RERA projects in Indapur
21 projects under 21 MahaRERA registrations, registered 2017–2026. 17% have a completion date extended beyond the one promised.
Taluka
21RERA projects
21Registrations
6Completion still due12 past their completion date
4 monthsMedian extension beyond promised date17% of registrations extended
0Regulatory casesnone on MahaRERA's lists
18Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
| 2018 | 3 |
| 2019 | 2 |
| 2020 | 3 |
| 2021 | 1 |
| 2022 | 2 |
| 2023 | 1 |
| 2024 | 1 |
| 2025 | 2 |
| 2026 | 2 |
Projects in Indapur
21 projects registered with MahaRERA in this taluka and the places within it.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Vishwa ResidencyOm Jay Ganesh Construction | PR1260002600536 | 25 May 2026 | 22 Dec 2028 | — | Not yet due | 0 |
| Trinity HeightsBlackstone Developers | PR1260002502622 | 5 Mar 2026 | 2 Jan 2029 | — | Not yet due | 0 |
| Building AH & H Developers | PR1260002501705 | 5 Dec 2025 | 13 Feb 2028 | — | Not yet due | 0 |
| Thorat IconDevansh Promoter And Developers | P52100079125 | 6 Feb 2025 | 28 Oct 2026 | 28 Feb 2027 | Extended 4 mo | 0 |
| Gods GiftVishal Shivaji Gaikwad | P52100054906 | 15 Feb 2024 | 31 Mar 2027 | 31 Mar 2027 | Not yet due | 0 |
| Saisneh AppartmentSonali Sandeep Kumbhar | P52100050685 | 28 Apr 2023 | 12 Dec 2023 | 12 Dec 2023 | Promised date passed | 0 |
| Swamini HeightsSamarth Developers Nirmit Swamini Heights | P52100045233 | 10 May 2022 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Thorat HeightsJagdamba Developers | P52100035047 | 29 Apr 2022 | 31 Aug 2026 | 31 Aug 2026 | Promised date passed | 0 |
| Anand Pride PlusAnand Contractors & Developers | P52100031161 | 11 Oct 2021 | 31 Dec 2024 | 31 Dec 2025 | Extended 12 mo | 0 |
| Vastushree BuildingM/s.Shiv Developers through its Prop.Shri. Shankar Laxman Gaikwad | P52100026211 | 30 Aug 2020 | 15 Sep 2022 | 15 Sep 2022 | Promised date passed | 0 |
| Sai ShrushtiSai Construction | P52100026153 | 25 Aug 2020 | 30 Dec 2025 | 30 Dec 2025 | Promised date passed | 0 |
| Anand ExclusiveAnand Contractores And Developers | P52100025418 | 23 May 2020 | 26 Dec 2024 | 26 Dec 2024 | Promised date passed | 0 |
| Anand PrideAnand Contractores And Developers | P52100021410 | 26 Jun 2019 | 8 Mar 2024 | 8 Mar 2024 | Promised date passed | 0 |
| Pruthvi TowerVaishali Santosh Lokhande | P52100021270 | 18 Jun 2019 | 7 Mar 2025 | 7 Mar 2025 | Promised date passed | 0 |
| Siddhi Anand ResidencyAnand Contractors And Developers | P52100018538 | 13 Nov 2018 | 30 Oct 2023 | 30 Oct 2023 | Promised date passed | 0 |
| Mahi Anand ResidencyBhagwan Machindra Mahadik | P52100016298 | 2 May 2018 | 30 Sep 2020 | 30 Sep 2020 | Promised date passed | 0 |
| Akshata Anand ResidencyAnand Contractors And Developers | P52100016189 | 23 Apr 2018 | 30 Mar 2021 | 30 Mar 2021 | Promised date passed | 0 |
| Mission Human ParkSalknath Haribhau Kale | P52100013330 | 22 Sep 2017 | 31 Aug 2018 | 31 Aug 2018 | Promised date passed | 0 |
| Indreshwar Apartment | P52100023297 | — | — | — | — | 0 |
| Morya City B | P52100029454 | — | — | — | — | 0 |
| Rohan Residency | P52100016684 | — | — | — | — | 0 |
Other talukas in Pune
Most active promoters
By projects registered here, as named on MahaRERA.
- Anand Contractores And Developers2 projects
- Anand Contractors And Developers2 projects
- Anand Contractors & Developers1 project
- Bhagwan Machindra Mahadik1 project
- Blackstone Developers1 project
- Devansh Promoter And Developers1 project
- H & H Developers1 project
- Jagdamba Developers1 project
- M/s.Shiv Developers through its Prop.Shri. Shankar Laxman Gaikwad1 project
- Om Jay Ganesh Construction1 project
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology