Its promised completion date, Jul 2023, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.

Narayangaon, Pune 412411 · Promoter: Rnarvade Empire Developers And Associates Pvt Ltd

Delivery3 yrs 3 mo past duePromised Jul 2023 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 48 units · as the promoter reported to MahaRERA
Time Square project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Its promised completion date, Jul 2023, has passed and MahaRERA does not show it completed

  • This projectRegistered 9 Sep 2019, completion promised 31 Jul 2023, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100022272
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000222729 Sep 201931 Jul 202331 Jul 2023Rnarvade Empire Developers And Associates Pvt LtdProject page
Documents25

1 document held by Deedo, 24 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardCOMPANY PAN.pdf · uploaded 17 Aug 2019Source

Legal

  • Declaration Form BFORM B.pdf · uploaded 17 Aug 2019Source
  • Legal Title reportSEARCH TITLE.pdf · uploaded 17 Aug 2019Source
  • OtherDeclaration Sec 15.pdf · uploaded 15 Jun 2021Source
  • Other7 12.pdf · uploaded 25 Oct 2021Source
  • OtherLegal Title Report updated_compressed.pdf · uploaded 25 Oct 2021Source
  • Otherform 4.pdf · uploaded 25 Oct 2021Source
Show all 25 documentsShow fewer documents

Migrated

  • 1 PAN CardCOMPANY PAN.pdf · uploaded 17 Aug 2019Source
  • 1 Copy of the legal title reportSEARCH TITLE.pdf · uploaded 17 Aug 2019Source
  • 1 Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 17 Aug 2019Source
  • 1 Building Plan Approval / NA Order for plotted developmentBUILDING LAYOUT.pdf · uploaded 17 Aug 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 17 Aug 2019Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 17 Aug 2019Source
  • 1 Details of encumbrancesENCUMBRANCE.pdf · uploaded 20 Aug 2019Source
  • 1 Proforma of Allotment letterNO AGREEMENT.pdf · uploaded 20 Aug 2019Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 29 Aug 2019Source
  • 1 OtherDeclaration Sec 15.pdf · uploaded 15 Jun 2021Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCompletion Certificate.pdf · uploaded 9 Sep 2021Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 9 Sep 2021Source
  • 2 Other7 12.pdf · uploaded 25 Oct 2021Source
  • 3 OtherLegal Title Report updated_compressed.pdf · uploaded 25 Oct 2021Source
  • 4 Otherform 4.pdf · uploaded 25 Oct 2021Source

Technical

  • DocumentLAYOUT.pdf · uploaded 17 Aug 2019Source
  • DocumentBUILDING LAYOUT.pdf · uploaded 17 Aug 2019Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsSURVEY NO 323 A/SURVEY NO 364/2

As registered with MahaRERA and published on its project page

Project type
Commercial
Status on MahaRERA
Certificate Signed
Unit types
Shop48 units in all
Address
Survey No 323 A/Survey No 364/2, Narayangaon, NarayangaonPIN 412411
Village
Narayangaon, Junnar taluka
Designated bank account
82
Developed in phases
No

Survey, CTS, gat or plot numbers

SURVEY NO 323 A/SURVEY NO 364/2

Boundaries

North
By Cts 323 B
South
By Cts No 322
East
By Road
West
By Cts No 313

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking48 units

0 of 48 units booked (0%), as the promoter reported to MahaRERA

Shop · 48 units
TypeCarpet areaUnitsBooked
Shop10.27 sq m · 111 sq ft40
Shop13.05 sq m · 140 sq ft10
Shop13.5 sq m · 145 sq ft170
Shop13.72 sq m · 148 sq ft40
Shop14.17 sq m · 153 sq ft20
Shop17.08 sq m · 184 sq ft40
Shop18 sq m · 194 sq ft60
Shop18.9 sq m · 203 sq ft10
Show all 15 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Shop21.1 sq m · 227 sq ft10
Shop27 sq m · 291 sq ft20
Shop32.67 sq m · 352 sq ft10
Shop32.69 sq m · 352 sq ft20
Shop36.67 sq m · 395 sq ft10
Shop41.17 sq m · 443 sq ft10
Shop42.03 sq m · 452 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVijaykumar—
Chartered accountantPgmj And Associates—
EngineerSagar Bhivsen Gadge—
OtherAkil Rouf Sayyed—
OtherRnaravde Empire Developers And Associates Pvt Ltd—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology