8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects153
Registrations159some projects hold several
Completion still due5981 past their date
Median extension4 months52% of registrations extended
Regulatory cases3on 3 projects

8 in 10 registrations run late here

159 MahaRERA registrations in Junnar and the places within it

10 not yet due49 extended, not yet due81 past even the latest date19 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Junnar

153 projects registered with MahaRERA in this taluka and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Global LuxuriaDnyaneshwar Mahadu Jadhav proprietor of Global ConstructionCompleted—77%
Amol SmrutiSeema Amol Lolage4 yrs 2 mo late——
B SquareYogesh Vijay BhideCompleted—76%
G.t. RadianVivek Govind Thakkar3 yrs 6 mo late——
Gajre HeightsSangita Mangesh JoshiCompleted—43%
Sindhu Shantaisantosh nathuram navale3 yrs 11 mo late—42%
Kamal PlazaJadhav Civil ProjectCompleted—87%
Time SquareRnarvade Empire Developers And Associates Pvt LtdCompleted——
VrundavanWagh And Bhor GroupCompleted—35%
Savera-2Vizion ConstructionCompleted—75%
Umar ResidencyUmar Builders And DevelopersCompleted——
Samrudha ComplexRavi Somjibhai PatelCompleted—95%
Gulmohar SocietyNitin Sitaram KulkarniDue Apr 2028, extended 4 mo—51%
Hallmark SquareYogesh Baban Jadhav proprietor of Hallmark properties4 yrs 6 mo late—22%
RoyalparkBankar Dugane Associates7 yrs 8 mo late—89%
Sai Dham - 2Gholap DevelopersCompleted—95%
Radha ClassicRadha HousingCompleted, extended 1 yr 6 mo—33%
Gitai Sankul B And C WingGitai SankulCompleted, extended 3 yrs 6 mo—57%
Jayram ResidencySachin Jayram NalawadeCompleted, extended 1 yr 1 mo——
Sai Dham - 1Gholap DevelopersCompleted—88%
Manas ResidencyOorjitaa RealtorsDue Dec 2026——
Sonai ParadisePhoenix Buildcon3 yrs 8 mo late——
Mariyah HeightsSayed Naveed AhemdCompleted, extended 2 yrs——
Arihant ComplexIndraneel Shantaram TambeCompleted—53%
Shree Muktai ComlexSamarth DevelopersCompleted, extended 9 mo——
Junnar market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Jadhav Civil Project6 projects
  2. Suryaputra Developers4 projects
  3. Vizion Construction4 projects
  4. Dnyaneshwar Mahadu Jadhav Proprietor Of Global Construction3 projects
  5. Gholap Developers3 projects
  6. Prime Construction3 projects
  7. Deepali Buildcon2 projects
  8. Eknath Bhau Shinde2 projects
  9. Landmark Associates2 projects
  10. Nandanvan Developers2 projects

Junnar, in questions

How many projects in Junnar run late?

8 in 10 MahaRERA registrations (130 of 159): their completion date was extended or has passed, data through 15 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Junnar by Deedo. Medians on fewer than 3 deeds are not shown.

Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology