Junnar, Pune
Deedo IDDL-PUN-JUNNAR8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects153
Registrations159some projects hold several
Completion still due5981 past their date
Median extension4 months52% of registrations extended
Regulatory cases3on 3 projects
8 in 10 registrations run late here
159 MahaRERA registrations in Junnar and the places within it
10 not yet due49 extended, not yet due81 past even the latest date19 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Junnar
153 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Alkabir ComplexMustafa Jaleel Ansari | 8 mo late | — | 47% |
| Dwarka HeightsJadhav Civil Project | 1 yr 3 mo late | — | 36% |
| Sankalp ResidencyMachindra Ganpat Pate | 11 mo late | — | — |
| Laxmi HeightsAtharva Santosh Sarjine | 1 yr 8 mo late | — | 65% |
| Vizion BlissVizion Construction | Due Apr 2027, extended 4 mo | — | 24% |
| Landmark Trade CenterLandmark Associates | 1 yr 5 mo late | — | — |
| Landmark Business ParkLandmark Associates | 1 yr 5 mo late | — | — |
| Global Luxuria IIDnyaneshwar Mahadu Jadhav proprietor of Global Construction | Due Apr 2027, extended 4 mo | — | — |
| Vrindavan ParkJadhav Civil Project | Completed | — | — |
| ShreepushpaDeepali Civil Project | 1 yr 11 mo late | — | — |
| Gulmohar ResidencySrushti Developers | 11 mo late | — | — |
| Prime CornerPrime Construction | 1 yr 9 mo late | — | — |
| Shivai Sahakari Gruh Nirman Sanstha MaryaditMayuresh Developers | Due Apr 2027, extended 4 mo | — | 11% |
| Arya Business CentreAnaya Developers | Due May 2027, extended 2 yrs 6 mo | — | — |
| Shree Muktai ComplexSamarth Developers | 2 yrs 2 mo late | — | — |
| Sairam ResidencyManoj Harishchandra Kale | 11 mo late | — | — |
| Surya HeightsSuryaputra Developers | Completed | — | 94% |
| Shree Dattatraya ApartmentKalpana Ankush Gopale | Due Jul 2027, extended 4 mo | — | — |
| Time CityRajendra Narawade And Sudhir Narawade | Due Apr 2028, extended 4 mo | — | — |
| Royal ResidencyShree Swami Samarth Developers | Completed | — | 86% |
| Shubham Tarangan Phase IIShubham Vipra Associates | Completed | — | 47% |
| Silver ParkJaihind Properties | Due Dec 2027 | — | — |
| Central PlazaJadhav Civil Project | Completed | — | 13% |
| Sai SavliDeepak Balkrushna Repale | 5 mo late | — | 26% |
| Rajmudra Phase 1 and 2Rajmudra Developers | 4 yrs late | — | 13% |
Nearby: other talukas in Pune
Most active promoters
- Jadhav Civil Project6 projects
- Suryaputra Developers4 projects
- Vizion Construction4 projects
- Dnyaneshwar Mahadu Jadhav Proprietor Of Global Construction3 projects
- Gholap Developers3 projects
- Prime Construction3 projects
- Deepali Buildcon2 projects
- Eknath Bhau Shinde2 projects
- Landmark Associates2 projects
- Nandanvan Developers2 projects
Junnar, in questions
How many projects in Junnar run late?
8 in 10 MahaRERA registrations (130 of 159): their completion date was extended or has passed, data through 15 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Junnar by Deedo. Medians on fewer than 3 deeds are not shown.
Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology
