RERA projects in Ale

15 projects under 17 MahaRERA registrations, registered 2017–2026. 59% have a completion date extended beyond the one promised.

Locality
15RERA projects
17Registrationssome projects hold several
11Completion still due6 past their completion date
4 monthsMedian extension beyond promised date59% of registrations extended
0Regulatory casesnone on MahaRERA's lists
28Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20171
20181
20191
20201
20215
20221
20230
20245
20250
20262

Projects in Ale

15 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Sai DattaVaradvinayak Builders And DevelopersPM12600026006091 Jun 202631 Mar 203031 Jul 2030Extended 4 mo0
Navkar HeightVb LandmarksP5210007799219 Nov 202431 Dec 202730 Apr 2028Extended 4 mo0
Shinde ResidencyShinde DevelopersP521000768793 Jul 202431 Dec 202730 Apr 2028Extended 4 mo0
Priya HitarthiYash Dudhraj SanghviP5210005571215 Apr 202431 Dec 202630 Apr 2027Extended 4 mo0
Mauli HeightsMauli DevelopersP5210005474412 Feb 202431 Dec 202630 Apr 2027Extended 4 mo0
Global Luxuria IIDnyaneshwar Mahadu Jadhav proprietor of Global ConstructionP5210004693520 Sep 202231 Dec 202630 Apr 2027Extended 4 mo0
Arya Business CentreAnaya DevelopersP5210003196829 Nov 20216 Nov 20241 May 2027Extended 30 mo0
Sairam ResidencyManoj Harishchandra KaleP521000316343 Nov 202110 Dec 202510 Dec 2025Promised date passed0
Shree Dattatraya ApartmentKalpana Ankush GopaleP521000298528 Jul 202131 Mar 202731 Jul 2027Extended 4 mo0
Shubham Tarangan Phase IIShubham Vipra AssociatesP5210002906623 Apr 202131 Dec 202531 Dec 2025Promised date passed0
Rajmudra Phase 1 and 2Rajmudra DevelopersP521000277373 Jan 202128 Nov 202228 May 2024Extended 18 mo0
Global LuxuriaDnyaneshwar Mahadu Jadhav proprietor of Global ConstructionP5210002646924 Sep 202030 Jun 202530 Jun 2025Promised date passed0
VrundavanWagh And Bhor GroupP52100022068, P52100055465, PR126000260191825 Aug 20191 Jul 20311 Jul 2031Not yet due0
Manas ResidencyOorjitaa RealtorsP5210001643110 May 201831 Dec 202631 Dec 2026Not yet due0
AkashgangaAkash Promoter And Developers Company Proprietor Kishor Genbhau DangatP5210001145631 Aug 201730 Sep 201830 Sep 2018Promised date passed0

Other localities in Junnar

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Dnyaneshwar Mahadu Jadhav proprietor of Global Construction2 projects
  2. Akash Promoter And Developers Company Proprietor Kishor Genbhau Dangat1 project
  3. Anaya Developers1 project
  4. Kalpana Ankush Gopale1 project
  5. Manoj Harishchandra Kale1 project
  6. Mauli Developers1 project
  7. Oorjitaa Realtors1 project
  8. Rajmudra Developers1 project
  9. Shinde Developers1 project
  10. Shubham Vipra Associates1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology