Junnar, Pune
Deedo IDDL-PUN-JUNNAR8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects153
Registrations159some projects hold several
Completion still due5981 past their date
Median extension4 months52% of registrations extended
Regulatory cases3on 3 projects
8 in 10 registrations run late here
159 MahaRERA registrations in Junnar and the places within it
10 not yet due49 extended, not yet due81 past even the latest date19 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Junnar
153 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Suyog SamrajyaAshirwad Infrastructures | Due Apr 2028, extended 4 mo | — | — |
| Vaishnavi Vastu A and BVaishnavi Promoters And Developers | Due Apr 2028, extended 4 mo | — | 8% |
| Betel LeafVighnaharta Developers | Due Mar 2028, extended 4 mo | — | — |
| Harsh HeightsSambhaji Radhabhau Hadawale | 11 mo late | — | 27% |
| Priya HitarthiYash Dudhraj Sanghvi | Due Apr 2027, extended 4 mo | — | — |
| Patil Dumbre TowersPatil Dumbre Builders And Developers | Due Apr 2030, extended 4 mo | — | 7% |
| Florina ResidencyDeepali Buildcon | 8 mo late | — | 60% |
| Nirmiti IconNirmiti Developers | Due Dec 2026, extended 4 mo | — | — |
| The Life Park Phase IBandhan Abhay Tambe | Due Apr 2028, extended 4 mo | — | — |
| Mauli HeightsMauli Developers | Due Apr 2027, extended 4 mo | — | — |
| Shrihari PlazaShrihari Developers | Due Mar 2029, extended 4 mo | — | — |
| Sai ShrustiEknath Bhau Shinde | Due Nov 2027, extended 4 mo | — | — |
| Crystal TowerJadhav Civil Project | Due Apr 2027, extended 4 mo | — | 32% |
| Govind PlazaRamdas Shantaram Gholap | Due Apr 2028, extended 4 mo | — | — |
| Prime PrestigePrime Construction | Completed | — | — |
| Chhatrapati SquareSachin Jayram Nalawade | Due Apr 2027, extended 4 mo | — | — |
| Royal AvenueParadise Builder And Developers | Due Nov 2027, extended 4 mo | — | 63% |
| DwarkamaiRajlaxmi Associates | 2 yrs 4 mo late | — | 50% |
| Oxygen Park Phase IYogiraj Developers and Construction | Due Apr 2027, extended 4 mo | — | 28% |
| Happy MorningSandip Balkrishna Bangar | Completed, extended 11 mo | — | 18% |
| Quality Royal ParkQuality Construction | Due Mar 2027 | — | 43% |
| ShivsahyadriNandanvan Developers | Due Apr 2028, extended 4 mo | — | 32% |
| Varad ResidencyQuality Construction | Due Jul 2027, extended 4 mo | — | 29% |
| Divyata ParkShantaram J Gadhve | Due Dec 2026 | — | — |
| Vijayalaxmi SulojayShreevijayalaxmi Developers | Due Apr 2027, extended 4 mo | — | 25% |
Nearby: other talukas in Pune
Most active promoters
- Jadhav Civil Project6 projects
- Suryaputra Developers4 projects
- Vizion Construction4 projects
- Dnyaneshwar Mahadu Jadhav Proprietor Of Global Construction3 projects
- Gholap Developers3 projects
- Prime Construction3 projects
- Deepali Buildcon2 projects
- Eknath Bhau Shinde2 projects
- Landmark Associates2 projects
- Nandanvan Developers2 projects
Junnar, in questions
How many projects in Junnar run late?
8 in 10 MahaRERA registrations (130 of 159): their completion date was extended or has passed, data through 28 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Junnar by Deedo. Medians on fewer than 3 deeds are not shown.
Data through28 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology