Deedo IDDL-PUN-JUNNAR8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects153
Registrations159some projects hold several
Completion still due5981 past their date
Median extension4 months52% of registrations extended
Regulatory cases3on 3 projects
8 in 10 registrations run late here
159 MahaRERA registrations in Junnar and the places within it
10 not yet due49 extended, not yet due81 past even the latest date19 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Junnar
153 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Global LuxuriaDnyaneshwar Mahadu Jadhav proprietor of Global Construction | Completed | — | 77% |
| Amol SmrutiSeema Amol Lolage | 4 yrs 2 mo late | — | — |
| B SquareYogesh Vijay Bhide | Completed | — | 76% |
| G.t. RadianVivek Govind Thakkar | 3 yrs 6 mo late | — | — |
| Gajre HeightsSangita Mangesh Joshi | Completed | — | 43% |
| Sindhu Shantaisantosh nathuram navale | 3 yrs 11 mo late | — | 42% |
| Kamal PlazaJadhav Civil Project | Completed | — | 87% |
| Time SquareRnarvade Empire Developers And Associates Pvt Ltd | Completed | — | — |
| VrundavanWagh And Bhor Group | Completed | — | 35% |
| Savera-2Vizion Construction | Completed | — | 75% |
| Umar ResidencyUmar Builders And Developers | Completed | — | — |
| Samrudha ComplexRavi Somjibhai Patel | Completed | — | 95% |
| Gulmohar SocietyNitin Sitaram Kulkarni | Due Apr 2028, extended 4 mo | — | 51% |
| Hallmark SquareYogesh Baban Jadhav proprietor of Hallmark properties | 4 yrs 6 mo late | — | 22% |
| RoyalparkBankar Dugane Associates | 7 yrs 8 mo late | — | 89% |
| Sai Dham - 2Gholap Developers | Completed | — | 95% |
| Radha ClassicRadha Housing | Completed, extended 1 yr 6 mo | — | 33% |
| Gitai Sankul B And C WingGitai Sankul | Completed, extended 3 yrs 6 mo | — | 57% |
| Jayram ResidencySachin Jayram Nalawade | Completed, extended 1 yr 1 mo | — | — |
| Sai Dham - 1Gholap Developers | Completed | — | 88% |
| Manas ResidencyOorjitaa Realtors | Due Dec 2026 | — | — |
| Sonai ParadisePhoenix Buildcon | 3 yrs 8 mo late | — | — |
| Mariyah HeightsSayed Naveed Ahemd | Completed, extended 2 yrs | — | — |
| Arihant ComplexIndraneel Shantaram Tambe | Completed | — | 53% |
| Shree Muktai ComlexSamarth Developers | Completed, extended 9 mo | — | — |
Nearby: other talukas in Pune
Most active promoters
- Jadhav Civil Project6 projects
- Suryaputra Developers4 projects
- Vizion Construction4 projects
- Dnyaneshwar Mahadu Jadhav Proprietor Of Global Construction3 projects
- Gholap Developers3 projects
- Prime Construction3 projects
- Deepali Buildcon2 projects
- Eknath Bhau Shinde2 projects
- Landmark Associates2 projects
- Nandanvan Developers2 projects
Junnar, in questions
How many projects in Junnar run late?
8 in 10 MahaRERA registrations (130 of 159): their completion date was extended or has passed, data through 15 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Junnar by Deedo. Medians on fewer than 3 deeds are not shown.
Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology