Junnar, Pune

Deedo IDDL-PUN-JUNNAR

8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects153
Registrations159some projects hold several
Completion still due5981 past their date
Median extension4 months52% of registrations extended
Regulatory cases3on 3 projects

8 in 10 registrations run late here

159 MahaRERA registrations in Junnar and the places within it

10 not yet due49 extended, not yet due81 past even the latest date19 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Junnar

153 projects registered with MahaRERA in this taluka and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Alkabir ComplexMustafa Jaleel Ansari8 mo late—47%
Dwarka HeightsJadhav Civil Project1 yr 3 mo late—36%
Sankalp ResidencyMachindra Ganpat Pate11 mo late——
Laxmi HeightsAtharva Santosh Sarjine1 yr 8 mo late—65%
Vizion BlissVizion ConstructionDue Apr 2027, extended 4 mo—24%
Landmark Trade CenterLandmark Associates1 yr 5 mo late——
Landmark Business ParkLandmark Associates1 yr 5 mo late——
Global Luxuria IIDnyaneshwar Mahadu Jadhav proprietor of Global ConstructionDue Apr 2027, extended 4 mo——
Vrindavan ParkJadhav Civil ProjectCompleted——
ShreepushpaDeepali Civil Project1 yr 11 mo late——
Gulmohar ResidencySrushti Developers11 mo late——
Prime CornerPrime Construction1 yr 9 mo late——
Shivai Sahakari Gruh Nirman Sanstha MaryaditMayuresh DevelopersDue Apr 2027, extended 4 mo—11%
Arya Business CentreAnaya DevelopersDue May 2027, extended 2 yrs 6 mo——
Shree Muktai ComplexSamarth Developers2 yrs 2 mo late——
Sairam ResidencyManoj Harishchandra Kale11 mo late——
Surya HeightsSuryaputra DevelopersCompleted—94%
Shree Dattatraya ApartmentKalpana Ankush GopaleDue Jul 2027, extended 4 mo——
Time CityRajendra Narawade And Sudhir NarawadeDue Apr 2028, extended 4 mo——
Royal ResidencyShree Swami Samarth DevelopersCompleted—86%
Shubham Tarangan Phase IIShubham Vipra AssociatesCompleted—47%
Silver ParkJaihind PropertiesDue Dec 2027——
Central PlazaJadhav Civil ProjectCompleted—13%
Sai SavliDeepak Balkrushna Repale5 mo late—26%
Rajmudra Phase 1 and 2Rajmudra Developers4 yrs late—13%
Junnar market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Jadhav Civil Project6 projects
  2. Suryaputra Developers4 projects
  3. Vizion Construction4 projects
  4. Dnyaneshwar Mahadu Jadhav Proprietor Of Global Construction3 projects
  5. Gholap Developers3 projects
  6. Prime Construction3 projects
  7. Deepali Buildcon2 projects
  8. Eknath Bhau Shinde2 projects
  9. Landmark Associates2 projects
  10. Nandanvan Developers2 projects

Junnar, in questions

How many projects in Junnar run late?

8 in 10 MahaRERA registrations (130 of 159): their completion date was extended or has passed, data through 15 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Junnar by Deedo. Medians on fewer than 3 deeds are not shown.

Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology