8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects153
Registrations159some projects hold several
Completion still due5981 past their date
Median extension4 months52% of registrations extended
Regulatory cases3on 3 projects

8 in 10 registrations run late here

159 MahaRERA registrations in Junnar and the places within it

10 not yet due49 extended, not yet due81 past even the latest date19 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Junnar

153 projects registered with MahaRERA in this taluka and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Suyog SamrajyaAshirwad InfrastructuresDue Apr 2028, extended 4 mo——
Vaishnavi Vastu A and BVaishnavi Promoters And DevelopersDue Apr 2028, extended 4 mo—8%
Betel LeafVighnaharta DevelopersDue Mar 2028, extended 4 mo——
Harsh HeightsSambhaji Radhabhau Hadawale11 mo late—27%
Priya HitarthiYash Dudhraj SanghviDue Apr 2027, extended 4 mo——
Patil Dumbre TowersPatil Dumbre Builders And DevelopersDue Apr 2030, extended 4 mo—7%
Florina ResidencyDeepali Buildcon8 mo late—60%
Nirmiti IconNirmiti DevelopersDue Dec 2026, extended 4 mo——
The Life Park Phase IBandhan Abhay TambeDue Apr 2028, extended 4 mo——
Mauli HeightsMauli DevelopersDue Apr 2027, extended 4 mo——
Shrihari PlazaShrihari DevelopersDue Mar 2029, extended 4 mo——
Sai ShrustiEknath Bhau ShindeDue Nov 2027, extended 4 mo——
Crystal TowerJadhav Civil ProjectDue Apr 2027, extended 4 mo—32%
Govind PlazaRamdas Shantaram GholapDue Apr 2028, extended 4 mo——
Prime PrestigePrime ConstructionCompleted——
Chhatrapati SquareSachin Jayram NalawadeDue Apr 2027, extended 4 mo——
Royal AvenueParadise Builder And DevelopersDue Nov 2027, extended 4 mo—63%
DwarkamaiRajlaxmi Associates2 yrs 4 mo late—50%
Oxygen Park Phase IYogiraj Developers and ConstructionDue Apr 2027, extended 4 mo—28%
Happy MorningSandip Balkrishna BangarCompleted, extended 11 mo—18%
Quality Royal ParkQuality ConstructionDue Mar 2027—43%
ShivsahyadriNandanvan DevelopersDue Apr 2028, extended 4 mo—32%
Varad ResidencyQuality ConstructionDue Jul 2027, extended 4 mo—29%
Divyata ParkShantaram J GadhveDue Dec 2026——
Vijayalaxmi SulojayShreevijayalaxmi DevelopersDue Apr 2027, extended 4 mo—25%
Junnar market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Jadhav Civil Project6 projects
  2. Suryaputra Developers4 projects
  3. Vizion Construction4 projects
  4. Dnyaneshwar Mahadu Jadhav Proprietor Of Global Construction3 projects
  5. Gholap Developers3 projects
  6. Prime Construction3 projects
  7. Deepali Buildcon2 projects
  8. Eknath Bhau Shinde2 projects
  9. Landmark Associates2 projects
  10. Nandanvan Developers2 projects

Junnar, in questions

How many projects in Junnar run late?

8 in 10 MahaRERA registrations (130 of 159): their completion date was extended or has passed, data through 28 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Junnar by Deedo. Medians on fewer than 3 deeds are not shown.

Data through28 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology