Erandwana, Pune

Deedo IDDL-PUN-ERANDWANA

5 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects12
Registrations12
Completion still due102 past their date
Median extension4 months33% of registrations extended
Regulatory cases0none on MahaRERA's lists

5 in 10 registrations run late here

12 MahaRERA registrations in Erandwana

6 not yet due4 extended, not yet due2 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Erandwana

12 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
DwarikaAngal & CoDue Sep 2029——
PriyanjaliMadane ConstructionsDue Dec 2028——
Yashashri Poorti Co Op Housing SocietyD&T Properties Unit-5Due Sep 2030——
RatnakarSuvidhasankalp Realtors Private LimitedDue May 2028——
Swojas AasaraSwojas United Constructions LLPDue Jan 2029, extended 4 mo——
All 12 projects →
Erandwana market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Shree Venkatesh Buildcon Pvt Ltd3 projects
  2. Ranjekar Realty Llp2 projects
  3. Angal & Co1 project
  4. Dinesh Shankarrao Madane1 project
  5. D&T Properties Unit-51 project
  6. Kotibhaskar Infrastructures &Developers Pvt.Ltd1 project
  7. Madane Constructions1 project
  8. Suvidhasankalp Realtors Private Limited1 project
  9. Swojas United Constructions LLP1 project
  10. Vikas Bhatewara Ventures1 project

Erandwana, in questions

How many projects in Erandwana run late?

5 in 10 MahaRERA registrations (6 of 12): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Erandwana by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology