

See every deed registered on it.

Its promised completion date, Nov 2025, has passed and MahaRERA does not show it completed

  • This projectRegistered 5 Apr 2023, completion promised 30 Nov 2025, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

All 109 deeds →
Latest registered deeds in this project
MonthFlatKindAreaPriceRecord
Dec 2024Shital CHS · 15Title transfer444 sq ftView Title transfer, Dec 2024
Aug 2020Shital CHS · 5Resale325 sq ftView Resale, Aug 2020
Dec 2019Not on recordResale820 sq ftView Resale, Dec 2019
Jul 2018Shital CHS · 11Resale—View Resale, Jul 2018
Aug 2017Shital CHS · 12Title transfer—View Title transfer, Aug 2017
Aug 2017Shital CHS · 5Title transfer—View Title transfer, Aug 2017
Jun 2017Shital CHS · 4Title transfer—View Title transfer, Jun 2017
Jun 2017Shital CHS · 11Title transfer—View Title transfer, Jun 2017
Jun 2017Shital CHS · 3Title transfer—View Title transfer, Jun 2017
Sep 2026Shital CHS · 11Rental—View Rental, Sep 2026

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100050396
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000503965 Apr 202330 Nov 202530 Nov 2025Saransh ConstructionProject page
Documents80

18 documents held by Deedo, 62 filings listed on MahaRERA's project page

Registration certificate

Other (17)

Show all 80 documentsShow fewer documents

Other (17)

Finance

  • PAN CardPAN Card.pdf · uploaded 15 Mar 2023Source

Legal

  • Declaration Form BForm B.pdf · uploaded 15 Mar 2023Source
  • Legal Title reportTitle Search Report Annexure.pdf · uploaded 19 Mar 2023Source
  • Legal Title reportTitle Search Report.pdf · uploaded 19 Mar 2023Source

Migrated

  • 1 PAN CardPAN Card.pdf · uploaded 15 Mar 2023Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrance Certificate.pdf · uploaded 15 Mar 2023Source
  • 1 b Details of encumbrances concerned to LegalEncumbrance Certificate.pdf · uploaded 15 Mar 2023Source
  • 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 15 Mar 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentLayout.pdf · uploaded 15 Mar 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 15 Mar 2023Source
  • 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 15 Mar 2023Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 15 Mar 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Account Details.pdf · uploaded 15 Mar 2023Source
  • 1 Deviation Report with respect to Allotment letterDeviation Report - Allottment Letter.pdf · uploaded 15 Mar 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Report - Agreement.pdf · uploaded 15 Mar 2023Source
  • 1 Copy of the legal title reportTitle Search Report Annexure.pdf · uploaded 19 Mar 2023Source
  • 2 Copy of the legal title reportTitle Search Report.pdf · uploaded 19 Mar 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 19 Mar 2023Source
  • 1 Proforma of Agreement for saleSample Agreement.pdf · uploaded 19 Mar 2023Source
  • 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 19 Mar 2023Source
  • 1 CERSAI detailsCERSAI Report.pdf · uploaded 20 Mar 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest.pdf · uploaded 20 Mar 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect letter.pdf · uploaded 1 Nov 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech Letter.pdf · uploaded 1 Nov 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)EngineersCertificate.pdf · uploaded 1 Nov 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate.pdf · uploaded 1 Nov 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Final.pdf · uploaded 1 Nov 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 1 Nov 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech Letter Dec 23.pdf · uploaded 29 Feb 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)EngineersCertificate Dec 23.pdf · uploaded 29 Feb 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)_CA Certificate Final Dec 23.pdf · uploaded 29 Feb 2024Source
  • 2 Copy of Layout Approval (in case of layout)A.pdf · uploaded 13 Apr 2024Source
  • 2 Commencement Certificates / NA Order for plotted development240328 Commencement Certificate Scanned Low Res.pdf · uploaded 13 Apr 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect letter.pdf · uploaded 27 Jan 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)2406 Architect Letter.pdf · uploaded 27 Jan 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)2409 Architect Letter.pdf · uploaded 27 Jan 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)250108 Arch Letter.pdf · uploaded 27 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)2412 Form 3 R1.pdf · uploaded 27 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)2403 EngineersCertificate 2403 Mar 24.pdf · uploaded 27 Jan 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)2406 Engineers Certificate.pdf · uploaded 27 Jan 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)2409 Engineers Certificate.pdf · uploaded 27 Jan 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)2412 Engineers Certificate.pdf · uploaded 27 Jan 2025Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)2412 Engineers Certificate.pdf · uploaded 27 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)250408 Arch Letter.pdf · uploaded 16 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 16 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)2503 Engineers Certificate.pdf · uploaded 16 Apr 2025Source

Technical

  • DocumentLayout.pdf · uploaded 15 Mar 2023Source
  • DocumentLayout.pdf · uploaded 15 Mar 2023Source
  • DocumentA.pdf · uploaded 13 Apr 2024Source

Technical (Architect)

  • DocumentArchitech Letter Dec 23.pdf · uploaded 29 Feb 2024Source
  • DocumentArchitect letter.pdf · uploaded 27 Jan 2025Source
  • Document2406 Architect Letter.pdf · uploaded 27 Jan 2025Source
  • Document2409 Architect Letter.pdf · uploaded 27 Jan 2025Source
  • Document250108 Arch Letter.pdf · uploaded 27 Jan 2025Source
  • Document250408 Arch Letter.pdf · uploaded 16 Apr 2025Source

Technical (Engineer)

  • DocumentEngineersCertificate Dec 23.pdf · uploaded 29 Feb 2024Source
  • Document2403 EngineersCertificate 2403 Mar 24.pdf · uploaded 27 Jan 2025Source
  • Document2406 Engineers Certificate.pdf · uploaded 27 Jan 2025Source
  • Document2409 Engineers Certificate.pdf · uploaded 27 Jan 2025Source
  • Document2412 Engineers Certificate.pdf · uploaded 27 Jan 2025Source
  • Document2412 Engineers Certificate.pdf · uploaded 27 Jan 2025Source
  • Document2503 Engineers Certificate.pdf · uploaded 16 Apr 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Plot No 117, S No 97/2

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 3BHK, 4BHK14 units in all
Address
Plot No 117, S No 97/2, Kothrud, Bhusari ColonyPIN 411038
Village
Kothrud, Haveli taluka
Land area for this project
483 sq m (5,200 sq ft)
Permissible built-up area
2,015 sq m (21,693 sq ft)
Sanctioned built-up area
1,545 sq m (16,634 sq ft)
Designated bank account
76
Developed in phases
No
Also registered as
Patel Classic, Chitralekhashree, Chitralekhashree Apartment

Survey, CTS, gat or plot numbers

Plot No 117S No 97/2

Land as published on MahaRERA's project page

Plot No 117, S No 97/2

Boundaries

North
30 Feet Colony Road
South
Vacant Land
East
Plot No 116
West
Plot No 118

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking14 units

3 of 14 units booked (21%), as the promoter reported to MahaRERA

2BHK · 3 units3BHK · 10 units4BHK · 1 unit
TypeCarpet areaUnitsBooked
2BHK54.68 sq m · 589 sq ft10
2BHK61.11 sq m · 658 sq ft10
2BHK62.33 sq m · 671 sq ft10
3BHK70.48 sq m · 759 sq ft11
3BHK76.74 sq m · 826 sq ft51
3BHK79.68 sq m · 858 sq ft41
4BHK94.09 sq m · 1,013 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDixit & Associates—
Chartered accountantM/s Anurag Meherwal and Co.—
EngineerAjay Bhilare & Associates—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Kothrud

All 4,695 projects in Kothrud · Compare Shital Chs with another project

Shital Chs in numbers

Registered deals, summarised

Deedo has 109 registered documents at Shital Chs, from Jan 2016 to Sep 2026: 9 sales, 90 leave and licence agreements, 1 mortgage.

How many properties have been sold at Shital Chs?
9 sales are registered at Shital Chs, 3 of them resales.
Are properties at Shital Chs rented out?
Yes: 90 leave and licence agreements are registered at Shital Chs, at a median rent since Jan 2016 of about ₹16,000 a month with a deposit of about ₹30,000.
Where does this data come from?
The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Shital Chs by Deedo, last updated with deals registered in Sep 2026.

Latest deal · Title transfer · Dec 2024

₹25–50 L