Junnar, Pune
Deedo IDDL-PUN-JUNNAR5 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects153
Registrations159some projects hold several
Completion still due6080 past their date
Median extension4 months52% of registrations extended
Regulatory cases3on 3 projects
8 in 10 registrations run late here
159 MahaRERA registrations in Junnar and the places within it
10 not yet due50 extended, not yet due80 past even the latest date19 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Junnar
153 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Sai Anand PlazaM/s Kulswami Builders and Developers | Due Jul 2035 | — | — |
| Skyline ResidencyTamboli Builders & Developers | Due Dec 2027 | — | — |
| Oxygen Park Phase 2Yogiraj Developers and Construction | Due Dec 2028 | — | — |
| Crystal Tower Phase 2Jadhav Civil Project | Due Jul 2029, extended 4 mo | — | — |
| Nest In ParkM/S. Js Realty | Due Apr 2029, extended 4 mo | — | — |
| Florina Phase IIDeepali Buildcon | Due Jul 2028, extended 4 mo | — | — |
| Sai DattaVaradvinayak Builders And Developers | Due Jul 2030, extended 4 mo | — | — |
| Shree Muktai HeightsMangesh Mahadev Bankar | Due Apr 2030, extended 4 mo | — | — |
| Rajlaxmi PrestigeRajlaxmi Developers | Due Apr 2030, extended 4 mo | — | — |
| ShivkunjDurva Developers | Due Jan 2029, extended 4 mo | — | — |
| K K MarketK K Construction | Due Apr 2030, extended 4 mo | — | — |
| Global Silver parkVedant And Bhujbal Developers | Due Dec 2029 | — | — |
| Alephata Central ParkSUV Developers | Due Apr 2030, extended 4 mo | — | — |
| Ayodhyam VillaSRP Buildcon | Due Apr 2031, extended 4 mo | — | — |
| Swami Vishwa HeightsLaxmi Developers | Due Apr 2030, extended 4 mo | — | — |
| Tulsi ViharTulsi Developers | Due Apr 2029, extended 4 mo | — | 0% |
| Kalash ResidencyPramod Ramdas Bangar | Due Jul 2028, extended 4 mo | — | 0% |
| SuryaprasthaSuryaputra Developers | Due Apr 2027, extended 4 mo | — | 28% |
| Gaurinandan HeightsTrident Civil Projects | Due Apr 2028, extended 4 mo | — | — |
| Navkar HeightVb Landmarks | Due Apr 2028, extended 4 mo | — | 0% |
| Prime VastuPrime Construction | Due Jul 2027 | — | 0% |
| Landmark ParadiseLandmark Promoters & Builders | Due Nov 2027, extended 4 mo | — | 0% |
| Yashwant VillasNirmiti Construction | Due Apr 2029, extended 4 mo | — | — |
| Global CityDnyaneshwar Mahadu Jadhav proprietor of Global Construction | Due Apr 2028, extended 4 mo | — | 0% |
| Shinde ResidencyShinde Developers | Due Apr 2028, extended 4 mo | — | 0% |
Nearby: other talukas in Pune
Most active promoters
- Jadhav Civil Project6 projects
- Suryaputra Developers4 projects
- Vizion Construction4 projects
- Dnyaneshwar Mahadu Jadhav proprietor of Global Construction3 projects
- Gholap Developers3 projects
- Prime Construction3 projects
- Deepali Buildcon2 projects
- Eknath Bhau Shinde2 projects
- Landmark Associates2 projects
- Nandanvan Developers2 projects
Data through28 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology