Deedo IDDP-PUN-W0TBCompletion was pushed back 4 months, to Nov 2027; no MahaRERA orders on record; 63% of its units are booked.
Otur, Pune 412409 · by Paradise Builder And Developers
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Nov 2027
- This projectRegistered 8 Sep 2023, completion promised 31 Jul 2027, revised to 30 Nov 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100052536
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100052536 | 8 Sep 2023 | 31 Jul 2027 | 30 Nov 2027 | Paradise Builder And Developers | Project page |
Documents69
1 document held by Deedo, 68 filings listed on MahaRERA's project page
Finance
- PAN CardPan Card.pdf · uploaded 6 Jul 2023Source
Legal
- Other – Legal1_DA.pdf · uploaded 6 Jul 2023Source
- Other – Legal2_DA.pdf · uploaded 6 Jul 2023Source
- Other – Legal3_DA.pdf · uploaded 6 Jul 2023Source
- Other – Legal4_DA.pdf · uploaded 6 Jul 2023Source
- Other – Legal5_DA.pdf · uploaded 6 Jul 2023Source
- Legal Title reportTitle Report.pdf · uploaded 18 Jul 2023Source
Show all 69 documentsShow fewer documents
Legal
- Declaration Form BForm B.pdf · uploaded 27 Jul 2023Source
Migrated
- 1 CERSAI detailsCERSAI_Search_Report_200273491157_For_Asset_Based_Search_05_07_2023_12_21_13_433.pdf · uploaded 5 Jul 2023Source
- 2 CERSAI detailsCERSAI declaration.pdf · uploaded 5 Jul 2023Source
- 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 5 Jul 2023Source
- 1 PAN CardPan Card.pdf · uploaded 6 Jul 2023Source
- 1 a Details of encumbrances concerned to FinanceEncumbrance-Finance.pdf · uploaded 6 Jul 2023Source
- 2 a Details of encumbrances concerned to FinanceEncumbrance -Legal.pdf · uploaded 6 Jul 2023Source
- 1 b Details of encumbrances concerned to LegalEncumbrance-Finance.pdf · uploaded 6 Jul 2023Source
- 2 b Details of encumbrances concerned to LegalEncumbrance -Legal.pdf · uploaded 6 Jul 2023Source
- 1 Copy of Layout Approval (in case of layout)1.pdf · uploaded 6 Jul 2023Source
- 1 Building Plan Approval / NA Order for plotted development2.pdf · uploaded 6 Jul 2023Source
- 2 Building Plan Approval / NA Order for plotted development3.pdf · uploaded 6 Jul 2023Source
- 3 Building Plan Approval / NA Order for plotted development4.pdf · uploaded 6 Jul 2023Source
- 4 Building Plan Approval / NA Order for plotted development5.pdf · uploaded 6 Jul 2023Source
- 5 Building Plan Approval / NA Order for plotted development6.pdf · uploaded 6 Jul 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentNA Order.pdf · uploaded 6 Jul 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSeparate Bank Account.pdf · uploaded 6 Jul 2023Source
- 1 Deviation Report with respect to Allotment letterDeviation-Allotment Letter.pdf · uploaded 6 Jul 2023Source
- 1 Deviation Report with respect to model copy of AgreementDeviation-Agreement.pdf · uploaded 6 Jul 2023Source
- 1 Other – Legal1_DA.pdf · uploaded 6 Jul 2023Source
- 2 Other – Legal2_DA.pdf · uploaded 6 Jul 2023Source
- 3 Other – Legal3_DA.pdf · uploaded 6 Jul 2023Source
- 4 Other – Legal4_DA.pdf · uploaded 6 Jul 2023Source
- 5 Other – Legal5_DA.pdf · uploaded 6 Jul 2023Source
- 1 Declaration about Commencement CertificateDeclaration-CC.pdf · uploaded 7 Jul 2023Source
- 1 Copy of the legal title reportTitle Report.pdf · uploaded 18 Jul 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 18 Jul 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Royal Avenue.pdf · uploaded 19 Jul 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engg_Royal Avenue.pdf · uploaded 20 Jul 2023Source
- 1 Declaration in FORM BForm B.pdf · uploaded 27 Jul 2023Source
- 1 Proforma of Agreement for saleAgreement.pdf · uploaded 27 Jul 2023Source
- 1 Other – TechnicalMail by SDO regarding CC.pdf · uploaded 3 Aug 2023Source
- 2 Other – TechnicalACE Scanner_2023_08_03(2).pdf · uploaded 3 Aug 2023Source
- 3 Other – TechnicalForm 3_ Paradise Royal Avenue_Updated.pdf · uploaded 3 Aug 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAdobe Scan 21-Aug-2023-1.pdf · uploaded 21 Aug 2023Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsAdobe Scan 21-Aug-2023-2.pdf · uploaded 21 Aug 2023Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsAdobe Scan 21-Aug-2023-3.pdf · uploaded 21 Aug 2023Source
- 4 Disclosure of Interest in Other Real Estate OrganizationsAdobe Scan 21-Aug-2023-4.pdf · uploaded 21 Aug 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Paradise Builders_Form 3_Sept 23_compressed.pdf · uploaded 31 Jan 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Paradise Builders_Form 3 Dec 23_compressed.pdf · uploaded 31 Jan 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 March 2023_Corrected_compressed.pdf · uploaded 31 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Paradise Builders_Form 3_Sept 23_compressed.pdf · uploaded 31 Jan 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Paradise Bulider and Developers Sept 23.pdf · uploaded 31 Jan 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Paradise Bulider and Developers Dec 23.pdf · uploaded 31 Jan 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Paradise Bulider and Developers March 24.pdf · uploaded 31 Jan 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Final_Form 5_BJ.pdf · uploaded 31 Jan 2025Source
Technical
- Document1.pdf · uploaded 6 Jul 2023Source
- Document2.pdf · uploaded 6 Jul 2023Source
- Document3.pdf · uploaded 6 Jul 2023Source
- Document4.pdf · uploaded 6 Jul 2023Source
- Document5.pdf · uploaded 6 Jul 2023Source
- Document6.pdf · uploaded 6 Jul 2023Source
- Other – TechnicalForm 3_ Paradise Royal Avenue_Updated.pdf · uploaded 3 Aug 2023Source
- Other – TechnicalMail by SDO regarding CC.pdf · uploaded 3 Aug 2023Source
- Other – TechnicalACE Scanner_2023_08_03(2).pdf · uploaded 3 Aug 2023Source
Technical (Architect)
- DocumentForm 1.pdf · uploaded 18 Jul 2023Source
Technical (Engineer)
- DocumentForm 2 Engg_Royal Avenue.pdf · uploaded 20 Jul 2023Source
- DocumentParadise Builders_Form 3_Sept 23_compressed.pdf · uploaded 31 Jan 2025Source
- DocumentForm 2_Paradise Bulider and Developers Sept 23.pdf · uploaded 31 Jan 2025Source
- DocumentForm 2_Paradise Bulider and Developers Dec 23.pdf · uploaded 31 Jan 2025Source
- DocumentForm 2_Paradise Bulider and Developers March 24.pdf · uploaded 31 Jan 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 179/8/A, 181/3
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK, 3BHK, 1BHK, 1RK, Shop93 units in all
- Address
- 181/3 AND 179/8/A, Nagar Kalyan Road, OturPIN 412409
- Village
- Otur, Junnar taluka
- Land area for this project
- 3,200 sq m (34,444 sq ft)
- Permissible built-up area
- 6,438 sq m (69,302 sq ft)
- Sanctioned built-up area
- 6,438 sq m (69,302 sq ft)
- Designated bank account
- 99
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
181/3 AND 179/8/A
Boundaries
- North
- Nagar Kalyan Road
- South
- 3 Mtere Wide Village Road
- East
- GAT NO 181 Hissa No 4
- West
- GAT NO 181 Hissa No 2
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking93 units
59 of 93 units booked (63%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Wing A | 2BHK | 59.21 sq m · 637 sq ft | 14 | 9 |
| Wing A | 2BHK | 70.71 sq m · 761 sq ft | 14 | 10 |
| Wing A | 3BHK | 82.01 sq m · 883 sq ft | 14 | 7 |
| Wing B | 1BHK | 46.03 sq m · 495 sq ft | 10 | 8 |
| Wing B | 1RK | 23.13 sq m · 249 sq ft | 1 | 1 |
| Wing B | 1RK | 25.13 sq m · 270 sq ft | 1 | 1 |
| Wing B | 1RK | 37.66 sq m · 405 sq ft | 1 | 0 |
| Wing B | 1RK | 38.31 sq m · 412 sq ft | 1 | 0 |
Show all 27 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Wing B | 2BHK | 66.97 sq m · 721 sq ft | 2 | 0 |
| Wing B | 2BHK | 67.07 sq m · 722 sq ft | 10 | 9 |
| Wing B | 2BHK | 75.58 sq m · 814 sq ft | 8 | 6 |
| Wing B | Shop | 9.29 sq m · 100 sq ft | 1 | 1 |
| Wing B | Shop | 9.37 sq m · 101 sq ft | 1 | 1 |
| Wing B | Shop | 11.16 sq m · 120 sq ft | 1 | 1 |
| Wing B | Shop | 11.29 sq m · 122 sq ft | 1 | 1 |
| Wing B | Shop | 11.37 sq m · 122 sq ft | 1 | 0 |
| Wing B | Shop | 14.57 sq m · 157 sq ft | 1 | 0 |
| Wing B | Shop | 19.05 sq m · 205 sq ft | 1 | 0 |
| Wing B | Shop | 19.08 sq m · 205 sq ft | 1 | 1 |
| Wing B | Shop | 20.2 sq m · 217 sq ft | 1 | 1 |
| Wing B | Shop | 20.42 sq m · 220 sq ft | 1 | 0 |
| Wing B | Shop | 20.43 sq m · 220 sq ft | 1 | 1 |
| Wing B | Shop | 20.5 sq m · 221 sq ft | 1 | 0 |
| Wing B | Shop | 20.53 sq m · 221 sq ft | 1 | 0 |
| Wing B | Shop | 20.55 sq m · 221 sq ft | 1 | 0 |
| Wing B | Shop | 20.56 sq m · 221 sq ft | 1 | 0 |
| Wing B | Shop | 21.76 sq m · 234 sq ft | 2 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Nilesh Bide | — |
| Chartered accountant | Susmit Joshi | — |
| Engineer | Vijendra Gaikwad | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Otur
- Skyline ResidencyRERA PM1260002602184
- Oxygen Park Phase 2RERA PM1261012602139
- Patil Dumbre TowersRERA P52100055604
- The Life Park Phase IRERA P52100054874
- Govind PlazaRERA P52100053656
- Chhatrapati SquareRERA P52100052511
- Oxygen Park Phase IRERA P52100051846
- Quality Royal ParkRERA P52100051581
All 19 projects in Otur · Compare Royal Avenue with another project